Anode Baking
Anode Baking
Anode Baking
Lindsay
TMS (The Minerals, Metals & Materials Society), 2011
Abstract
847
Temporary crossover Before installing the temporary crossover, the stage 1 furnace
needed to be prepared and modified. Sections 16, 17, 52 and 53
In an open type furnace, the gases flow along each flue wall line, were fully loaded with baked anodes and packed with coke.
from the blowing ramp and even the cooling ramp, up to the Therefore, four sections of the first stage furnace were not used in
exhaust ramp. The regulation of the negative pressure downstream the anode baking process during the operation with the temporary
of the heating zone and the high pressure in the blowing zone crossover. The second top blocks of section 16 and the third top
allow the control of the flow inside the flue walls and the fire blocks of section 53, as well as some bricks were removed, in
progression speed. order to allow the vertical ducts of the temporary crossover to be
installed.
The typical design of the open type furnace has two metallic
ducts, with the inner part lined with insulating materials, which Once the brickwork modifications were finished, the temporary
are located at each end of the furnace. These devices, called crossover was installed. The metallic connections with the flue
crossovers, are used to collect the gases from each line of flue walls were not in direct contact with the bricks, allowing free
walls and to conduct them from one furnace half to the other. expansion and movement of the different materials. Pressed
refractory fiber was used to ensure the tightness between the
Before the erection of sections 18 and 51, i.e. the “new” sections vertical metallic connections and the flue walls. Figure 3 shows
adjacent to the “old” ones, it was necessary to remove the the erection of the temporary crossover after finishing the
crossover between sections 17 and 52, and to demolish the end brickwork modifications.
insulation. Modifications of the headwalls between the “old” and
“new” sections were also required. In order to allow the normal The gas passage at the central baffle was closed with dense bricks,
operation of stage 1 furnace, a temporary crossover was installed separating in this way the end sections from the rest of the
between section 16, second flue wall peephole and section 53, furnace. In order to avoid any flow of gasses into the furnace,
third flue wall peephole. Figure 2 shows a scheme of this expandable baffles were located at the headwall windows, close to
configuration the fourth line of peepholes of section 16 and the first line of
section 53.
848