Earned Value Management: SL No. Description Status %age or Value

The document provides information on earned value management for a project. It shows that the project is 50% complete based on actual work, but was planned to be 70% complete. It is behind schedule with a Schedule Performance Index (SPI) of 0.714 and a negative Schedule Variance (SV) of -20. It is also over budget with a Cost Performance Index (CPI) of 0.714 and a negative Cost Variance (CV) of -20. Formulas are provided to calculate key earned value metrics.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views3 pages

Earned Value Management: SL No. Description Status %age or Value

The document provides information on earned value management for a project. It shows that the project is 50% complete based on actual work, but was planned to be 70% complete. It is behind schedule with a Schedule Performance Index (SPI) of 0.714 and a negative Schedule Variance (SV) of -20. It is also over budget with a Cost Performance Index (CPI) of 0.714 and a negative Cost Variance (CV) of -20. Formulas are provided to calculate key earned value metrics.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

EARNED VALUE MANAGEMENT

%age or
Sl No. Description Status
Value
1 Budget at Completion (BAC) 100
2 Planned % Complete (%PC) 70%
3 Actual % Complete (%AC) 50%
4 Actual Cost (AC) 70

5 Planned Value (PV) 70


6 Earned Value (EV) 50
7 Schedule Performance Index (SPI) 0.714
8 Schedule Varience (SV) -20 Project is behind the schedule
9 Cost Performance Index (CPI) 0.714
10 To Complete Performance Index (TCPI) 1.667
11 Cost Varience (CV) -20 Project is over budgeted
IF SPI = 1 SV = 0 Project is on proper schedule
SPI < 1 SV < 0 Project is behind the schedule
SPI > 1 SV > 0 Project is ahead of schedule

IF CPI = 1 CV = 0 Project is on budget


CPI < 1 SV < 0 Project is over budgeted
CPI > 1 SV > 0 Project is under budgeted
Sl No. Formulaes
1 PV = BAC X %PC
2 EV = BAC X %AC
3 SPI = EV / PV
4 SV = EV - PV
5 CPI = EV / AC
6 TCPI = (BAC-EV) / (BAC-AC)
7 CV = EV - AC