Assignment 2
Assignment 2
Concept phase
Implementation phase
Planning phase
Termination phase
1 point
Arrange the following elements of the Project Cycle in the right order:
A- Project Appraisal
B- Feasibility Analysis
C- Negotiation
D- Project Selection
A-B-C-D
B-A-C-D
B-A-D-C
A-B-D-C
1 point
Which is not a Project Management Maturity Model?
Kerzner’s model
1 point
What is the correct sequence of Project Life Cycle phases?
Engineering aspects
Location
Process
Pricing options
1 point
Project identification is generally done through _______________?
Brainstorming
Questionnaire
Fundamental analysis
Technical analysis
1 point
Which of the following activity is not a part of development phase?
Schematics
Resources
Cash flowing
Procurement
1 point
BCG Matrix is used for?
Project appraisal
Project selection
Project controlling
Project budgeting
1 point
Which of the following is not a brainstorming activity?
Testing
SWOT analysis
1 point
New ventures by fresh entrepreneur/promotor are _____________?
Greenfield projects
Brownfield projects
Conglomerate projects
Concentric projects
You may submit any number of times before the due date. The final submission will be considered for grading.