Gravity Flow System
Gravity Flow System
TAti1ii1~~
:L~iSU~‘~F
201—1374
zo~
I ~O H V~
~c~r.~~nrcj c”~~~’~t’
~
KAND~U~
GRAY rTY-FLo~ WATER SYSTEMS
FOR SMALL COMMUNITIES
BY:
THOMAS D. JORDAN JR.
FIRST PRINTING
1 SEPTEMBER 1980 (1000 COPiES)
UNICEF
Box 1187
KATHMANDUJ NEPAL
TABLE OF CONTENTS
PREFACE
ChaDter 1: INTRODUCTION 2
1.1 Description of Systems 2
1.2 Fundamental Problems 3
1.3 Organization of this Handbook 4
Chapter 2: VILLAGE EVALUATION & FEASIBILITY STUDY 5
2.1 Introduction ‘5
2.2 Population Survey 6
2.3 Village Enthusiasm & Motivation 6
2.4 Current Water Sources 7
2.5 Source Investigation 7
—Springs
-Small streams
-Big streams & rivers
2.6 Flow-measuring Techniques 8
-Bucket & Stopwatch
-V-notch weir
-Velocity-area method
2.7 Safe Yield 13
2.8 Water Quality 13
2.9 Source Development 13
2.10 Water Rights 15
2.11 Local Materials, Labor, & Logistics 15
-Overf1 ow
-Washout
-Partitioned tanks
14.7 Construction 131
-Site selection
-Excavation
-Foundations
-Wall construction
-Plastering
-Floor
-Finished grading
-Maintenance
14.8 Design Example 135
cm = centimeters m = meters
2 = square centimeters m2 = square meters
cm
cm3 = cubic centimeters m3 = cubic meters
kg = kilogram H = head
kg/cm2 = kilograms per square centimeter = at
LPS = liters per seCond (flow) 0 = dlamter
m/sec = meters per second (velocity) ‘ = inches
LPCPD = liters per capita per day ,f’’ = square-root
GI = galvanised iron (pipe)
. water surface of tank
HOP = high-density polyethylene (pipe) (9 atmospheric pressure)
Q = flow
. HGL = Hydraulic Grade Line
ID = inner diameter
00 = outer diameter
CGS = corrugated gal vanised steel
RCC = reinforced concrete
RF = reinforcement
IMPORTANT NOTICE
The pipeline problems worked out as examples in the text and figures
of this handbook were made using a frictional headloss table for HOP pipe
according to DIN (German) specifications. Since ‘the examples were worked
out, a new frictional headloss table was obtained for hOP pipe manufact-
ured to ISI (Indian) specifications, which are the specifications adopted
by\UNICEF for Nepal. The new headloss tables have been included in the
reference tables at the end of this handbook, but the original examDles
have not been re-worked.
—l —
PREFACE
1. INTRODUCTION
This handbook concerns itself with all the knowledge, theory, and
material necessary to survey, design, and construct a coninunity
water supply (CWS) system to meet the drinking water requirements
for rural villages of small-to-
moderate populations. The
systems described herein are
of the gravity—flow type; that
is, the action of gravity is
used to move the water downhill
from a source to the village.
This type of system is shown
schematically in Figure 1—1: a
suitable source is located at
an elevation higher than the
village. An intake structure is
built to collect the water,
which is then piped down to
the village through a buried
pipeline of High-Density
Polyethylene (HOP) pipe. If
needed, a reservoir tank is
built above the village. From
there, the water is distributed
to several public tapstands that
are scattered throughout the
village, via the mainline,
branchlines, and taplines.
Where multiple sources are used,
a collection tank may be built,
and due to the topography of
the land, at certain points
break-pressure tanks may be
required to prevent excessive
pressures from bursting the
HDP pipe. If the source water
is carrying a lot of suspended
particles, a sedimentation tank
may be required to clean the
flow of these.
—3-
1 .2 FUNDAMENTAL PROBLEMS
The construction of a CWS system in rural villages is often beset
by many problems which prolong, frustrate, or even cancel the project.
And even when these initial problems are successfully circumvented
and the project is completed, the system may soon be broken down due
to misuse or unforeseen circumstances.
The technical problems encountered during construction may be
such things as difficult terrain for pipelaying landslides or
erosions which threaten to sweep away tanks, or water sources which
unexpectedly yield less water than counted upon (or even dry up
completely).
These are problems which are often clear and easily comprehended
by the overseer in charge of construction, who can usually plan a
strategy to overcome them.
2.1 INTRODUCTION
The first phase in creation of a CWS system is a visit to the
village by a surveyor, for the purposes of determining the feasibility
of the proposed project. Should he determine that the project is
feasible, the surveyor must then conduct a topographic survey.
This chapter will set forth guidelines for the surveyor to use
when visiting a village on a feasibility study. The next chapter
will present specific details on how to conduct the topographic
survey.
—6—
//
f/i
6~bUND\1E 0F
QU’C-~~U~4
WATE~~E~AL~~~WSWATER TO
5~P ~MTO ~
ft
/1
v’
~P DUQIr~~~45O~4
WHEM WATER TABi-e- ~tN~
LoWE~-ThA~ SPR1)
Discussed below are three simple methods for measuring the flows
of springs and streams. Alway~measure the flow several times, and
calculate an average readilig. Any measurements which are obviously
deviant should be repeated. Question the villagers closely about
seasonal variations in the flow.
Bucket and stopwatch: Spring flows are most conveniently
measuredWy using a iide-mouthed container (of known capacity) and
timing how long it takes to fill up. A large-size biscuit or
kerosene container (capacities of about 18-20 liters), or a bucket,
is usually available in the village. For the most accurate results,
the capacity of the container should be such that it requires at
least 15 seconds to fill (smaller containers, such as one—liter
drinking canteens, should only be used if nothing larger is available).
An ordinary wristwatch (that has a sweep—second hand) can be used
for timings, but it is best in this case if two persons work together:
one concentrating on the wristwatch, the other filling the container.
The flow is calculated:
V-Notch weir: The V-notch weir can be used to measure the flow
of large springs and small streams. This weir has a notch angle of
~çJb, and is reconinended for the normal range of flows encountered in
typical village sources. The surveyor may carry his own weir, or
one can be easily made in the village from a wooden board or a sheet
of tin. The weir is placed as a dam, perpendicular to the flow, with
all the water overflowing in the notch. The stream or drainage
channel above the weir should be straight and unobstructed for a
distance of at least 2 meters. Flow is determined by using a ruler
to measure the depth of water overflowing the notch (measured in
centimeters), which is then read off of the calibration curve shown
in Figure 2-2. The dimensions of a 60° V-notch weir are also shown
in the figure.
Velocity—area method: This method requires more work and is
not as accurate at the V-notch weir, yet for particularly wide
streams it can be easier to use. Measure the surface water velocity
of the stream by timing how long it takes a drifting surface float
(such as a block of wood) to move down a measured length of the
stream (this measured section must be fairly straight and free of
obstacles, for a length of 6-10 times the average water depth).
Measure the cross-sectional area of the stream. The measurements
—11—
‘‘“I
‘---I
3 4 5 ~ 7 8 ~ 10 11 t2 1’, i~ 1 11 11 ia 2~
P (W~TCRDCPTh, CM~
x—1
Y 1.73
—
D~FTI~ AV~.4GE
CROSS S~CTL
FLO4T A~EA OF
STI~EAM 5~CTJO~4
In any case, the surveyor will have to use his own judgement
about the suitability of a source. Villagers will know through
experience if the water of a source is drinkable, therefore they
should be consulted.
UPHILL (STEEF’
SUT STABLE)
CATCIiME1.JT FOR
SOURCB * 1 REQUIRES
~/.i OF ~4LJ-; FOR
SOURCE * 2 REQL.JIRE.5
3M OR WAI_L -
NOTES
I SOURCE * 1 SPRING G 037 LPS ELEV bOOM.
2 SOuRCE *2~5PElNG~022 LP~ ELEV = 998M~.
~ COLLECTIOM TAI~4IC ~ EJ_~V • e~-~ i~
4 5oumc~ AREA ~u~GI_E w/LI-rrLE L.~H1LL CUL-rI-
VATIOP4 OR GRAZIM~3
~ MAINL1P-LE NEEOS i ~M 131 Pl~ CROSSING GIJLLV
G 5URv~.y 8~GuI-J@ SOURCE. *2
Before leaving the village, the surveyor should sit down and
obtain all the information relevant to the following aspects:
- the full proper name of the village, ward number(s), panchayat,
district, and zone;
- name of nearest roadhead, and distance;
3. TOPOGRAPHIC SURVEYING
3.1 INTRODUCTION
This chapter shall present methods of conducting a topographic
survey along a proposed pipeline route. Such a survey can be done
using a theodolite, barometric altimeters, or an Abney hand level.
Each of these methods will be discussed, although the main emphasis
of the chapter shall be on surveying with the Abney level, since
that is the easiest and most—widely used technique.
3,5 DESCRIPTION
The Abney level is hasiccily a square tube (dimensions of about
16 x l,s x 1.5 cm) with an eyepiece at the observer’s end and horizontal
cross—hair at the objective end. Figure 3-1 shows a typical Abney
level. Near the center of the tube is a 45° mirror, ~.hich reflects
half of the line—of—s ght upwards through an aperture in the tube.
Mounted above the aperture is a bubble level with an index mark
etched at its center. The bubble level is affixed to a movable index
arm, which adjusts against scale graduations on a nickel—silver arc.
Some types of Abney levels have interchangable arcs, offering
different types of scales (such as decrees, percent, etc). For the
purpose of tnis handbook, the degree arc is used.
-‘B-
3Er acmew—
FIGURE 34 Tv~IC~-
ABMEY LEVEL
MGWITHTHL~M~
10 use the ~bneY, th~instru~tIs held to the eye and 5jghted on
~ target, ~~nteriflg the ~~sshatragainSt the target. The Index arm
Is then adjusted until the bubble (Visible In th~right half of the
fIe1d0~~~ Is center~against the target and the cress_hair
When correctiY adjusteds the targets the crosS air. and the bubble are
—19—
7-1CM
r
I4O~IZOMTAL
350 9 o
‘~ ~393 © Sire or C~Jie~7,o~JNIC~
I,
—S5~oF61 FoR Gz.L7
s2. —1 —
~9a z U,
l~ -2~ -% w
I ç~
—
I—
E ~Lj
0
20 -23~ —9
F 0
•f0
Q) 4.3 LL)
—~— I 0
NThC~
E G 9~8 —.
~30 +lZ° +~ ~
::,
C
H 120 ® ‘SITE ~ J~E5EYOIR. -I-l-
w
0 -2.° 0 u-
-Ti uJ
> 1 1~2 c~t~
z -J
0)
—5° —z 0~
0)
24 -~ -3
U
C ~ç R’~ 9~9 INTE~C.EPT5 FOOTI qTh -
4V) Z~?- -~ —3
-b L Zob q~,
H ~ m~i (S~L)
30 00 0
2~ —
-26-
4.1 INTRODUCTION
1961 -1971
average
annual PERCENTAGE INCREASE
GEOGRAPHIC AREA growth rate 1O-yrs 15-yrs 20—yrs 25-yrs
Note: All figures derive from the 1952-54, 1961, and 1971 census data.
The 10—25 year growth figures are based upon 1961-1971 average annual
growth rates, computed by C. Johnson.
FIGURE 4-].
POPULATION FORECAST TABLE
-29-
The total water demands for the village at the end of the design
period is the sum of the per capita demand plus special need demands.
Per capita demand is the water required per person of the projected
village population. A per capita demand of 45 litres per person per
day is the present design standard. This figure derives from World
Health Organization (WHO) studies, and includes allowances for
personal washing, drinking, cooking, and a portion of domestic animal
needs.
When a marginal water source is encountered, and the target figure
of 45 LPCPD (liters per capita per day) cannot be met, then one may
go as low as 230 liters per household per day. This figure is based
upon minimal needs, and assumes 8-10 persons per household.
)
-30-
5. TYPES OF SYSTEMS
5.1 INTRODUCTION
There are several types of gravity-flow water systems, each
type being determined by certain design characteristics. These
systems fall into two general catagories: open systems, and closed
ones.
An open system derives from the concept that the taps can be
left open and flowing continuously all day long, and still provide
constant and steady flow. This means that the safe yield of the
source(s) is sufficient enough to supply all tapstands directly,
without requiring a reservoir tank.
A closed system is one where the safe yield of the source
cannot provide continuous flow to all taps, or where the safe yield
is such that a reservoir tank is necessary to store water for peak
demand periods which the source alone could not meet. All tapstands
on the system must have a faucet, either of the self-closing or
manually—operated type.
Both catagories of systems may require break—pressure tanks,
but an open system will never require a reservoir tank. At all
tapstands, regardless of the type of system, a control valve must
be Installed to proportion and regulate the flow between taps.
From these two catagorles, there are five different types of
systems which can be built, as discussed below.
the condition of tne system and the new village water needs will
require a major overhaul of the system, or even construction of an
entire new one.
Additional taps: The need for additional taps can be minimized
by trying to predict in which directions the village is likely to
expand in the future, and locate tapstands accordingly. Although
this anticipation of the future will rarely be easy to make, the
geography of the land around the village will sometimes set limits
on expansion (such as rivers, cliffs, direction of ridges and hills,
etc.).
If additional tapstands are needed, no changes in the pipeline
will be necessary if the villagers are willing to slightly reduce
the flow from the other taps to make water for the new taps. De-
creasing the flow of four tapstands by 20% will allow the addition of
a fifth one to the line. The system designer should indicate in the
design report just where additional tapstands may be added, and what
flow re-adjustments would be necessary. This information should be
in the project file at the LDD office, and also should be discussed
with the village leaders.
Increased water demands: This problem can only be solved if
there is another water source located above the intake or reservoir
level so that the flow from the new source can be added to the
,
Branchpoint tees and/or control valves for the future extension may
be installed at the time of initial construction. The design report
should indicate after how many years it is intended to extend the
system, and the matter discussed with the LDD regional engineer and
village leaders.
—35—
6. HYDRAULIC THEORY
6.1 INTRODUCTION
In this chapter, the basic hydraulic principles that govern the
behavior of gravity-flow water systems will be presented. It will
not be possible to understand this material in a single, cursory
reading, yet full understanding of these concepts is necessary before
any person can properly design such a system. The designer should
read, study, and repeatedly refer back to this chapter until he is
satisfied with his knowledge of these principles.
The next chapter shall discuss special strategies in designing
a pipeline section where there are potential air—blocks.
6.2 ENERGY
To move water, whether moving it uphill, downhill, or horizontally,
requires energy. As Its name implies, in a gravity—flow water system
the source of energy is the action of gravity upon water.
100 centimeters high (1 x 1 x 100 cm) would therefore weigh 100 grams.
The same column 1000 cm high would weigh 1000 grams (1 kilogram). The
area at the base of this column is one square centimeter (cm’) and supports
the entire weight of
9e column. Therefore, the pressure at the base of
this column is 1 kg/cm . The same column 20 2meters high30(2000
a column cm) exerts
m high would
aweigh
pressure
2 kgs,of and
3 kg/cm2 column 43of meters
exert a a pressure high exerts a pressure of
2 kg/cm
4.3 kg/cm2, and so on.
Any person who has ever dived to the bottom of a lake or swirming
pool quickly learned that the water pressure increased as he descended
but that swirmiiing horizontally at a constant depth produced no change
in pressure. This comon experience serves to illustrate a major
principle In hydraulics:
Water pressure at some depth is directly related
to the vertical distance from that depth to the
level of the surface, and is not affected by
any horizontal distances.
Consider the system shown in Figure 6—1 The water pressure at
.
* the pressure exerted by other fluids, such as mercury, oil, etc, can
also be reported as equivalent heads of that fluid. Barometric
pressure, for example, is often measureWli “millimeters of mercury”.
-37-
2
0
J
ki
It can be seen that the water heights in these tubes form a new
line for each new flow through the system. For a constant flow, the
line formed by the water heights will remain steady. The system is now
said to be in namic e uilib turn. The line formed by the water levels
in the tubes is ca e t e rau Ic rade line, cormuonly abbreviated as
HGL. A different flow esta ishes a d fferent dynamic equilibrium,
and a new HGL.
The diameter of the pipe, and the amount of flow through it, determinE
the velocity of the flow*. The greater the flow, the faster the velocity,
and the greater the frictional losses. Likewise, the rougher the surface
of the obstacle, the greater the frictional losses.
Frictional losses are not linear: doubling the flow does not neces-
sarily double the losses: usually, losses are trebled, quadrupled, or
even greater.
Gate valves: Gate valves serve as on/off control valves, for the
purpose of completely cutting off the flow. Generally, they are located
at the outlets of intakes, reservoirs, strategic break—pressure tanks,
and at major branchpoints. They are not recorrrnended (or use in regulating
flow (ie— partially open or closed) since the water will erode the bottom
edge of the gate and result in a leaky valve whenever it is meant to be
closed. Directdon of flow through the valve is unimportant.
flow, velocity, and pipe size are all related by the Equation of Continuity
presented in Technical Appendix A.
-41-
Globe valves: These valves are designed for regulating flow through
the system. They are best located near discharge points, so that it is
easier to measure the flow through the valve. They are generally located
at discharge points in reservoirs, strategic break—pressure tanks, and
at every tapstand*. Direction of flow through a globe valve is important:
there is an arrow stamped on the valve that indicates the proper direction
of flow, and care must be taken to see that the valve is installed correctly.
The frictional headloss tables for both HDP and GI pipe are given
at the end of this book. These headloss factors are never perfectly
accurate since frictional losses are affected by many different factors
which may vary from system to system. For this reason, it is necessary
to always include a margin of safety when plotting the HGL (see Section
6.13).
Example: What are the frictional headlosses in the pipeline
section bilow?
a) 135Om of 32m HDP @ 0.45 LPS:
Frict’l headloss factor = 2.56m/lOOm
1350 x 2.56/100 = 34.6 meters headloss
b) 730m of 2” GI pipe @ 1.30 LPS:
Frict’l headloss factor = 1.84%
730 x 1.84/100 = 13.4 meters headloss
c.) 2075m of Class IV SOrmii HDP @ 1.40 LPS:
Frict’l factor = 3.22%
2075 x 3.22/100 = 67 meters headloss
Frictional headlosses can be rounded off to the nearest 1/2—meter,
or even to the nearest meter.
Frictional headlosses of flows through fittings such as elbows,
reducers, tees, valves, etc, are given as equivalent plpelengths.
The third reach is from Tap # 1 to the end of the 32m HDP pipe
section: 500 meters of pipe. The desired flow in this section is now
only 0.225 LPS (ie— flow for just the remaining single tap).
500m of 32mm HDP @ 0.225 LPS
frict’l factor = 0.78%
500 x 0.78/100 = 4 meters headloss
The HGL at this point is now 17 meters below the static level,
meaning that a total of 17 meters of head has been lost to friction
by the flow between the source and end of this reach.
Iii
lAP * 2
ELEY~O~
~MI~- ~
TAD p4-OW -0 22~LAP,
f’~ FRICTIOt~&LHEDLOS5E5/Iooi~ 1
I(2o~w~ Q’o 0 ~o‘.em
4ooqZ~
I
I 32 MM O7~% 2-56%l
L~ -
The final reach is 280 meters of 20mm HDP pipe, carrying a flow
of 0.225 LPS.
280m of 2Dm HDP @ 0.225 LPS
frict’l factor = 12.0%
280 x 12/100 = 34 meters headloss
The residual head at Tap # 2 Is 9 meters.
Observe that the HGL only changed slope at points of—new pipe sizes
and/or new flows. To allow only the desired 0.225 LPS out of each tap,
globe valves must be Installed in the tap pipeline (tapline) and adjusted
so that precisely the 0.225 LPS comes out of the faucets. When adjusted
like that, the valve for Tap # 1 will be burning off 13 meters of head,
and the valve for Tap # 2 will be burning off 9 meters of head. The effects
of residual heads are discussed in Section 6.13.
positive residual head means that gravity will try to increase tne flow
through the pipe; as flow increases, the frictional headlosses will
decrease tne residual head. The flow will Increase until the residual
h,ead is reduced to zero.
~i~ric
fl(AMPL~
i~m~NATURAL (MAXIMuM)
FLOW THROUGh THE PIPELINE
I.’ 5ECTION SHOWN. WHERE
H’ ~OM
L~ 472 M
PIPE’ CLAS5 III a2MJ.~.HDP.
L
~L’N
(PIPELENGTH.MET~R5) -
THE NATURAL FRICT’L FACTOR
NOT~5: FN’ _______ = 0
2 FREE DI5CHARGE OP FLOW INTO LOWER. ~ 32mm IlbP PIPE 00.URS FOR
4 FLOY,( OF 100 LPS
TAP OPEN
First Reach (Source--Tap)
Q 0.78 LI’S
L 10Dm of 50flin HOP + 15Dm of 32riun HOP
Headlosses= im (5C~iinHDP section) + 1Dm (32m HOP section)
Residual head @ Tap= 14m; Tap f1ow~0.225 LPS
Second Reach (Tap--Tank)
Q= 0.55 LPS
L~35Dm of 32niii HDP
Headloss 13m
Residual head 0 Tank discharge= 3Gm
This residual head at the tank discharge will be exactly burned
off when the control valve at the discharge is adjusted to allow
precisely 0.55 LPS into the tank. At this setting, the equivalent
pipelenqth of the valve is 974m (ie- the length of 32nin HOP pipe
required to burn c’ff exactly 3Gm of head at 0.55 LPS flow).
TAP CLOSED
The equivalent pipeline of the system Is:
10Dm of 5(~iin HOP
50Dm of 32nin HOP
974m of 32rmi HOP (the equivalent plpelength of the valve)
To learn the new discharge flow into the tank, it Is necessary to
calculate the natural flow of the equivalent pipeline (ie— the flow
at which 6Dm of head will be burned off by 10Dm of 50nin HDP + l474m
of 32nin HOP). By trial—and-error calculations and interpolations
from the Frictional Headloss Table, the flow is found to be about
0.575 LPS. At this flow, the headlosses are:
10Dm of 5Dmn HDP @ 0.46 rn/lOOm = 0.46rn
50Dm of 32ITTn HOP @ 4.05 rn/lOOm = 20.25m
974m of 32m HDP equivalent pipelength 0 4.05 rn/lOOm =39.44rn
TOTAL HEADLOSS =60.15m
Thus, when the tap is open, the discharge into the tank will be
0.55 LPS. and when the tap Is closed, the discharge will be slightly
less than 0.575 LPS.
withstand greater pressures, but it is much more expensive than Class III
and therefore should not be used except where pressure requires it (it should
not be used because of more suitable headloss factors).
kg/cm2is (250 meters of head).
61 pipe:
Galvanized Maximum
iron pipe used pressure rating = in25 Nepal
in CWS projects manufactured in India.
61 pipe is used where pressures exceed 100 meters of head, or where proper
burial of the pipeline is not possible. Current LDD policies set limits
on the amount of GI pipe to be used In a project, therefore consultation
with the regional engineer is necessary when a system appears to require a
lot of 61 pipe.
In all the above pressure ratings, for HDP pipe as well as 01 pipe,
there Is a large safety factor. Thus, the above pressures can be safely
exceeded by a few meters, but only when absolutely necessary. In the case
of HOP pipe, the manufacturers state that the working lifetime of the pipe
Is 50 years when It is properly joined, buried, and pressures do not exceed
the class rating. In the case of 61 pIpe, the safety factor is even larger,
but It must be ~pt In mind that the pipe corrodes over the years, reducing
waiP thicknesses and therefore reducing its strength.
-
StATIC
LIMiT OP
UMITOF&LASSIII hOP PIPE.
/
Therefore, as a general
standard design, do not design
any system where the HGL will fall
less than 10 meters above the
ground, except when unavoidable.
Never allow the HGL to go under-
ground at all.
1464. PLOTTED ~R MA%~FLOW
ThED4JSI A conwmgcIOeIop
Figure 6-11 shows the ~ipt SIZES lb KEW IT MINI-
same profile, with pipe sizes MALI-V ICin A3O,’E 6~OUt4D
selected to keep the HGL at PRO9LE.
least 10 meters above the
ground.
FIGURE 6-11
PROPERLY-DES I GNED HGL
-53—
6.18 SUWIATION
This chapter has presented the design methods needed to select
pipe sizes and classes, and how to arrange the pipe to keep the HGL
within acceptable limits above the ground profile. One more final con-
sideration, that of air—blocks, must be discussed. This will be
done in Chapter 7; and then Chapter 8 will present the specific
procedures for turning a topographic survey into a properly designed
- system.
—54-
7.1 INTRODUCTION
This chapter considers the details of determining whether or not a
pipeline is likely to be affected by trapped pockets of air which could
interfere with the flow. If the designer determines that his system
is a likely victim of air-blocks, he can then refer to Technical Appendix B
for the analysis and procedures needed to deal with these air—blocks.
SOuRCE
STAnC
SQEATEQ ~n1Al~4
10 A%ETffRS
5OU~
7.4 AIR-VALVES
Mrvalves provided by UNICEF are sturdy devices, and operate
automatically. Maximum pressure rating is 60 meters of head. Details
of installation are shown in Figure 7—3.
—56—
VALVE
• W4”~’V’El ~puc~
1 64 5MORT MI~PL~
• I”~3Zmm. 64/KOP
BRASS UNION
FIGURE 7-3
DETAILS OF AIR-VALVE & INSTALLATION
7.6 WASHOUTS
Over a period of time, suspended particles carried in the flow will
tend to settle out, particularly at low points in the pipeline or where
the flows are low enough so that the flow velocity drops below 0,7 meters/
second. Reservoirs usually allow most of these particles to settle,
but pipeline sections upstream from the reservoir do not benefit from
this. Break—pressure tanks do not allow any sedimentation to occur,
since flows through these are extremely turbulent.
Washouts should be located at the bottom points of major U—profiles,
especially those upstream from the reservoir tank. The number of washouts
in a system depends upon the type of source (a stream yields more suspended
materials than a spring), whether or not there is a sedimentation tank and/or
reservoir, and the velocity of flow through the pipeline.
The washout pipes should
be of the same size as the
pipeline at that point. Endcap—
type washouts will require that
the pipeline will be completely
drained before the end—cap can
be replaced (since it is impos-
sible to put it back on while
there is water gushing out of
it), which is not so with a
washout that has a gate valve
(a globe valve is definately
not suited for this type of
work). ~Handles should be
removed and valves well buried
to discourage tapering.
Endcaps should be torqued
lightly with a wrench (so
that they cannot be removed
by hand) but not extremely
tightly, since they will
tend to rust onto the pipe
and be very difficult to
remove at a later time. Figure 7—5 shows some washout designs.
-58-
8. PIPELINE DESIGN
~l INTRODUCTION
The concepts of hydraulic theory, descriptions of various factors
which influence flow, techniques for determining pressures and the HGL,
have all been presented so far. In this chapter, all of it will be
brought together to show how it is practically applied in the design
of a real system.
The pipeline design phase begins with the graphic plotting of the
topographic survey (from the initial survey of the system) and ends
when all sections of the pipeline (Ie— mainline, sourcelines, branch—
lines, and taplines) have been designed in their final form. Blueprints
are then made of the design.
This chapter will present standards and guidelines for preparing the
pipeline drawings, example designs for mainlines, branchlines, source
collection lines (ie- for systems with multiple sources), and a pIpeline
section of combination pipe sizes.
-
2
1
ormacr. ZC4E
~rR:
I
~tft
•1
~TE:
I
DESIGN ~VI0N
I
~4iLY DEMAND
1
VERTICAL. i-CM -
~7 800
9 2
____ ___ I
PtPELENGTH (MET~)
5~T~
MLRVAT10N
FIGURE 8,2
PORTIoN OF SAMPLE DESIGN SHOWING PRQFILE AXES
- 60-
General plan view & key plan: In addition to the profile design,
blueprints should be made of the general plan of the system, which shows
the rough layout of the system, with village landmarks indicated. A key
plan of the system is also made, showing the relative arrangements of tanks,
control valves, branchlines, tapstands, etc. An example is shown in
Figure 8—3.
NOTE: Since these design examples were worked out, new frictional headloss
tables for HDP pipe were obtained. The new tables are now in the back
of this book, and are not the ones referred to in the following examples.
When designing the pipeline, the designer can begin at the source
and plot his way downstream, or begin at the end and plot his way
upstream, or begin at the ends and plot towards the middle, depending
upon his intuitive feelings. With experience, he will develop more
intuition at where to best begin. In this example, however, plotting will
begin at the source and proceed downstream.
Reservoir calculations:
EOUPCE #2
SOaLE# I
r*~ac,
TAP* 1
Ix’
~t-ICE POST
54-I’VA TmMPLE
COLLECTION T4NIC,
VALVE BOX
~2o
TAD 4*‘5
NOTES:
1 ALL PIPE CLASS lit ‘lOP, SIZE IN MM
2- ALL cON1fl)I~ VALVES SHOWN ARE SATE VALVES OP COQRESPOt-’C)ING PIPE SIZES
a sma. DE5ISNS FOR LNThKES. COLLECTION TANK, RESEEvOIQ, E
4 VAL~VE6OXOETAIL.5
pressure tank #2 BT #2
A third break-pressure tank must be 60 meters lower than BT #2,
which puts it at an elevation of 84Dm, between Taps #2 and #3.
The next break-pressure tank (BT #4) must be 60 meters lower than
ST #3, which puts it at an elevation of 78Dm, between Taps #3 and #4.
Consulting the HOP Frictional Headloss Table (at the back of this
Handbook) for a flow of 1.35 J..PS, it is seen that the headloss factor
of 32mm HDP pipe is too high (l8.15%)while that of SDrmn HDP pipe Is too
low(2.08%,). Thus, a combination of both of these pipe sizes is needed
to produce exactly the desired headloss. Calculations* indicate the
following lengths are needed:
243m of 5Dm HDP 9 2.08% creates Sm of headloss
137m of 32rimi HDP 9 18.15% creates 25m of headloss
Since there are no tapstands along this reach, there is no reason why
the pipe must flow full. Select the smallest size that will allow the
design flow through:
32mm HOP is the smallest pipe size that has a frictional factor less
than 25%, so this is the pipe size to be used. Since there is no need
to maintain pressure in the pipeline, the pipe is allowed to discharge
freely into ST #2. Gravity will drain the line faster than it will fill,
so it wont flow full.
This reach will require 53Dm of Class III pipe and 85Dm of Class IV
pipe. Once again, combination pipe sizes are required. Class III 50mm
HOP pipe will be used for the entire Class III length:
The only pipe size which gives a close frictional factor is 32mm HDP:
A combination of 32nrn HDP and 2Dniii HDP pipe sizes are used:
In this last reach, it can be seen on the profile that the final
l6ni of 32mm HOP pipe will be exposed to a static pressure greater than
6Dm of head. However, the maximum static pressure on this pipe would
only be about 66m of head, which is a tolerable amount. However, the
designer may also use Class IV 32niii HOP for some or all of this reach, or
install another break-pressure tank. If he is not sure, the designer
should consult with the LOD regional engineer.
Final Check
LII
I-
III
FIGURE 8—5
DESIGN EXAMPLE: BRANCHLINE
must be long enough so that the sum of the headloss of each is equal to
the total desired headloss. Refer to Figure 8-7:
Since the total pipelength, design flow, and desired headloss are
all known, the lengths of the two pipe sizes can be determined by the
following equation:
HDP EMDCAP
A HEa&TtDSMALL
APP2~XIMATE_f4f~j.O55:
H - 349 ~ ~A4tfl’ QH HEADt.0S5
zFLOW CM)
(1P5)
FIGURE 8—9
FRICTIoNAL DIFFUSER
FIGURE 8-10
INSTALLATION OF DIFFUSER
—75—
Q 0 225L~PSI
LI~O4~
—1
>
C
r REACH ® ) ® © ®
-4 FLOW P4P Lo~43r~lPt P~ FRICT ~ HEAD H6I. c~’ E1$VATION 146L ~ RESIDUAL
1•11 -n (LP5) Cm) 5IZE F,~1OR LC~ STAT1ONI WSr4F1ONU 5TATICt’III }IEADOF5TA-
5t~TlON ~TAi1ON
C) I IT
~ C
m ~ INTAI~.f ~S~~lR 020 i300 31MM — - — 905 —
Cl) lii
0) 00 RES T/W~1 i i25 g~ ,m~i 1.Llr/. 12/,4 905 ~5 9 -4
0~.
I-’
TAP# 1 Bpi- 0 90 230 50MM 0.997. 2fl% ~93 ~8o 991 11 IIGI. REDUCED ID 9~0M
>(
BPi~ JI 090 200 50M/,4 099% 21,\ 88o 8G5 ~79 13
-D
I-
‘ii
Ji J2 a 4~ ~350 32MM 2.56~~ 9M ZSi ‘835 892 47
,J2 T2 0225 i30 20MM I2.0~ 16M 9Z2 830 866 36 0 K
J3 T4 0225 190 2OM,4~ 1W7. 22/4 ‘85~~ 765 g.3Ut GO MEW F~T’L DlFF~ER
1OTAL = 4310 M.
-77—
9.1 INTRODUCTION
Once the profile has been plotted and the final pipeline sizing has
been approved, the designer enters the next phase of planning the project:
the extensive designing of the system components (such as intakes,
reservoir tank, break-pressure tanks, tapstands, etc) and preparing the
detailed estimates of material, labor, and money that will be required
to Implement the project.
In the past, most CWS projects in Nepal have been surveyed, designed,
and constructed by the same person. This allowed for a fairly Informal
manner of designing a system, since the actual construction overseer was
intlutately familiar with th. thoughts of the designer~ Detailed plans
were not so necessary, as long as he kept the rough design notes and
calculations that he had made.
However, there is now an Increasing trend in Nepal towards turning
over the completed project design to a fresh person who will be the one
who oversees Its construction. In these cases, the overseer cannot
get by with just an estimate sheet and a few cryptic notes in an
unfamiliar format. Designers are now required to be more professional,
and their designs more detailed, so that a person unfamiliar with the
project can take over with minimal loss of information. Unless the
designer specifically details just how he Intended the system to be
constructed, the overseer cannot be expected to build the system
according to the designer’s materials and cost estimate.
Because of the knowledge and experience that is building up,
100 will soon be able to create standardized designs for most components
of a system. Such standardized designs will detail plan specifications,
material requirements, labor estimates, etc, and will greatly reduce the
task of the designer. However, certain components of the system, such as
intakes, will always have to be “custom-designed” for each individual
system. Therefore, the designer Is still required to develop a clear,
professional technique for passing his ideas along to the overseer.
To PIPE FITTIN6S
~iL-
0 MI,• 5W CJ~3~
~ ~o3m.’I HOP (~,L4o,,,) ç~3mm ~ (r~pi)
~L~mIfl (T~pa)
~L
~-‘8oot~-’8Q~l~’ G1 (~Tfl’~
I~7~ OThn~~~ET~ ~
~L-?~° %
tI~J-)&~O~ ~ ~1~Et ~ ~
(5Orr~.n ~Et E~\TY~~t~
tlt
1-IOoo ~-i~o c~’~s
~ ~ 5o,~3arnrn 1tc~UC.E~c
FIGURE 9-1
EXAMPLE PIPELINE ESTIMATES
~.4C*~F1LLWRN GRA~ L.
~ S1DNE TUE”
SEAL W~TIICONCWETE SLAB 12CM 7NI~I
FIGURE 9—2
EXAMPLE ROUGH—DESIGN PLAN
-80-
&~t.3~
m~aniy @~‘i mortar
E5~T%FjP,tES PER SIUJGLE TRN~z
OF 11~50l’4~.’1
35”~ ~ =
2 ~.
~00 ‘J~ =
1c~.~o•~
S0~, mor~c~r 0-
TAI~S~i.
Efl~-PR~5SURE ~Z ~~
FIGURE 9—3
EXAMPLE MASONRY CALCULATIONS
~ 6~ c~T-T1N6S
FIGURE 9—4
EXAMPLE GI PIPE ARRANGEMENT & ESTIMATE
-82-
9.12 SUI’V1ARY
It Is emphasized once again that the designer must very carefully
prepare accurate and clear notes of his designs, so that the overseer may
easily understand how the project Is envisioned.
Each of the above sections will be individually discussed in some of
the following chapters, so that better Ideas of the materials required
can be had. A table of estimates can be found in REFERENCE TABLE VIII
at the end of this handbook.
-83-
10.1 INTRODUCTION
No other phase of a CWS project is likely to consume so much of the
labor, or run into more difficulties, than the construction of the
pipeline. Difficult terrain, all too comon in the rugged countryside of
Nepal, can prolong this phase far beyond what would resonably be expected
which drains away village enthusiasm, which in turn prolongs the work even
more. Motivating the villagers is a major aspect of the overseer’s job.
It Is important, therefore, that the pipeline work be done properly
the first time. To have to locate some internal blockage that is the
result of carelessness, or to have to rejoin pipe already buried, or to
have to redig the trenchline because of erosion problems which could have
been foreseen, are all discouraging tasks.
Although the above problems are not completely avoidable, they can
be minimized. This chapter shall deal with the proper technical
procedures for constructing the pipeline, and will also discuss some
typical problems that experienced CWS overseers in Nepal have been
confronted with, and how they overcame such difficulties.
There will be high initial enthusiasm of the workers for the first
few days or weeks of digging. The work force during this time will never
be bigger, nor will the villagers ever work so hard. It is a good time
to tackle the most difficult portions of the trenchline. Try to avoid
anything which will slow down the work rate (such as lack of materials,
or scheduling work just before major holidays, etc).
Layin9 the pipe as continuously as possible is best. With time
and rainfall, open trenches will fill in, requiring them to be cleaned
out again before laying the pipe. Digging the trenchline one coil—
length at a time is good, laying the pipe down and then immediately
burying it. A steady rate of completing the pipeline keeps the enthusiasm
high.
The division of work will usually mandate that each villager, or
household, or ward, is responsible for digging a certain length of
mainline, as well as all of their own particular branchline or taplines.
If possible, get the entire village to 1ne
dig dug.
the mainline first, before
having the individual sections of pipel
From the very beginning, establish standards and procedures that
must be followed. Getting the trenchilne consistantly dug to the
proper depth is easiest i-F the overseer insists on it being so before
putting down any pipe in it. Once this routine is established, and
firmly maintained, there will be less problems later on.
The pIp~lineshould ideally follow the same route that the original
survey was conducted along. However, it is not unusual to have to make
detours due to Impassable rock areas, land erosions, or because of an
original survey along an impractical route. When such re—routing is
necessary, the overseer must re—survey the new section to determine how
it will affect the HGL of the system, and to see whether additional pipe
is necessary.
The pipeline should be kept as far away from erodible points as
possible: landslide areas, gullies, streams or riverbanks, etc. When
passing through a terrace, keep the trenchline “inside” (as close to
the back of the terrace as possible), and when cutting down the faces
of terraces, run the trenchline diagonally across the face (refer to
Figure 10-2). Motor roads should be crossed perpendicularly and the
trench dug as deep as possible up to 150 cm.
Due to hard, rocky ground along some sections, it will not be
possible to always get the trench 100 cm deep. The overseer should
try to learn what sort of traffic can be expected to walk over the
pipeline (human, animal, farming, etc), how vulnerable the section will
be to erosion, and from this information he should decide if the soil
cover will be adequate. If nor, it will be necessary to substitute
GI pipe along that section. Ideally, the surveyor has already determined
all the places where GI pipe will be needed, but practically speaking
there will be sections, not visible from a surface walkover, where
additional CI pipe will be needed.
When crossing landslides, gullies, and/or streams, a suspended
pipeline may be necessary. Refer to Section 10.11 and Technical
Appendix E for further discussion of these special problems.
Experience advises digging the trenchline in sections equal to
the length of the coil of pipe to be buried in it. Each worker is
assigned a three—meter length of the trench to dig to the proper depth
(a villager can typically dig this length in soft,easy soil in one day,
or two days if the ground is harder). Pick-axes and crowbars that are
provided by the government are not individually owned by the villagers,
but should be moved up and down along the trenchline to be used where
needed.
The trenchline should be free of all sharp rocks which can cut
into the HDP pipe (after the pipe is laid it tends to contract, which
can force it to kink around sharp stones). When the entire section is
dug, it should be inspected along its full length by the overseer
before he allows the pipe to be uncoiled and laid.
-87-
* the most coninon internal blockages are caused by the wooden plugs that
some HOP manufacturers use to seal the ends of the pipes. These plugs
sometimes get forced into the pipe.
-89-
10.6 BACKFILLING
Backfill-ing the trench should be done as soon as the pipe has been
laid, to minimize exposure to sun and curious villagers, both of which
are detrimental to the pipe. Ideally, the
backfill should be screened and compacted
in 10 cm layers, but practically speaking
this is difficult to get the villagers to
do. The chief concerns of backfilling
should be to prevent any organic materials
(such as leaves, sticks, bushes, etc)
from being used, and prevent rocks and
stones From being dumped directly on the
pipeline (after the pipe has been covered
with about 50 cm, it is allowable to use
rocks in the backfill). Because the
backfill will tend to settle, the dirt
should be mounded up over the trenchline
to compensate, as in Figure 10—5.
When the trench is less than 100 cm deep, the pipe should be
bedded on sand, and further covered by 20 cm more of sand. On this,
a reinforced-concrete (RCC) slab 10 cm thick shoula be poured. Once
the slab has hardened, backfilling procedes as above. Refer to
Chapter 19.12 for details of RCC slabs. Figure 10—6 illustrates
backfilling across a road.
Steep slopes: Where the trench cuts down a steep incline, the
backfill is vulnerable to easy erosion by rainfall, which will tend to
wash all backfill to the bottom of the slope. Facing the trench with
stone, as shown in Figure 10—8, will
help to protect the backfill.
0
BRANCH POINT
PIPELINE
2tIANeE 11.1 PIPeSZI
- at all branchpoints;
— at all reducers (changes of pipe sizes);
- changes in pipeline direction;
- every 200 meters in open terrain, 50 meters in jungle.
—93—
A record of each marker should be kept, a copy with the villagers and
a copy for the LDD project file.
Cutting: CI pipe is cut using a hacksaw, and the rough edges are
trimed with a flat file. Use of oil durirg the cutting will help prolong
the life of the hacksaw blades. If machine oil is not available, then
cooking oil is an acceptable alternative. Even water Is better than
nothing.
Threading: This is done using adjustable pipethreaders. Although
it Is sometimes possible to make the threads with a single cut, It is
recomended that they be made by a series of shallow cuts, adjusting the
die teeth to make a deeper cut each time. This technique will prolong
the life of the die teeth. Lubricating oil is absolutely necessary and
should be used extravagantly.
Even if the pipe has already been cut and threaded in a workshop,
it is an advisable practice to bring pipethreaders, extra die teeth,
and a pipe vise out to the project site, since inevitably there will be
some threads which are damaged and must be cut anew.
Discussion with the villagers will give an idea how extensive the run-off
is. Narrow, deep gullies can be crossed by a span of CI pipe above the
bottom of the gully, clear of the maximum flood level and anchored in the
banks of the gully (similar to the crossing shown in Figure 10—12).
Broader gullies should be crossed by GI pipe buried as best as possible,
and anchored down using drystone masonry or gabions,as shown in Figure 10—11.
Refer to Technical Appendix H for information on gabions.
-96-
Heavy animals such as cows and water buffalos can crush or crimp the
HOP pipe if they happen to step directly on it. Open trenchlines,
expeclally along a cowpath, pose a serious danger to these animals, since
they can easily stumble into it and break a limb (some animals have even
broken their necks and died, resulting in a serious loss for some family).
Many times this has led to excessive amounts of crimping in the pipe,
requiring a lot of lost pipe and much labor re—joining it.
- 99-
11.1 INTRODUCTIQN
The first point of flow in a water system is at the source, where
water is collected at an Intake and funneled into the pipeline. This
chapter will discuss various types of intake works, such as spring and
stream intakes, dams, source protection, etc.
Due to the uniqueness of a source, there never will be a standard
design that can be universally built for every system. However, the
intake works should incorporate standard design features, which allow
for adequate control of the water, opportunities for sedimentation,
and prevention of further contamination. These design features will be
the basic theme of this chapter. It is up to the designer to incorporate
them into his plan for the intake works. The construction overseer must
also be aware of these principles, so that he can make modifications in the
event of unforeseen problems.
The fundamental purpose of the intake works is to collect water
from one or several points and focus this flow at a single point: the
entrance to the pipeline. If the water is dirty, it must be allowed
to sit relatively undisturbed for a period of time. The water must
be protected as much as possible against further contamination
(from rain run—off, grazing animals, and curious villagers). And it
must be built in such a way to last for the lifetime of the system.
The number of possible ways to design the intake for a source is
infinite, influenced by factors such as available materials, source flow,
flood levels, ground stability, topography of the area, etc. This chapter
will present several different designs, all of which have been successfully
used in the past, and from which the designer can modify and develop
a suitable intake for his own system.
The next chapter will present the technical details of sedimentation
tanks, which may be required by silty sources such as streams.
I’o
~0
of an Intake wall.
FIGURE 11-1
FOUNDATION OF INTAKE TANK
-lot-
11.5 SCREENING
Suspended particles in the flow can add to the wear and tear on the
HOP pipe, so it is desirable to eliminate such particles as much as possible.
Screening can remove a lot of
these particles, and sedimentation
removes much of the remainder.
OQY- STONE
There should be at least
two screening points in the flow:
a coarse filter to remove larger
floating and suspended debris, and
a fine—mesh screened intake over
the pipe end.
11.6 SEDIMENTATION
Sedimentation is the process whereby tne water is allowed to sit
relatively undisturbed for several hours. In the resulting lack of
turbulence, the finer suspended particles sink and settle out of the
water. Since the chief source of turbulence in water is due to the
velocity of the flow, then the slower the flow through the sedimentation
chamber, the more effective the sedimentation process.
The size (capacity) of the chamber depends upon the type of source,
the amount of flow, and whether or not there Is a reservoir tank further
downstream. Sedimentation requirements may be nothing more than a small
chamber in the intake structure, or may be a large, separate tank (such
tanks are discussed In the next chapter).
-103-
11.9 ROOFING
The roofing on the intake structures must be secure enough to prevent
curious people from interfering with them, and should seal the source
off against any further contamination from surface run—off of rain,
grazing animals, leaves, etc. Accessways are required so that the intake
can be cleaned and repair work performed; an opening to allow a man in
should be at least 60 cm square.
Common roofing schemes in Nepal are:
Slate roofing: constructed by the villagers, If slate Is locally
available. Requires a lot of wood for beams and rafters.
CGS roofing: corrugated galvanized steel roofing sheets, nominal
size 3’ x 10’, effective size 70cm x 320cm. Refer to Technical
Appendix F
-105-
ONION
~RT
FJGu~11-6 Tv~ic~
WmEI Pi~i~
—106-
above ground level. Dirt should be mounded against the tank walls so that
water will be turned away, and the source should have a drainage ditch dug
around its uphill side. This channel should be deep, and can be lined
with dry-stone masonry. Each year, particularly just before the monsoon
season, it should be cleared of accumulated debris.
—107-
by the distances and elevations between the sources. Flow from higher
sources can be piped directly into lower sources, or each source may
have its own individual pipeline to a single collection tank or
-108-
The important concepts that must be kept in mind when designing dams
are as follows:
- when water is backed up to the maximum flood level , It must not
flood the surrounding land;
-log-
WI CEMTlM~1~R5
I I 100 I~° I
4C1 ~
FIGURE 11—10
MASONRY DAM DETAILS
-110—
FLOOD SPIL.LWAY
(3”6I ~$PU~
MA%.
FLOOD 5P~LLN~Y.
IN _
_____________ W45$0U1
150
GI PID~3A5 ~ERFL.0w5
OUTLET PIPE
l~CTES:
1. 0’.I~QFL.0Y~• 3”GI X 1~CM ~ M4’C FLOW • 15 LPS
W.~HOUTS • 3” 01 X 200 CM w/ ENOCAD J ~R EACH.
2. b~64SHOUT8W4~ISTes LOCATED DI~CT1~V
BELOW l~ffA~I.
FIGURE 11—11
BURLAP (JUTE) BAG EMBANKMENT
—Ill—
-SI
MaMUM o~Qaa~t This overflow will be confined
to a special channel, which will
carry the excess flows away without
causing erosion problems. The
O/ERFLOW CAPCITY OF SPILLWAVS spillways should have masonry
(Peg 30cm. OF 14 wing—walls, and a bed of dry—
_______ _______ stone masonry to absorb the
D
________ b LPG
________ hard flow currents of the
S 48~ 10414 overflowing water. Figure
nfl 11-12 presents the overflow
15fl7j 10754 capacity of spillways of
different depths. For example,
a spillway 20 cm deep and 90 cm
FIGURE 11-12 long can handle an overflow
SPILLWAY DESIGN of more than 124 LPS.
—112—
bRY~
~LTU~
L_WASMOUT3
FIGURE 11-13
EXAMPLE INTAKE DESIGNS
—114-
12.1 INTRODUCTION
Water from stream sources and large springs typically contains
suspended particles, since the turbulence of large flows can churn up
clay, silt, sand, and even small pieces of gravel. Such particles carried
in the flow can give the water a dirty, unappetizing appearance and taste,
and also add substantially to the erosion of the HOP pipe. If, however,
the water Is allowed to sit relatively quietly In a tank for some period of
time, much of these suspended particles may sink and settle out to the
bottom of the tank. This process is called sedimentation, and is
accomplished in sedimentation tanks, specially designed for this purpose.
Seaimentation tanks should be built for all systems using stream
sources, and for those spring sources where the water is visibly dirty or
cloudy. This chapter will present the technical procedures for designing
adequate sedimentation facilities for a system.
12.4 CAPACITY
When the detention time has been selected, the required capacity of
the sedirrentation tank can be calculated:
* however, the Intake should have a settling chamber with the prescribed
screening, as dIscussed--tn-Chapter 11 .5 & 11.6
-116—
DIM~N5~ONSIN ~NT1MeT~p5.
OU1~T
FIGURE 12—1
RECOMMENDED SEDIMENTATION TANK
—117—
DIMENSIONS IN CENTIMETERS
STONE OR
WIRE MtSfl
5, 25 , 25 ~
I- •~~‘ •1~~ --
WATER
20
S
‘so
30
13.1 INTRODUCTION
The function of a break—pressure tank is to allow the flow to
discharge into the atmosphere, thereby reducing its hydrostatic pressure
to zero, and establishing a new static level. Strategic placing of
break—pressure tanks can minimize the amount of Class IV and GI pipe
which must be used in a system (except where there are U-profiles).
In Chapter 8.3, the design example of the mainline included four
break-pressure tanks, and discussion was presented about the various
strategies to locate them.
It is anticipated that shortly the LDD office will have developed
standardized designs for break-pressure tanks, complete with detailed
estimate lists. Therefore, this chapter will present just the basic
design principles and characteristics of such tanks which have been
successfully constructed in Nepal.
[~EN~Ic*~S IN C.Et’&1~MSTER
A BRASS ~6ON
8 61 BL~IW
C 6~P(PR
o cop4T~B~I~~IE
a ci cs~
~ FLAT ~4LVE
6 UMEQU4I~ ci
FIGURE 13—2
GI PIPE ARRANGEMENTS FOR BPTs
-122—
The rate of flow out of the hOP break-pressure tank will be dependant
upon the head of water acting at the outlet pipe. This head will be
limitea by the height of the snorkel overflow tee above the outlet pipe.
Consequently, the huP break-pressure tank should be at least one meter
below the overflow tee, i.e. about 90cm below ground level.
-124-
14.1 INTRODUCTION
The construction of the reservoir tank will be the most visible
effort of the entire system. It will require the coordinated tasks
of dozens of people, ranging from the masons who lay the stone to
the assistants who mix cement, to the men, women (and sometimes even
children) who collect stones from the fields or porter sand up from
the rivers. When completed, the reservoir becomes a public monument
of the village and a source of pride to the villagers, especially if
the project Is considered a successful one.
When It comes to designing the reservoir tank, the most common
attitude of the villagers is “the bigger the betterY’. While this is
an understandable idea, there is no point in building any tank so
large that the source will never be able to fill it up during the
overnight re-filling period. The storage caffiacity of the reservoir
is actually determined by the projected village water needs (as dis-
cussed In Chapter 4) and the safe yield of the source. The actual
dimensions of the tank are determined by its capacity, the conditions
at the site selected, and rules of economical design.
This chapter will present all the procedures and knowledge that
is necessary to design and construct practical reservoir tanks. At
the end of the chapter is an example design.
14.3 CAPACITY
To determine how large a reservoir tank must be— it is necessary to
calculate how much water is demanded at various times during the day,
and compare this to how much water is yielded by the source for those
same time periods. The difference will either mean that water will be
drawn out of the reservoir or will flow Into the reservoir.
The maximum size of a tank should not be greater than needed to
store the water yielded by the source during the night. It is possible to
sometimes design a tank to take advantage of the higher yields during the
monsoon season if the dry-season safe yield is not enough.
Schedule 1
6:00 AM - 8:00 AM 30% of total daily water need
8~00~AM- 4~00PM 40% “ “
Schedule 2*
5:00 AM - 7:00 AM 10% of total daily water need
7:00 AN —11:00 AN 25% ‘ ‘ “
11 ~OOAM — 1 •o~PM 35% “ “ “
Since the source is not large enough to supply more than two of the
tapstands by itself, a reservoir tank Is required. Using the two demand
schedules, the following water demands are calculated:
Schedule 2
5 AM - 7 AM (2 hrs, 10%) 3240 1800 +1440 (tank overflows)
7 AM - 11 AM (4 hrs, 25%) 6480 4500 +1980 ( 0
11 AJ’~ — 1 PM 2 hrs, 35%) 3240 6300 -3060 (water withdrawn)
1 PM - 5 PM 4 hrs, 20%) 6480 3600 +2880 (tank refilling)
5 PM - 7 PM (2 hrs, 10%) 3240 1800 +1440 (tank overflows)
Largest deficiency = 3060 liters
Schedule 2
5 AM - 7 AM (2 hrs, 10%) 3240 3510 - 270 (water withdrawn)
7 AM - 11 AM (4 hrs, 25%) 6480 8775 -2295 ( ‘ “
14.4 SHAPE
When the required capacity of the reservoir tank has been cttcu ~ted,
it is then time to begin determining the shape and dimensions of th tank.
This is usually a compromise procedure that may have to be repeated two
or three times before the optimum design is discovered.
All other factors being equal, the most economical tank shape is
circular, then nearly-circular, then square, and then rectangular. For
ease of construction, certain shapes are easier than others:
Circular tanks: The most economical shape to use, but not easy to
construct, especially for small diameters.
Octagonal (8-sided) tanks: The best shape to use, but not easy to
construct for diameters less than 2! meters (or capacities smaller
than 3200 liters).
Hexagonal (6-sided) tanks: Good for tanks between 1700—3200 liters
(diameters not less than 2 meters).
Square tanks: Thts is the traditional shape, and easiest to
construct for small capacities (such as mini—tanks, break-pressure tanks,
etc).
Rectangular tanks: The least-economical shape, especially as one
side becomes much longer than the other. However, due to physical
constraints of the site, it may be necessary to use this shape. Keeping
it as nearly square—shaped as possible will make a more economical design.
Special note for CGS—roofed tanks: When a square or rectangular
tank Is to be roofed with CGS, It is easier to slightly adjust the
dimensions of the tank so that it Is neatly covered by the sheets
(such as “5 sheets wide by 1! sheets long”). This helps to minimize
the amount of CGS sheet cutting, which is a relatively difficult task.
For the multi—sided tanks this is not so easy to do, but should still
be kept in mind.
Figure 14—1 is a table of these various tank shapes, giving the
simple mathmatical equations for determining their dimensions once
capacity and water depth have been selected.
R= 0.598I~’
OCTAGONAL
a= 0.76R
L 6.O8R
R= 0.623J~’
HEXAGONAL
a= R
L= 6R
aIx’
SQUARE & L= 4a
d= 1.414a
RECTANGULAR
11i~ a= O.8l6,/Z~
L= 5a
d= 1 .803a
b= l!a
EXTERNAL WALL
10
10
65 65 - - 50 15 - 65 - — 50 15 -
70 55 15 - 55 15 — 55 15 — 55 15 -
75 60 15 - 60 15 — 60 15 — 60 15 -
80 65 15 - 60 20 - 65 15 - 60 20 —
85 65 20 — 60 25 - 65 20 — 60 25 —
90 65 25 — 60 30 - 65 25 — 55 20 15
95 65 30 - 55 25 15 60 20 15 60 20 15
100 60 25 15 60 25 15 60 25 15 60 20 20
105 65 25 15 60 30 15 60 25 20 60 20 25
110 65 25 20 Not 60 25 25 Not
115 65 30 20 permissible 65 25 25 permissible
Notes: these ~regravity-walls with a safety factor of brick
1.5 against
2450 kg/m3 and masonry
overturning~
@ 2120 kg/mi. based
All upon stone masonry
dimensions above in @ centimeters. Approximate
depth of excavation: Dr ~H + 30
FIGURE 114-2
WALI.. DESIGN TABLE
—131—
14.7 CONSTRUCTION
This section will present the general steps in construction of a
reservoir, listing important considerations of each step.
Site selection: The site selected for the reservoir should be on
stable ground which will not be threatened by landslides or erosion.
-132-
CENTlMErE~~J
II’~
FIGURE 114-3
FIGURE 14-4
SERVICE PIPES FOR PARTITIONED RESERVOIR
-133-
Preliminary calculations:
Water depth selected to be 65 cm (=0.65m)
Required water surface area = capacity/depth
3/0.65m
= 16.0m
= 24.62m2
Internal dimensions for a square tank = 124.62’ = 4.96m
= 5.Om x 5.Om
The area to be covered by the roof includes the water surface, the top
of the tank walls (each 30 cm wide) and a 10cm overhang:
Roofing area = 5.0 + 0.3 + 0.3 + 0.1 + 0.1 5.8m x 5.8m
Cross-sectl areas of
2
masonry = 0.42m
gravel = 0.05m2
Excavations:
volume of main excavation 7.6 x 8.0 x 0.6 = 36.48m3
volume of foundation trench excavations:
(5.6 + 5.6 + 6.0 + 6.0) x 0.3 x 0.5 = 3.48rn~
Masonry:
3
Total volume of sand = 3.41m
TOTAL VOLUME OF CEMENT = 0.25 x 3.41 = O.85ni3
TOTAL MASON LABOR = 9.74 x 1.4 = 13.64 man-days (skilled)
TOTAL LABOR = 9.74 x 3.2 = 31.17 man-days (unskilled)
Floor slab
Roofing
Plastering.
lWItS;
1. Gi PIPE CIZES ~ 4RPAP"~EMEHT4cr DETAILED HERE
Z REFER it F~6L)RE ILf -1 POE OETA’LS OF SELL p,AjEfl5IOr4S
a EACH ~c SEAM 14A5 A 1”GI P1p5 COL-cJf,jfl ~ ,M,0-SPAN
4 036 AHCICR SOLTS SPACED AT 65 CM
S 0CM
5 80M
520 -~
FIGURE 114—9
RESERVOIR FOR DESIGN EXAMPLE
-140-
15.1 INTRODUCTION
15.3 FLOW
The standard tapstand flow is 0.225 LPS (13.5 liters/minute).
Such a tap will adequately serve a population of 200—230 persons. Where
a tapstand will be serving only just a few households then the flow can
be cut down a bit, and conversely the flow may be increased for a more
densely—populated area (a double - or triple—faucet tapstand may also be
built, refer to Section 15.5).
The design flow is achieved by installing a !” globe valve at the
base of the tapstand, and adjusting it until the desired flow is delivered.
This valve is then securely locked up, to prevent furhter tampering. The
faucet at the discharge serves only as an on/off control valve.
* “Water Supply for Rural Areas & Small Coninunities” (WHO, 1959)
-142—
Dry-stone tapstands can be used when the tapstand can be built into
an embankment, or where there are skilled rock-cutting masons who can
carefully fit together a solid tapstand structure; these types require
minimal (if any) cement mortar. Both of these types are shown in
Figure 15—2.
—143—
=~ BACKPILL. 3’
FIGURE 15-4
WOODEN TAPSTAND
DW.E~N5 IN TW~ET~R5
r©
T4P6T414D TAPGTANO
~
~‘ 61 TEE
~ ~
FIGURE 15-5
GI PIPE ARRANGEMENTS FOR TAPSTANDS
-145-
16. VALVEBOXES
16.1 INTRODUCTION
The purpose of a valvebox is to protect a control valve from
undesirable tampering which can upset the hydraulic balance of the system
and disrupt flows.
Valveboxes can be attached to the structures (as is coimnon with tanks)
or located independently along the pipeline (such as at strategic
branchpoints or near tapstands). They can be constructed of masonry,
GI pipe, HOP pipe, or reinforced concrete (RCC), depending upon the
materials available, size and number of valves, how often they will be
operated, etc.
FIGURE 16—1
MASONRY VALVEBOX
!” 2”
111 311
1!” 3”
2” 4’
It is reconinended, however,
that the overseer personally
check that the control valves will
actually fit inside the GI pipe.
The base of the 61 pipe is
Lock1r~ BAR. slotted to allow it to slip over
the pipeline, and locked into
place with a 3/8’ bolt or hooked
FIGURE 163 rebar ~theseare passed through
GI PIPE VALVEBOX two !” holes
bottom of the drilled
pipe). inAn the
endcap
screwed down with a pipewrench
will be a secure cover. For
operatl-ng the valve, a “key” of !” or 1” GI pipe is used: the ends of
this key are slotted so It can be slipped onto the valve handle and
turned. Dry-stone masonry walls and gravel backfill are recommended,
and painting the GI pipe will help to retard corrosion.
These are valveboxes attached to, or built Into, some structure, such
as intake tanks, break—pressure tanks, or reservoirs. Such boxes will
usually consist of three masonry walls (of which the wall of the tank
may be one) with a dry—stone masonry wall as the fourth. This dry—stone
wall can be dismantled and the pipeline below it dug up without destroying
any part of the valvebox.
Various drawing of some valveboxes are presented in Figure 16—6:
—151—
RCC SLAb
61 PIPE
p.
1’2~’~
FIGURE 16-6
VARIOUS VALVEBOX COVERS
—152—
17.1 INTRODUCTION
At the current time, there is no practical water treatment system
which can be broadly used in Nepal. Thus, emphasis must lie in locating
the cleanest possible source of drinking water, then properly securing
it against further contamination.
Physical contaminants, such as suspended matter, can be removed or
greatly reduced by allowing sedimentation to occur, as discussed in
Chapter 12.
There are only two additional steps that can be practically employed
towards improving water quality: slow—sand filtration, and aeration.
This chapter will not attempt to present the technical details for these:
the reader can find an abundance of such information among the sources
listed in the Reference section of this handbook. Instead,~genera1
description and discussion will be presented so that the reader can gain
a basic understanding of these procedures.
17.3 AERATION
IS B~BN
INTO SM.4I-&~P~PI.L1~
BY V~OOEN&AT5.
FIGURE 17-2
AERATION TOWER
18.1 INTRODUCTION
Hydraulic rams (hydrams) are coming Into greater and greater use
Nepal, allowing many villages that earlier could not use a gravity—flow
water system (because the source was too low) to now have a drinking
water system which Is still economical to construct. Although the hydram
is a pump, it requires no fuel or electricity. Instead, it operates by
using the gravitational energy contained in a large amount of water
falling a short distance to pump a small amount of water up a high distance.
This means that the hydram can be used to pump water from a low
source up to a reservoir tank which is built higher than the village.
From there, the water is distributed via a normal, gravity-flow pipeline.
This chapter will introduce the basic principles of a hydram, and
present the technical knowledge necessary for a surveyor to conduct a
field survey of a potential hydram project and determine if a hydram is
feasible. Although the installation of a hydram requires special knowledge,
there is no reason why a surveyor cannot properly identify a feasible
hydram project, or a designer properly design such a system.
18.2 DESCRIPTION
Qp 2 _____________
x Hd x Od Where:
3 x Hp Qp = delivery flow (LPS)
Hd = “falling” head (meter)
Hp = “lifting” head (not to exceed
100 meters)
Qd = “falling” flow (LPS)
These variables are indicated in Figure 18—2.
—156—
- r ]NC.OP.~P.ATED
SUPPLY PIPE 10
P~VEPIPE -
SUPPLY TANK/
-1
J i
~4IULTIPL-EHYD0AA~INSTALLMENT
WITh SEPEBATE PEIVE PIPES
ANP COMMON DELIVERy PIPE
FIGURE 18-3
-158-
19.1 INTRODUCTION
Just about all structures constructed in water supply projects
require the use of cement: mortar for masonry, plaster for waterproofness,
and concrete for floor slabs. Proper knowledge of how to select the best
materials, how to organize cement—mixing procedures, and how to make
efficient and economical use of cement is all esaential to the overseer.
This chapter is intended to be a fairly complete field reference.
It will describe the various materials required for cementwork, their
properties, and important considerations. It will discuss masonry of
brick and stone, and concrete slabs for floors and roofs. It will present
organizational procedures, helpful construction tips, and mention some
coninon problems.
Some of the more important Information is included in REFERENCE TABLE
VIII at the end of this handbook.
gravel: usually found along rivers and streams: small pebbles and
stones, worn fairly smooth and rounded by the action of water.
crushed stone: large pieces of rock or stone broken down to
aggregate size, by manual labor using sledge hammers.
crushed brick: pieces of broken-up brick.
19.3 CEMENT
Cement is a mixture of chalk or limestone, and clay, which is fired
and then ground into a fine powder. Additional materials may be added
to impart certain properties to the cement (such as to make it quick-
setting, low—heat, rapid-hardening, etc). Ordinary cement is a gray
powder, commonly known as “Portland cement”. This is the type commonly
provided for water supply projects in Nepal
Properties of cement: Portland cement is used for ordinary
construction projects. Cement mortar or concrete has high compressive
(crushing) strength, but relatively low tensile (stretching) strength.
When water is added to a mortar or concrete mixture, it forms a fluid mass
which is easily worked and placed into position. Within an hour
(depending upon temperature and mix) the cement begins to set, losing
its plasticity. Within 4 hours It has finished setting and can no longer
be worked. From the time that setting begins, the cement is undergoing
a chemical hardening process which will continue for at least a year,
although it most-rapidly hardens during the first few days.
Aged cement will form lumps. All lumps should be screened out of
the cement, and no lumps should be used which cannot be easily crumbled
—161—
by the firtgers. If old cement (ie— field stored for more than 6 months)
must be used, increase the amount of cement in the mix by !—i parts
(depending upon how lumpy it is).
19.4 WATER
Water in the cement mix serves two purposes: first, to take part
in the hydration reaction of the cement; and secondly, to make the mix
fluid and plastic enough so that it can be easily worked and placed.
Quality: Water that is fit for drinking is usually fit for mixing
cement. Water unsuited for drinking may still be used, if tested as
follows:
Using water of known suitability (ie— drinking water), make 3 cakes
of cement paste, each approximately 1-2 cm thick by 6 cm in diameter.
At the same time, make 3 identical cakes using the unknown water.
Comparing the two types, observe the setting time, the “scratchability”
(using a fingernail) and strength after a few hours, 24 hours, and
48 hours. Only if both types of cakes are equally strong should the
unknown water be used.
Quantity: Water Is necessary for the hydration of the cement, but
too much water added during mixing results in a weaker strength. The
quantity of water generally needed to make the mix easily workable is
much more than is needed for the hydration reaction. Therefore, no
more water should be added than necessary to make the mix easily workable.
The ideal quantities of water depend upon the amount of cement In the
mix, and approximate guidelines are given along with the mix proportions
for concrete, in Section 19.11.
Once the cement has finished setting, further addition of water
does not weaken it. In curing concrete, this is a necessary action to
prevent the surface of the slab from drying out too quickly.
19.5 SAND
Sand is used in both mortar and concrete (in the latter, It is
sometimes referred to as “fine aggregate”). Proper sand is well—graded
(ie- containing grain! of many sizes mixed together). Sand of a uniform
size, such as beach sand or very fine sand, is not suitable (but can be
mixed into coarser sands).
Sources of sand: Sand found in land deposits is known as “pit sand”.
Such grains are generally Irregular, sharp and angular. Sand carried by
water, such as found along banks of rivers or lakes, is known as
“river sand”. Such grains are generally rounded and smooth, due to the
action of water.
Both types of sand are suitable for cementwork, so long as they are
well-graded and clean.
-162-
19.6 AGGREGATES
Aggregates is the general term for the material mixed with cement
and water to form concrete. Sand is a fine aggregate, and larger
material is a coarse aggregate.
Coarse aggregates may be gravel (generally river—worn, rounded rocks)
or crushed rock and brick.
Stones of granite, quartzite, basalt, or having rough non—glossy
surfaces are best. Hard lirnestones are good, soft sandstones are not.
Limestones and sandstones are porous and therefore not good for water
tank floor slabs, but can be used for roof slabs (same applies for
crushed brick).
Aggregates must be clean and well-graded. Smaller rounder
aggregates (such as river gravel) are better for waterproof floor
slabs.
—163—
19.9 MORTAR
Cement mortar Is used for masonry construction of walls, and for
plastering. Grout is used to cement rebar anchor rods into rocks and
imbedding GI pipes into the masonry.
Typical mixes: Proportions of cement to sand, by weight or by
volume:
Type of mortar Cement:sand
Ordinary masonry 1:4
Reinforced brick roof slabs: 1:3
Spatterdash (1st coat plaster) 1:4
Rough plaster (2nd coat) 1:3
Final plaster (3rd coat) 1:2
Grout: 1:1 — 1:1!
Volumes of mortar: The total volume of mortar is equal to the total
volume of sand in the mix. The cement mixes with water to form a paste
which fills in the voids in the sand. Thus, a 1:4 mix requires 100%
sand and 25% cement; a 1:3 mix requires 100% sand and 33% cement, etc.
—166—
Quantities required to make one cubic meter (1 m3) of various mortar
mixes:
Mortar mix Sand (m3) Cement (m3)
1:4 1.0 0.25
1:3 1.0 0.33
1:2 1.0 0.50
l:1! 1.0 D.67
1:1 1.0 1.00
19.10 MASONRY
Because the masonry walls of the tanks are required to be as
waterproof as possible against the hydrostatic pressure of the water
inside, particular attention must be paid to the workmanship of the
masons. It must be made clear to them that a masonry wall built the
same as walls for their houses is not adequate, and that the walls of
the tanks must be carefully laid down according to directions.
Brick masonry: Bricks are usually locally manufactured in Nepal,
and are of various shapes and quality. The exact dimensions of local
bricks should be obtained for making the estimated requirements. The
total volume of brick masonry is approximately 25% mortar and 75% brick.
Bricks should be soaked in water for several minutes prior to being
used (this prevents them from absorbing too much moisture from the
mortar) but not soaked excessively.
Masons who are experienced at building houses with brick and
mud mortar will be inclined to build tank walls in the same manner;
laying down a bed of mortar, then placing the bricks tightly together
on top of it, then laying down another mortar bed for the next course.
The result is a network of unobstructed channels between the bricks
where water will have easy leakage. Proper brick masonry for water-
proof walls requires spacing the bricks one centimeter apart, and
carefully filling in the joints with mortar. Bricks should be laid
in patterns that do not result in a straightline joint from the
inside to outside of the wall. Refer to Figure 19-2 for various points
on brick masonry.
The top course of bricks should be completely clean and wetted
before putting down the mortar bed for the next course. If the mortar
on the top course has begun to set, the joints should be scraped down
approximately one centimeter deep and refilled with fresh mortar. The
walls should be built up evenly, so that the weight is distributed
uniformly: no section of a wall should be more than 15 courses
(approximately 1 meter) higher than the lowest section.
Once the mortar has set, the masonry should be wetted regularly
(several times per day) for several days.
Dressed—stone masonry: Also known as “Ashlar masonry”. In this
type ófiiasonry, the stones are carefully cut to rectangular dimensions,
making ‘stone bricks”. Such masonry requires skilled masons, and much
-167-
BAD E~RJcx.,%4~A$ON2Y
4LTEaNATE VER1Ic4L
COURSES
BOND CORNERS
L~ ~V
I I ; V~7
FIGURE 19—2
TECHN I QUES
BRICK MASONRY
-168-
time and labor. Ashlar masonry is approximately 30% mortar and 70% stone.
Refer to Figure 19-3:
19.11 CONCRETE
Concrete is used for pouring floor and roof slabs of tanks. The
size and type of aggregates depends upon the purpose of the slab, Its
reinforcement, and its thickness (all discussed in Section 19.6).
Typical mixes: The following proportions are recommended for concrete,
proportions by either weight or volume:
Normal RCC work (roof slabs): 1:2:4 (cement, sand, aggregate)
Waterproof slabs (tank floors): 1:1!:3
The concrete is proportioned and mixed as already discussed in
Section 19.8.
Water: For the above mixes, the approximate amount of water needed
is 3/4 parts water per part of cement (1:3/4 cement:water) by volume.
Volumes of concrete: The total volume of the concrete mix Is never
less than the total volume of aggregates. Typically, air voids make up
50% of the aggregate volume, and these voids must first be filled by the
n,ortar. Excess mortar then adds to the volume of the concrete.
For the above mixes, the following volumes of cement, sand, and
aggregate are necessary to produce one cubic meter (1 m3) of concrete:
Concrete mix cement (m3) sand (m3) aggregate (m3)
1:2:4 0.25 0.5 1.0
l:1!:3 0.33 0.5 1.0
Segregation: This is the separation (due to gravity) of the aggregates
in the concrete. The heavier aggregates will tend to sink to the bottom,
and water will rise to the surface. The result is a poorly mixed concrete
which will be weak. Segregation usually happens transporting the concrete
from the mixing pad to the work site, therefore the mixing pad should be
as close to the final pouring point as possible, and the concrete should
be re-mixed with a trowel before pouring.
19.12 PLASTERING
Plastering masonry walls adds to their waterproofness. Several thin
coats of increasing richness (le— cement content) are better than one
or two thick coats.
All walls will receive three coats of plaster, each 1 cm thick; and
should be plastered at least 5 cm above the overflow level.
Spatterdash: This first coat is a rough plaster of 1:4 mortar. It
is applied by spattering the plaster against the walls, using a trowel.
This coat is NOT troweled smooth, and the resulting surface is extremely
bumpy and irregular. This provides a good rough surface for the next
layer to adhere to.
Second coat: A mortar mJ~xof 1:3, applied to the spatterdash coat.
That coat fs left with a rough surface.
Third coat: The final coat is a 1:2 mortar mix, which is finally
troweled smooth and clean.
Only one coat of plaster per day should be applied.
Volumes of plaster: For a plaster coat 1 cm thick, the following
quantities of cement and sand are needed for each square meter of plastered
surface:
Cement (m3J Sand (m3)
Plaster mix
Spatterdash (1:4) 0.0025 0.01
Second coat (1:3) 0.0030 0.01
Third coat 0.0050 0.01
no spatterdash coat needed). As soon as the second plaster coat has set,
the tank should be flooded a few centimeters deep (for curing the mortar)
for several days. Refer to Figure 19-7.
Mortared stone: This type of flooring is more difficult to put down,
especially with rubble-stone masonry. Care must be taken to prevent
air voids in the masonry. This type of floor should be 15 cm thick,
mortared and plastered as prescribed above.
Reinforced (RCC) concrete: The aggregate for concrete slabs should
be small and well-graded, maximum size being l8m. Rounded river gravel
is excellent for this type of slab. A reinforced slab should be 8cm
thick, with the reinforcement according to the specifications of
Section 19.7, and the concrete work according to Section 19.11.
Structurally, the roof slab must be “tied” into the masonry walls of
the tank. This is done by imbedding rebar rods in the walls, then
bending them over and securing the roof reinforcement to them. This is
shown in Figure 19-8:
SPACED 4
APART ON ALL SIDES-
NOTES;
1 RESAR MOST NOT TOUCH ANY BRICIC _______
2 MORTAR (~ 1 5 MI~ __________ fl
FIGURE 19—in
RF PRICK ROOF SLAB
GRID
FIGURE 19-12
SMALL COVER SLABS
-176-
tarpaulin, straw mats, or several layers of banana tree leaves. The sand
is re-wetted at least three times per day, for a week, after which the
surface can be cleared off and forms stripped away.
Small RCC slabs (less than 100cm square) can easily be made for
covers of valveboxes, break-pressure tanks, or accessways in larger tanks.
For such slabs, the reinforcement is best done using large—mesh wire
screen, but small size rebar can also be used.
Padding the cementwork with straw and covering with mats or tarpaulins
will be of special help. When re-wetting the cement (during curing),
heated water should be used if possible. Protecting the cementwork against
the wind is extremely important, and all protruding rebar should be wrapped
with cloth (since steel is an excellent conductor of heat, these would
be major points of heat loss).
The setting and hardening of cement is temperature—dependent, and
will proceed more slowly at lower temperatures. Increasing the amount
of cement in the mix by 20-25% will help generate more heat and earlier
strength. Heating the aggregates and using hot water for mixing will
improve the setting time (aggregate should not be heated hotter than
can be touched by the hand, nor should the water be hotter than
140° F/60° C.Never heat the cement alone, or add hot water to cement
alone).
The freezing point of the mix may be reduced by dissolving salt
into the heated mixing water. Salt is added by weight, and should
not exceed 5% of the weight of the cement. Each percentage of salt
lowers the freezing point by about 1!° F(0.8° C), but salt cannot be
used effectively for temperatures lower than 25° F(—4° C).
—179—
20.1 INTRODUCTION
Threadin~: Depending upon the size of the HOP pipe, it can sometimes
be threaded (just like CI pipe) and screwed in CI fittings. This is
particularly possible with Class IV pipe, which has thicker walls. A
short ‘nipple” of Class IV HDP can be threaded Into a CI fitting, and
regular Class III HDP pipe welded on.
Expanding: The HOP pipe can be heated and softened over a fire, and
then a threaded CI pipe or nipple can be janined/screwed into it.
The HOP/Cl joints should only be used at low—pressure points. They
are useful for making a discharge pipeline of tank washouts and overflows,
and for putting HOP screened intakes onto the outlet pipes, and for
air-vents, etc.
61 SOCKET
A~VENT
EN~I~TI
SCREWED INTO SOCKET
BUQ~O
OVERFL~OW
PIPELiNE
IIDP
FIGURE 20-2
DIRECT FIDP/GI JOINING
-181-
BOLTS IN MASONRY
TECHNICAL REFERENCES
TECHNICAL APPENDIX A
Equation of Continuity
Bernoulli’s Equation
EQUATION OF CONTINUITY
where: Q flow
V = velocity
A = cross-sect’l area of pipe
Explainea, the equation means that for a constant flow through a
pipeline, at any point the flow must be equal to the flow at any other
point. If the pipe size changes, then the velocity of the flow will
change until the flow is once again constant.
The most commonly used units for the equation are:
Variable Metric units
Q(flow) cm
3/sec
V (velocity) cm/sec
A (area) cm2
The use of the equation is demonstrated using the pipeline section
~hownin Figure A-l below:
~LPS
FIGURE A-i
PIPE SECTION OF SEVERAL SIZES
Knowing the flow (2.5 LPS = 2500 cm3/sec) and the cross-sect’l areas
of the pipe sizes, the Equation of Continuity can be used to calculate
the velocity of the flow through each pipe size:
If Q = V x A
then V = —k-— = 2500
cross-sect’l pipe area
2oniii section velocity = 1437 cm/sec = 14.37 rn/sec
Therefore 63riin section velocity = 112 cm/sec = 1.12 rn/sec
50m section velocity = 178 cm/sec = 1.78 rn/sec
—189-
BERNOULLI’S EQUATION
Thus, at some point A, the water may possess 30% pressure energy,
‘10% velocity energy, and 60% potential energy, while at some other
point B It may have 50% pressure energy, 15% velocity energy, and
35% potential energy. However, at both points the total sum of energy
would be equal.
Mathematically, Bernoulli’s Equation expresses this principle as
follows:
point A point B any other point
=constant
H +h÷_1L
~-P._- = J +h+~ = p+h+V2
r Zg r 2g r 2g
where: H = total sum of energy
p = pressure at points A, B...
r = specific weight of the fluid
h = height above reference level
V = velocity of flow
g = gravitational acceleration
-190-
p (pressure) kg/cm2
r (specific weight of water) l~ii/cm3
h (height) rn/sec
g (Earth’s gravftational acceleration) 9.8m/secZ
—191—
Example application:
An example of applying Bernoulli’s Equation to an ideal,
frictionless system is shown,
using Figure A—3. Bernoulli’s
Equation will be used to
calculate the discharge flow
into the tank:
Since the equation can
be applied to any points along
the pipeline, we shall apply
it at the two atmospheric
points: the water surface of
the upper tank, and the
discharge at the lower tank.
The equation would be written
as follows
upper point A lower point B
~+ h + V2 =~+ h + v 2
Some calculations can be made: since both points are at the same
atmospheric pressure and under no water pressure, then the pressure head
cancels out equally. The height of the upper water surface i~“1-I” above
the reference line, whereas it is zero for the lower point. Furthermore,
the water surface at the upper tank has zero velocity, therefore the
velocity head for that point is also zero. The modified equation now is:
possessed by the water would change form from point to point, but that the
total quantity would remain constant. Also, it was said that a
frictionless system possessed energy in only three forms.
In a real system, however, these are not true: some amount of
energy is converted into heat (by the friction and turbulence of the flow)
which is absorbed by the pipe walls and is lost from the system (ie— the
water no longer holds the energy, since it has been transferred into the
pipe).
Bernoulli’s Equation can be modified to this real situation by adding
another term, which represents this lost frictional energy:
point A point B
r-~Th
2 +f
r 2g = ~~+h+V
r 2g
TECHNICAL APPENDIX B
Analysis of Air-blocks
Formation of Air-blocks
Refer to Figure B-l below. When pipe is laid in the ground, very
often the topography of the land will create high and low points along it.
FIGURE B—i
EXAMPLE PROFILE FOR AIR—BLOCKS
If the pipeline is initially dry and then filled with water, It can be seen
that the water will first collect at point A, and then rise up evenly on
both sides until it overflows at point B and runs down to point C. At
this moment, as the water builds up at point C, the air in section BC is
trapped since it cannot escape either upstream or downstream. As the
water level continues to rise at point C, the trapped air is compressed.
The top of this trapped air pocket will always be at point B, and the
bottom will be compressed higher and higher towards point B as the
pressure continues to build up. When the water level is high enough,
it will overflow at point 0 down to point E, creating a second trapped
-195—
air pocket in section DE. From point E, the water level will rise In the
pipeline (towards the tank) only as long as there is additional pressure
(from the source) to push it higher. The final equilibrium of the system
would be as shown in Figure B-2:
souRca 51.ciic.
Mc
FIGURE B-2
SYSTEM IN EQUILIBRIUM WITH AIR—BLOCKS
The head between the source and top of the first air-block shall be
called the compression head, Hc; the sections of pipe cohtaining the
initial, uncompressed volumes of trapped air shall be the critical
sections (sections BC and CE in Figure B—f); the top of an air—block
will be the high point (points B and D); the bottom of an air—block
will be the low point (points B’ and D’); and the height to which
the water will rise shall be called the maximum elevation (point F).
Although the figure above shows a pipeline with only two air—blocks,
the procedural analysis described herein is equally applicable to a
pipeline with any number of air—blocks.
-196-
Procedure of Analysis
This step—by-step procedure will allow a pipeline with any number of
potential air-blocks to be examined and analysed. Figure B—3 below
illustrates such a system:
Slavic
OW FLOW q
PlEAD It.
ANY NuMeaaOp
FIGURE B—3
BASIC SYSTEM FOR AIR-BLOCK ANALYSIS
As the air is absorbed, the air—blocks will shrink, which allows the
flow to gradually increase. Within a day or so, all trapped air will
be carried out and the full design flow will be possible.
Therefore, it is necessary to determine some minimal flow that can
initially make it through the pipeline past the air-blocks. For this
type of analysis, assume that this minimum desired flow is 0.1 LPS.
The designer has already designed the pipeline to achieve the
desired HGL for the desired design flow. Analysis will begin at the
first air-block downstream from the source (or some other break—pressure
point) and progress downstream.
2, all heads and pipelengths are in
All and
meters, pressures are in
all volumes arekg/cm
in liters
Step 1
Determine the frict’l headloss of the o.l LPS flow between the
source and first air—block. Substract this from the static pressure
head on the air-block. The result is the net compression head, Mc.
Mc = static head — frict’l headloss
Step 2
Use the net compression head, Mc, to calculate the compressed air
pressure of the first air—block:
P = (0.1 x Mc) + 1.0
Step 3
Use Boyle’s Law to determine the compressed air volume of the
air—block:
v = initial volume of critical section
compressed air pressure
Step 4
Using the “volume per meter’ column of Reference Table IV or V,
calculate the length of pipe necessary to contain the air-block:
I. = volume of compressed air
length per liter
.
-198-
Step 5
On the graph profile, measure this distance “L” downstream from the
high point of the air-block. This locates the low end of the air—block.
Determine the elevation of this point.
Step 6
With this Information, It
is possible to calculate the
compressed air pressure of the
next downstream air—block
(refer to Figure B-4):
Pb = compressed air pressure
of air—hlock B
Nb = hydrostatic head
Step 7
With the air pressure of this new air-block, repeat steps 3,4,5 and
6 continuously, proceeding downstream for each air—block, until the
last one Is reached. Determine the air pressure and elevation of the low
end of this last air-block.
Step8
Calculate the equivalent head, He, of this last air-block:
He = 10 (P — 1 .0)
(where “P” is the compressed air
pressure of the last air—block)
-199—
Step 9
Calculate the frictional headloss of the 0.1 LPS flow from the first
air—block to the downstream tank. Subtract this from the equivalent head,
He, to determine the final head, Hf:
Hf = He — frict’l headloss
Step 10
Add “Hf” to the elevation of the low end of the last air—block.
The result is the highest elevation that the 0.1 LPS flow will reach.
If the downstream tank is lower than this elevation, then this minImal
flow will be able to get through the pipeline, and eventually will
eleminate all air-blocks so that the design flow will be able to make
it. Nothing needs to be done about the air—blocks.
Step 11
If the downstream tank is higher than the point that the 0.1 LPS
flow will reach, then the pipeline must be re-designed to minimize
(or eliminate) the air—blocks.
50MM HDP ~ M~
~4 1aMM~
lOOM 50MM
ISO M’ 32MM
M 212 M
50MM 32MM—., p~__ 1ISM
i~3C
~J
2
1
~
10-
~ ~
0 I I - I ~1~
ó 20G 3o~ 500 500 70 ~OO 900 1000 nOo
P1P~LENGTH(M~~EQ5)
FIGURE B—S
DESIGN EXAMPLE
-201—
Design Example
Figure B—5 shows an example profile with three potential airblocks.
In the preliminary design, a desired flow of 0.5 LPS was used, and
pipe sizes were selected to leave a residual discharge head of 5 meters
at the tank (this was accomplished by selecting 213m of 32m HOP and
887m of 5Onr HOP pipe). The pipe was arranged in accordance with the
above strategies: 5Gm HDP was used from the source to the first
air—block, and also used in the upper portions of each of the critical
sections.
Critical section I (points A—B): 75m @ bOrn HOP + lOOm @ 32rn HOP
Critical section II (potnts C—D): 5Gm @ 5Gm HOP + lOOm @ 32inii HOP
Critical section ru (points E—F): 62m @ BOrn HOP + 13m @ 32m HOP
The frictional headloss of the 0.1 LPS flow from source to the first
air-block is 0 (zero) meters. Thus, the net compression head:
Hc=20—0=2Ometers (Stepl)
Analysis of Air—block I:
compressed air pressure = P1 = 0.1 (Hc) + 1.0 = 0.1 (20) + 1.0
2 (Step 2)
= 3.0 kg/cm
compressed air volume = v = initial volume = 162
air pressure 3.0
V = 54 liters (Step 3)
TECHNICAL APPENDIX C
Derivation of
Combination Pipes Equation
In reference to Chapter 8.6, page 71
El x L
1~0X = head lost in large pipe section
The total desired headloss, N, is the sum of the headlosses in the two
pipe sections:
-I = Es x 100 L-X
+ El x
lOON = Es x X + El x (L - X)
lOON - (El x L)
(Es - El) =
-205-
TECHNICAL APPENDIX 0
Emotional Diffuser
= CA~
Where: Q = flow
C = coefficient of orifice
A = cross-sect’l area of orifice
g = gravitational acceleration
N = headloss through orifice
TECHNICAL APPENDIX E
Suspended Crossings
Basic Calculations
FIGURE [—2
VARIABLES FOR SUSPENSION CALCULATIONS
-208-
Step 1
Select the amount of vertical sag, Y, desired. The cable must
not sag so much that it will be snagged by floating debris or landsliding
rocks. A sag of 8%—l0% of the span is good, if there is adequate clearance
Step 2:
Step 3:
B = arctan 4V (degrees)
Step 5:
Step 6:
Compare the total tension, T, with the allowable tension of the
selected cable. Select a larger or smaller cable size if necessary, and
repeat the calculations.
Step 7:
DESIGN OF ANCHORS
CI Post: A length of CI
pipe securely imbedded in a ground
block of concrete will make a
sturdy securing point. If
necessary, two such posts can be
used. Refer to Figure E-4.
1” CI pipe: 68 kgs
1"” CI pipe: 151 kgs
2” CI pipe: 270 kgs
3” CI pipe: 678 kgs
Masonry Block Anchors: Where it is not possible to dig a posthole
deep enough for a CI post, then a cement masonry block anchor can be used.
Such an anchor functions by its frictional resistance to sliding.
CABLE
TEE
CLAM~
POST
FIGURE [-LI
6! POST ANCHORS
0 • a~t51fl
REQUIRED W~IG~{1
OF M~.G0NRY(Ka)
w.~ +TSne
3)
REqui~D VOLUME ~ff ,4tASOMRV (M
r BRICK • 2120 KG/1fl3
‘Si 5fl3NEr2~I.9)KG/M3
L DRV3~DNE 2000x6rn5
FIGUPE E—5
IASONRY BLOCK ANCHOR
-211-
0l 1PEl:~5T
~EQUI~ED M~4TEJ~[4LS
~‘GlPIPE (~G0C~
%~‘REBAR ~ 130 C/A
3
I
CEMENT(~ OOaM
FIGURE E—6
I
MASONRY BLOCK ANCHOR (C0N’T)
—212-
The total weight required is governed by the type of soil that the
anchor is imbedded in, and the angle of the suspension cable. Different
soils have different frictional characteristics:
Soil type u
The weight of the cement masonry block is about 630 kgs. The total
weight required can be calculated from the equation given in Figure E-5.
The remaining weight (if the masonry block alone is not enough)
3~ is added
using dry-stone masonry, which is approximately 2000 kg/m
CLAMPING
SNEATNING
Sheathing may be done by wrapping the NDP pipe with two or more
layers of burlap (jute) sacking material, or using split bamboo slats
secured by wire. This is shown in Figure E—B.
DESIGN EXAMPLE
FIGURE E-7
SECURING PIPE TO CABLE
Known variables:
Wp = 3.65 kg/rn
Ww = 1.26 kg/rn
S = 25 meters
V = 2.5 meters
W52 = 184 kg
=
tan B = = 0.40;
therefore B = 21MB’
L = S x (1 + 8Y2 = 25.7 m
w = T x cos 8 + T x sin 6
U
= 1735 + 132 = 1867 kgs
weight of masonry block 630 kgs, therefore 1237 kgs of dry-stone
3).
masonry is required additionally (this is about 0.618m
Refer to Figure E-10.
Designing the post anchor (west bankj
It was previously calculated that the horizontal tension, t, was 184 kgs.
From the Information on page 2U9, it is seen that a single post of 2 GI
pipe would be used (or two posts of 1! 61).
-216-
TECHNICAL APPENDIX F
Roofing
GENERAL NOTES
The roofing of a tank will depend upon its size, and whatever
materials are available locally or from the regional office.
The basic structural requirements for a tank roof are strength and
waterproofness. Since the tanks are relatively low structures, their
roofs become accessible playgrounds for children. Additionally,
the roof will become dirty with dust, leaves, bird—droppings, etc, which
must not be washed into the tank by rain.
Beams span the tank ano support the roof. A CGS roof requires the
minimum amount of wood ( and the simplest structure), and a slate roof
requires the most.
Maximum b d Cross-sect’l
Maximum b d Cross-sectl
Ar~ X Area
2) (cm) (cm x cm) (m2)
(cm) (cm x cm) (m
These calculated using maximum allowable extreme fiber stress of sal wood
@ 168 kg/square centimeter, with a mid-span load of 210 kgs.
—218-
1” 67 170
1!” 178 316
2” 278 480
SLATE ROOFING
This type of roofing depends upon the local availability of slate.
It requires a lot of supporting woodwork (beams, rafters, purlins
etc) which will increase the cost and construction time of the roof.
If a slate roof is to be used, the main beams are sized according to
the table above; the villagers can be relied upon to construct the
remaining woodwork and proper installation of the slate.
)
—2 19—
CGS ROOFING
Roofs of corrugated galvanized steel (CGS) sheets are the best and
easiest to construct, requiring a minimum of supporting wood. The
standard size available in Nepal is 3’ x 10’, and its effective size
(with one corrugation overlap)
is 300cm x 70cm, and weighs
approximately 25 kgs.
Although coniiionly used to roof houses and barns in Nepal, these are
not acceptable roofing methods for water tanks. They require frequent
maintenance, and will quickly become dirty and harbor Insects.
-220-
TECHNICAL APPENDIX C
The amount of head available to push the flow through the outlet piping
is exactly equal to the depth of water in the tank above the outlet level
Of this head, it will be assumed that not more than 20 cm is desired to be
lost due to the frictional headloss of the outlet flow.
TOTAL = 191
Therefore, the equivalent
pipelength of these fittings is-
191 x 1!” = 287” = 728 cm
Thus, the maximum outlet flow must not have a frictional headloss
factor greater than 2.33% for 1!” CI pipe. The same technique is used
to determine the maximum outlet flow for different pipe sizes. For the
above pipe arrangement, these maximum flows are:
!” 5.36% CU.lULps
1” 3.25% 0.33 LPS
1!” 2.33% 0.80 LPS
2” 1.32% 1.3D LPS
3” 1.26% 3.30 LPS
Frorii the above table it can be seen that 1/2’ pipe is unsuitable
as a tank outlet because of the low flow.
—222—
TECHNICAL APPENDIX H
Gabi ons
Gabions are wire-mesh cages filled with stone and arranged to form
retaining walls for banks and cliffs which may collapse due to erosion.
Their use in CWS projects will primarily be along banks of gullies and/or
streams, directly supporting the ground beneath a pipeline crossing.
Cabions can also be used to stabilize terraces and terrain around intake
tanks, etc.
S
“diaphragp~”.When the gabions
)
-224—
with a continuous length of wire, rather than “tied” together with short
pieces. The cages are placed into position while empty, stretched to
their full dimensions (pegging the corners securely to the ground will
help), and wired together. Diaphragms are inserted and wired into place.
Filling: Gabions are filled with clean, hard, angular rubble stones,
each stone being individually fitted into place, similar to constructing
a dry-stone masonry wall (stones should not just be dumped into the cages).
When the cages are filled, the lids are then wired shut for additional
stability. The gabions should be carefully backfilled for additional
stability. On completion, the gabions should be completely and tightly
filled, square, and true to dimensiQns.
Reference Table I
Metric Units
English Units
12 inches 1 foot
3 feet = 1 yard
5280 feet = 1 mile
Volume: 4 quarts = 1 gallon = 231 in3 = 0.13 ft3
1 ft3 = 1728 in3
Water: 1 in3 = 0.036 pounds yd = yards
1 ft3 = 62.4 lbs. ft = feet (‘)
1 gallon = 231 in3 8.34 lbs in = inches (“)
Weight: 16 ounces = 1 pound
qt = quarts
2000 lbs = 1 ton lb = pounds
oz = ounces
gal = gallons
Conversion Factors
English —... metric Metric—~.english
1” = 2.54 cm 1 cm = 0.39’
1’ 30.48 cm
1 yd = 91.44 cm 1 m 39” = 3.28’
1 mile 1609 rn = 1.6 km 1 km = 3280’ = 0.62 miles
1 oz = 28.4 gm 1 gm 0.035 oz
1 lb = 450 gm = 0.45 kg 1 kg = 35 oz = 2.2 lbs
1 qt 0.91 liters 1 liter 1.1 qt = 0.035 ft3
1 gal = 3.63 liters 1 m3 = 35.31 ft3
1 in3 = 16.39 cm3
1 ft3 = 28.3 liters
Reference Table II
INSTALLATION OF UNIONS,
FLANGES, & VALVES
124 m2
for intakes
Screening, wire 3mm square for air—releases
Screws, brass !”
Screwdri ver 8” for cement—mixing
Shovel, flat-edged for excavation
Shovel , round-edged for HOP pipejoining n
Stove, kerosene pressure** for caulking CI 1 ball
String, kite 300m threads
retractable-type
Tape measure, steel 2 -m tailor type 2
Tape measure, plastic 5’ for CGS sheets
Tin cutters for cement-work 2/mason
Trowels, masons for HOP pipejoining 1 box
Thermochrom crayons
for up to 2” Cr pipe
Vise, pipe 2”
for up to 1” GI pipe 1
Wrench, pipe 14” for up to 2” CI pipe t2 per project
Wrench, pipe 18” for up to 3” CI pipe J
Wrench, pipe 24”
* according to design + 10% extra
~ more convenient than blowtorches
Reference Table IV
-JI
i-l~I
(OJL~I u_I
I ~ If) LI_I LI_I C-J C\1
wl~I
~.jJwI
I—lw’
~(Owl
II— k—
In csj C’_I ~- ID
-, ‘~ I0I C~JI’D N- C\j I’D
wi L~ . .
~ I~
1— CD CD CD .-
wi
WI In
WI—IL N- ID CD I’D I’D CD I’D ~.j
~ wi U~) ,— C,J OD
-~
_J I I CD CD .- C’,J ,- U_I I’D
CDf~I~_ ~
~r—
_1 9-4-
00
Em
CD CD
~IW I— .- U_I C) 10 ID CD
~JLJ c’ (‘DI’,j
WIUDI DUN- ~OD
‘.“ I’D
~ICD,W, C’4 NJ
S S
U U
— -~-
U_I ID_I 0_I
uD~ CI I’D I’DIO -~ -~
ID CD
NJ ‘\JC’D
II II
0 i— —‘ -‘
I—, -.
I xl coc,, NJ—
—‘I ‘~I
I .
c”i
. . . .
N-
. I ‘-‘I
In
In
UI
‘0 ‘0
L) (U
If,
I/_I —~:. --
—.—. U,
-J .—‘ 0_I
(_) C
4-,
‘0
a) a)
WI4-’
N.IIU
‘—.15 UI
In
5-’
Wro 5 CD CD CD
NJ U_I 0_I
.—.t I..
0~15-,
4-,
0
—
o CD N) ~
uUTER DIAMETER WALL CROSS-SECTL VOLUME WEIGHT V
CD (0
PIPE ~I2E (mmiii) TH1~WSS AREA PER METER PER METER ~ —.
(no~al ~e) Max Mm (mm) (R~i~R) (liters) (kgs) (n
CD -~.~r~-l
-~ ~
CD (fl CD r~CD
~CD
— .—.m.-+
(~~CD ~-O
-~
~-~n
C,—
1!’40mm 48.8 47.° 3.25 12.57 1.26 3.65 m CD —I~
‘~ CD
~o—.r, G)
CD~—~OCD
0 CD
CDmU,-~ C-. -*5
2’ 5Orrmmii 60.8 59.7 3.65 19.63 1.96 5.17 - 0. -t, ~
0 0 CD
P1 3
0 0 U, CD
C C-f -~ (I) ~
C-f’< CD C-,
89.5 88.0 4.05 50.27 5.03 m-. -~
rn CD
3” 80mnmn 8.64 ~-
CD C-)
CD V 0. ,-f — -4
~fl PC
1CD CD — 0~
CD • (fl ~‘C C-)
c+ CD > CD
4’ 1 OUmul 115.0 113.1 4.50 36.59 d.0b 12.40 — CD~
U’ —4 CD -I
•C
~CD
-n C-.
cD
o rfQ Cd,
G) C
(aC ‘-fi 0
CD,-f
CD V C/C
CD
61 pipe typically is provided in 6—ureter lengths, with threaded and CD0.
~ CD —
socketed ends. .
C_f
CDV—.0.
(/~~
CDC
-S DT’ CD
C_f C, C ~
~- ~-
CD 0/ —‘ (/5
ef C/C CD rf
CD ~_f CD
—
C-C- ~
CD
-3
C/C (/10.
U,
Reference Table VI
RESIDUAL HEADS
EXCAVATIONS 3
Per 1-m
a) Ordinary soil o.ss man-days
b) Gravelly soil 0.77 man-days
c) Boulder mix 1.10 man-days
d) Medium rock cutting I .GO man—days
e) Hard rock cutting 2.50 man-days
PLASTER* Per 1—m2 of: Spatterdash (1:4) 1.3 mix 1.2 mix
a) Cement 0.0025 m3 0.0030 m3 0.0050 m3
b) Sand 0.01 m3 0.01 m3 0.01 m3
c) Mason labor 0.14 man-days 0.14 man-days 0.14 man-days
d) Unskilled labor 0.22 man—days 0.22 man—days 0.22 man-days
* Each coat of plaster 1 cm thick
a) Cement 0.089 m3
b) Sand 0.35 m3
c) Mason labor 1 .4 man-days
d) Unskilled labor 3.2 man—days
Reference Table VII (Con’t)
CCS ROOFING
Nominal size: 3’ x 10’
Effective size: 70cm x 100cm (with overlap of 1 corrugation)
WeIght: 25 kgs
CEMENT
Per bag: 50 kgs
burlap (jute) bag: 32 liters (0.032 m3)
paper bag: 34 li ters (0.034 m3)
SPECIFIC WEICHTS
Portland cement: 1440 kg/m3
brick masonry: 2120 kg/m3
stone masonry: 2450 kg/m3
concrete: 2409 kg/m3
seasoned wood: 650 kg/m3
water: 1000 kg/s3
dry-stone masonry: 2000 kg/m3
Reference Table VIII
TRIGONOMETRIC TABLE
00 0 1 0 1 90°
QQ3QC .0087 .99996 .0087 114.6 89°30
10 .0175 .99985 .0175 57.29 89°
l° 30 .0262 .99966 .0262 38.19 88° 30
2° .0349 .99939 .0349 28.64 88°
2° 30’ .0436 99905 .0437 22.90 87° 30
3° .0523 .99863 .0524 19.08 87°
3° 30’ .0610 .99813 .0612 16.35 86° 30
40 .0698 .99756 .0699 14.30 86°
4° 30’ .0785 .99692 .0787 12.71 85° 30
50 .0872 .99619 .0875 11.43 85°
5° 30’ .958 .99540 .0963 10.39 84° 30
60 .1045 .99452 .1051 9.514 84°
6° 30 .1132 .99357 .1139 8.777 83° 30
7° .1219 .99255 .1228 8.114 83°
7° 30 .1305 .99144 .1317 7.596 82° 30
8° .1392 .99027 .1405 7.115 82°
8° 30 .1478 .98902 .1495 6.691 8l° 30’
9° .1564 .98769 .1584 6.314 81°
9° 30~ .1650 .98629 .1673 5.976 80° 3O
100 .1736 .98481 .1763 5.671 80°
10030 .1822 .98325 .1853 5.396 79° 30’
11° .1908 .98163 .1944 5.145 79°
11° 30 .1994 .97992 .2035 4.915 78° 30’
12° .2079 .97815 .2126 4.705 78°
12° 30 .2164 .97630 .2217 4.511 77° 30’
130 .2250 .97437 .2309 4.331 770
VERTICAL ANGLE B
1° 2° 3° 4° 5° 6° 7° 8° 9° 100 11° 12° 13°
20 0 0 0 0 0 0 ! ! ! ! ! !
40 0 0 ! ! ! ! ! ! ! 1 1 1
60 0 ! ! ! ! ! 1 1 1 1 1 1!
w B 0 ! ! ! ! 1 1 1 1! 1! 1!1! 2
100 ! ! ! 1 1 1 1! 1! 1! 2 2 2
t 120 ! ! 1 1 1 1! 1! 2 2 2!2! 2!
~ 140 ! ! 1 1 1! 1! 2 2 2! 3 2! 3
16! ! 1 1 1 1! 2 2 2! 3 3!3 3!
18! ! 1 1 1! 2 2 2! 3 3 3!3! 4
220! ! 1 1! 1! 2 2! 3 3 3! 4 4 4!
~ 22! 1 1 1! 2 2! 2! 3 3! 4 4 4! 5
(0 24! 1 1 1! 2 2! 3 3! 3! 4 4! 5 5!
26! 1 1! 2 2! 2! 3 3! 4 4! 5 5! 6
28! 1 1! 2 2! 3 3! 4 4! 5 5! 6 6!
30! 1 1! 2 2! 3 3! 4 4! 5 5! 6 6!
14° 15° 16° 17° 18° 19° 20° 21° 22° 23° 24° 25°
2! ! ! ! ! ! ! ! ! 1 1 1
4 1 1 1 1 1 1! 1! 1! 1! 1! 1! 1!
61! 1! 1! 1! 2 2 2 2 2 2! 2! 2!
t~ 82 2 2 2! 2! 2! 2! 3 3 3 3! 3!
~102! 2! 2! 3 3 3! 3! 3! 3! 4 4 4
I—
~123 3 3! 3! 3! 4 4 4! 4! 4! 5 5
° 143! 3! 4 4 4! 4! 5 5 5 5! 5! 6
164 4 4! 4! 5 5 5! 5! 6 6! 6! 7
a 18 4! 4! 5 5! 5! 6 6 6! 6! 7 7! 7!
~ 205 5 5! 6 6 6! 7 7 7! 8 8 8!
~ 225! 5! 6 6! 7 7 7! 8 8 8! 9 9!
246 6 6! 7 7! 8 8 8! 9 9! 10 10
26 6! 6! 7 7! 8 8! 9 9! 9! 10 10! 1-1
28 7 7 7! 8 8! 9 9! 10 10! 11 11! 12
30 7! 7! 8! 9 9! 10 10! 10! 11 11! 12 12!
Reference Table X
FLOW !” GI 1” 61 1!’ 61 2” 61 3” 61
CLA5~IV (loKg./cm2)
FLOW 2Oirnii 32mm SOimii 63mm 90mm
3.1*
0.10 0.31*
0.12 45* 0.40*
0.14 5.6* 0.52*
0.16 7.3 0.67*
0.18 9.0 0.81 *
0.20 10.6 0.99*
0.225 13.4 1.22*
0.25 15.7 1 P43*
0.275 18.5 1 P74*
0.30 21.8 2.02* 0.25*
0.35 28.0 2.71* 0.31*
0.40 36.2 3.36 0.40*
0.45 45 4.0 0.49*
0.50 54 4.9 0.59*
0.55 63 5.7 0.71 *
0.60 73 6.7 0.81 * 0.27*
0.65 7.8 0.94* 0.31 *
0.675 8.4 1 .00* 0.34*
0.70 8.8 1 .06* 0.36*
0.75 10.1 1 .23* 0.40*
0.80 11.2 1 ~34* 0.45*
0.90 13.4 1 .67* 0.54
1.00 16.4 2.00* 0.66*
1.10 19.8 2.37 0.78*
1 .20 22.6 2.77 0.92*
1.30 26.4 3.19 1 .08*
1 .40 30.2 3.61 1 .23* 0.22*
1 .60 37.5 4.5 1 .52 0.28*
1 .80 5.6 1.85 0.35*
2.00 6.7 2.24 0.41*
2.20 8.3 2.69 0.49*
2.50 10.1 3.25 0.60*
2.70 12.2 3.92
3.00 13.9 4.6 0.84
3.20 17.4 5.5 0.99
3.50 18.9 6.2 1.11
3.70 21 .3 6.9 1 .29
4.00 23.7 7.7 1 .43
4.20 8.7 1 .57
4.50 9.5 1 .78
4.70 10.8 1 .97
5.00 11.8 2.13
5.50 13.4 2.46
6.00 15.9 2.91
6.50 3.36
7.00 3.89
INN~D~A~5T~R
(Mpt’~
I0
PLOW MONOGRAPH
•5
FOR SMOOTH PLASTIC PIPE
AND ~ PIPE
2.
H 20
Q~mTvOP~
L.rnC
wBLocrrY
~~?46 6pI~D IdTR/VO ~UR
~TICTD~f. I~NT~
I
—16 0-03-C
~ 0-s o~o~_t_o.I
—30 0-1
30- 0.1g.
0.1
35.
35 0•1 01.
10 0. o.i4
4. 0.5 01
c~,~-1
5. 03
3.
1.5 O~l o-5
~ 2
~
3 0.
,o 5~
0-5-
a.
10 . — ‘.5
qo I
‘5
/~ 100 ~
‘.5 —2
3•
40 ‘.3
a
—5
,~ ,~ I.. 3 ~
3—
lso-~ ~
100 4— — Ia
300 5— 5—
—
/0 — —as
3.
/5 — 4*0
2.
30-
— leo
£0 —
Printed in Nepal at jore Ganesh Press Pvt. Ltd. Kathmav