0% found this document useful (0 votes)
184 views9 pages

Complete Solved Paper of Cs 605

This document contains the complete solved paper of the CS605 - Software Engineering II final exam from 2010. It includes 36 multiple choice and short answer questions testing knowledge of software engineering processes, quality metrics, requirements management, and CMM levels. Student information fields are included at the top for name, student ID, exam date and center.

Uploaded by

hammad saeed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
184 views9 pages

Complete Solved Paper of Cs 605

This document contains the complete solved paper of the CS605 - Software Engineering II final exam from 2010. It includes 36 multiple choice and short answer questions testing knowledge of software engineering processes, quality metrics, requirements management, and CMM levels. Student information fields are included at the top for name, student ID, exam date and center.

Uploaded by

hammad saeed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

Prepared by Dil-E-Nadan

Campus[psmd01]Samundri
[email protected]

Complete Solved Paper Of CS605- Software Engineering II Finalterm


2010
FINALTERM EXAMINATION
Spring 2010
CS605- Software EngineeringII (Session - 4)
Time: 90 min
Marks: 60

Student Info
StudentID:

Center:

ExamDate:

Question No: 1 ( Marks: 1 ) - Please choose one


In order to measure the design quality, if the frequency of ripple defects is too large, then it means that there is tight
coupling and hence the

► design is maintainable
► design is not maintainable

► design has completed

► none of the given

Question No: 2 ( Marks: 1 ) - Please choose one


We can include following type of data in the database for creating matrix aganst each project except

► name of project

► size of project

► company’s CEO name

► cost of project

Question No: 3 ( Marks: 1 ) - Please choose one


The only reason for an estimate to be unreliable is lack of experience related to the application on the part of the
estimator.

► true

www.virtualinspire.com
Prepared by Dil-E-Nadan
Campus[psmd01]Samundri
[email protected]

► false

Question No: 4 ( Marks: 1 ) - Please choose one


A consideration of software scope must include an evaluation of all external interfaces.

► true
► false

Question No: 5 ( Marks: 1 ) - Please choose one


If an error related to requirements is identified in testing phase, so this error will be considered as an error
in ___________ phase.

► Design

► Code

► Requirement

► Testing

Question No: 6 ( Marks: 1 ) - Please choose one


Usually the performance of the organization change over-night.

► True

► False

Question No: 7 ( Marks: 1 ) - Please choose one


Quality is the compliance of software to implicit and explicit quality factors. Identify the explicit requirement from
the following:

► Maintainability

► Compliance with CMMI

► Ease of use

► Efficiency

Question No: 8 ( Marks: 1 ) - Please choose one


Following are the benefits of conducting review except

www.virtualinspire.com
Prepared by Dil-E-Nadan
Campus[psmd01]Samundri
[email protected]

► Help in finding the size of the project

► Helps in verifying the quality of product

► Help in identifying where improvement is required.


► Helps in identifying the bugs in the work product

Question No: 9 ( Marks: 1 ) - Please choose one


Mean Time To Repair (MTTR) is the

► Time when system remained unable for usage

► Time taken to fix the error

► Time taken to repair the software

► All of the given options are correct.

Question No: 10 ( Marks: 1 ) - Please choose one


Reliability and Safety are same concepts with respect to software quality

► True
► False

Question No: 11 ( Marks: 1 ) - Please choose one


SCM is the requirement of the ________ level(s) of CMM

► First

► Second and later

► Third and later

► Only Second

Question No: 12 ( Marks: 1 ) - Please choose one


We can include following items during configuration item identification:

► User Manuals and Documentations

www.virtualinspire.com
Prepared by Dil-E-Nadan
Campus[psmd01]Samundri
[email protected]

► Source Code

► Software Requirement Specifications

► All of the given choices are correct

Question No: 13 ( Marks: 1 ) - Please choose one


If a new version of a product is released by fixing the bugs in the previous release then it is termed as
_________________
► Product Update

► Product Upgrade

► Defect Removal

► Product Performance

Question No: 14 ( Marks: 1 ) - Please choose one


Every node signifies ___________ version of a release

► one

► two

► three

► four

Question No: 15 ( Marks: 1 ) - Please choose one


The Change Control Authority does not have the rights to permit to bring the change in the software
► True

► False

Question No: 16 ( Marks: 1 ) - Please choose one


Check in and Check out is actually one and the same process with two different names

► True
► False

www.virtualinspire.com
Prepared by Dil-E-Nadan
Campus[psmd01]Samundri
[email protected]

Question No: 17 ( Marks: 1 ) - Please choose one


There could be multiple GUIs to satisfy one requirement

► True

► False

Question No: 18 ( Marks: 1 ) - Please choose one


_____________ is the process of Design recovery. At this stage the documentation of the overall functionality is
created.

► Database Engineering
► Reverse Engineering

► Refactoring
► Forward Engineering

Question No: 19 ( Marks: 1 ) - Please choose one


In code restructuring, we do not change the functionality of the code

► True

► False

Question No: 20 ( Marks: 1 ) - Please choose one


In ______________, new user and technology requirement can also be integrated into the re-engineering effort.

► Backward re-engineering

► Forward re-engineering

► Business Engineering

► Business Process Engineering

Question No: 21 ( Marks: 1 ) - Please choose one


A _____________process is “a set of logically related tasks performed to achieve a defined business outcome”.

www.virtualinspire.com
Prepared by Dil-E-Nadan
Campus[psmd01]Samundri
[email protected]

► Business

► Software

► CMM

► ISO

Question No: 22 ( Marks: 1 ) - Please choose one


Software refactoring is a process in which

► External behavior of the system does not change

► Internal behavior of the system does not change

► Design of the software changes

► Architecture of the software changes

Question No: 23 ( Marks: 1 ) - Please choose one


The formal methods model of software development makes use of mathematical methods to

► define the specification for computer-based systems


► all of the given

► develop defect free computer-based systems

► verify the correctness of computer-based systems

Question No: 24 ( Marks: 1 ) - Please choose one


Which one of the following describes the data and control to be processed, function, performance, constraints,
interfaces, and reliability?

► Product Quality

► Software scope estimation

► Resources requirements

► Time requirements

www.virtualinspire.com
Prepared by Dil-E-Nadan
Campus[psmd01]Samundri
[email protected]

Question No: 25 ( Marks: 1 ) - Please choose one


Which one of the following describes the data and control to be processed, function, performance, constraints,
interfaces, and reliability?

► Resources requirements

► Software scope estimation

► Time requirements

► Product Quality

Question No: 26 ( Marks: 1 ) - Please choose one


The software plan is not a static document, it is frequently adjusted to make the project appear on track to meet all
deadlines and quality targets.
► True
► False

Question No: 27 ( Marks: 1 ) - Please choose one


The projects are classified into following categories except

► New application development

► Reengineering projects

► Concept development projects

► Marketing Development Projects

Question No: 28 ( Marks: 1 ) - Please choose one


The processes at ----------- is focus on continually improving process performance through both incremental and
innovative technological changes/improvements.

► Level 5
► Level 1
► Level 4
► Level 3

Question No: 29 ( Marks: 1 ) - Please choose one

www.virtualinspire.com
Prepared by Dil-E-Nadan
Campus[psmd01]Samundri
[email protected]

Quantitative process-improvement objectives for the organization are established, continually revised to reflect
changing business objectives at -------------.

► Level 3
► Level 2
► Level 5
► Level 1

Question No: 30 ( Marks: 1 ) - Please choose one


Reliability of a software is a

► functional requirement
► non-functional requirement
► Design Requirement
► None of the given

Question No: 31 ( Marks: 2 )


What issues must be included in the review list?

Question No: 32 ( Marks: 2 )


What is meant by requirement management?

Requirement Management is defined as a systematic approach to eliciting, organizing, and documenting


the requirements of the system, and a process that establishes and maintains agreement between the
customer and the project team on the changing requirements of the system.

Question No: 33 ( Marks: 2 )


Give any two advantages of Software CMM?

Question No: 34 ( Marks: 2 )


How can we implemente metrics in small organizations ?

Question No: 35 ( Marks: 3 )


Give in brief any three factors related with operation?

Question No: 36 ( Marks: 3 )


Discuss the hazards those are associated with a computer-based cruise control for an automobile?

www.virtualinspire.com
Prepared by Dil-E-Nadan
Campus[psmd01]Samundri
[email protected]

Question No: 37 ( Marks: 3 )


What would you understand by the conventional numbering of the product release?

Question No: 38 ( Marks: 3 )


Write down the levels of Capability Maturity Model (starting from 0-5)?

Question No: 39 ( Marks: 5 )


What are the risks associated in the migration of a Legacy system to a new system?

Question No: 40 ( Marks: 5 )


How Duplicate Code can cause problem in the maintenance of a program? Explain briefly.