Methos Statement For Substructure
Methos Statement For Substructure
Document No.
TITLE: Method Statement for Substructure Pages 32
CHEC/AUR/MS/001
1 Contents
1 Contents 1
2 Introduction ............................................................................................................................... 2
3 Scope of Method statement ....................................................................................................... 2
4 Required Manpower.................................................................................................................. 2
5 Pre excavation tasks ........................................................................................................... 2
5.1 5.1. Site Survey and Grid of Level ........................................................................... 2
5.2 5.2. Adjoining Structures and Property ................................................................. 3
6 Excavation and soilnailing works, ............................................................................................ 4
6.1.1 5.1.5. 3rd Stage of construction ................................................................................ 8
6.1.2 5.1.6. Excavation for pile caps and core pit ........................................................ 9
7.Environmental protection plan ......................................................................................... 11
7.1. 11.1. Environmental impacts ................................................................................. 11
7.2. 11.2. Mitigation measures ...................................................................................... 11
2 Introduction
AURELIA AVENUE CORNER MCKINLEY PARKMAY AND 21ST DRIVE, BONIFACIO GLOBAL
CITY, TAGUIG CITY, PHILIPPINES.
4 Required Manpower
Project Manager - 01 Site Engineer - 02
Material Engineer - 01
Level survey will be carried out and confirm the existing ground levels.
2
AURELIA PROJECT, PHILIPPINES
Third(3rd) party license surveyor will be appointed as subcontractor of crack surveys and monitoring
work. Initial survey carried out and report submitted for client/consultant review.
5.3. Site Drainage
The basement excavation will necessitate the process of dewatering, and taking into account the
need to maintain stability of excavations, well point de-watering would be prudent. Well point
dewatering should be installed depth of approximately 0.5 m below the final excavation level.
Refer the MS for Dewatering and recharge.
6. Plants and Machinery
Estimated no. to be
No. Description Plant and machinery image
Deployed
Note: photographs are only for illustration purpose. Brand and size are may differ.
3
AURELIA PROJECT, PHILIPPINES
Excavation shall commence from boundary edge of the site. Excavation shall continue up to Level
+3.075m depth.
4
AURELIA PROJECT, PHILIPPINES
MATERIAL USED
Soil Nails:
a) Reinforcement bars, threaded and joint couplers.
b) 150x150mm MS plate and lock-nut for the head.
c) Non-shrink cement grout (by adding Sika Intraplast-ZTM)
d) PVC spacers
e) Tremie Grout tube – polypipe ¾” or 1” (removable)
Guniting:
a) BRC wire mesh
b) Chippings (<10mm) and Sand
c) OPC Cement
d) 50mm PVC pipe, wrapped with geotextile as weepholes
The quantities of cement in the mix shall be measured by weight. The grout shall be free from
segregation, slumping and bleeding. Grout shall be mixed on site and shall be pumped into its
final position as soon as possible.
Two sets of three test cubes shall be taken for one batch of soil nails grouted for testing
purpose. Three test cubes shall be tested at 7 days and the remaining cubes at 28 days after
casting. The characteristic strength of the grout shall be 21 N/mm2 and 30 N/mm2 at 7 days
and 28 days.
5
AURELIA PROJECT, PHILIPPINES
METHOD OF INSTALLATION
3.1. CONSTRUCT SCAFFOLDING ON SLOPE
Scaffolding shall be installed safely using GI scaffold pipes of min 50mm diameter and
secured using an appropriate clamp. For safety reasons, no tie wires or other methods of
securing the GI pipes shall be used except the approved clamps. As the slope at Munchy’s is
steep (40-600 to horizontal) and high, proper scaffolding must be used and additional bracings
must be made to ensure its safety. Working platforms shall be installed and all workers must
wear safety belt / harness while working on the scaffolding
GUNITING WORKS:
NORMAL DRY-MIX SHOTCRETE/GUNITE OPERATION
6
AURELIA PROJECT, PHILIPPINES
a) Excavate certain depth (if require) and trim face to receive shotcrete / gunite.
b) Install steel mesh held down by short steel rods drilled/ hammered into the slope
at approximately 2m c/c.
c) Shotcrete/gunite shall be batched by volume using a wooden box of volume
equals to one 50kg bag cement.
d) Mixing shall be by drum mixer for approximately two minutes.
e) Shotcrete/ Gunite shall be conveyed by dry process through hose. Pipes may be
used for long conveyance distance.
f) The nozzle man shall hold the nozzle at a distance of 600mm to 1200 from the
shotcrete/ gunite surface.
g) Shotcrete/gunite shall be installed in layer not exceeding 100mm each and
allow to set before applying the next layer. The finished surface shall be
rough castnatural shotcrete/ gunite finish.
h) Curing shall be by water spray at least once a day for 4 days
7
AURELIA PROJECT, PHILIPPINES
Further excavation shall continue after finishing the 1st Layer gunite and shotcrete.
8
AURELIA PROJECT, PHILIPPINES
Excavation shall continue after 2nd layer and repeat the above-shown until the footing and foundation
designated level.
Pile cut-off level shall marked on the pile prior to hack the pile. All the debris from pile hacking shall
remove from the site. 50mm thick lean concrete shall laid prior to build solid block formwork for pile
caps. Outside of pile cap form shall backfill and compacted to the satisfaction of Specified
requirement. Further open cut excavation if the depth of excavation is not exceed 2m. Soldier pile with
timber lagging shoring or shall provide for excavations deeper than 2m. Special attention would be
consider to protect existing piles when excavating near the pile
9
AURELIA PROJECT, PHILIPPINES
Due to diaphragm wall stability we will retain earth, 10m from diaphragm wall and additionally keep
slope ratio of 1:1.75 (depth, length). After mobilisation of ground anchor work, 10 m reserved earth
will be excavate as per the sequence described in section 7 Excavation and earth work.
10
AURELIA PROJECT, PHILIPPINES
6. Quality management
Refer to approved PQP.
Segregate good excavated material shall be used for backfilling and excavated surplus material shall
be transport to selected disposal location.
1. Environmental aspects of heavy vehicular moment with in site.
2. Soil transportation for disposal of soil.
7.1. 11.1. Environmental impacts
1. Dark smoke and excessive dust emission from heavy vehicles can cause air pollution.
2. Earth spillage with in the work place and public road during transportation can cause dirt
accumulation on the road which can affect other road users.
7.2. 11.2. Mitigation measures
5. Risk assessment
11
AURELIA PROJECT, PHILIPPINES
Personal PPE
1. Safety Helmet
2. Safety foot wear
3. High visibility safety west.
4. Traffic handHelmet
1. Safety glove
5. Whistle
2. Safety foot wear
6. Stop
3. and
Highgo signagesafety west.
visibility
7. Traffic stick light
4. Whistle
12
AURELIA PROJECT, PHILIPPINES
Head Eye Hearing Foot Hand/Arm Body Resp. Fall Life High
Restraint Jacket Visibility
(buoyancy Vest
aid)
MANDATORY MANDATORY WHEN MANDATORY WHEN WHEN WORKING MANDATORY
REQUIRED REQUIRED REQUIRED AT
HEIGHT
Other Control Measures Implemented:
Site Safety Inspections, Revision of PPE requirement to be monitored and assessed and if required amended
PPE Inspection/Maintenance Arrangements:
All PPE is to be visually inspected on a daily basis prior to commencing works.
Fall restraints to be inspected in line with manufactures recommendation and inspection registers update.
Training/Instruction Required in Safe Use of PPE
Verbal Instruction YES Written Instruction
Tool Box Talk YES Specialist Training
ssued by:
Approved by:
Project Manager HSE Manager
13