Contract Management Practice
Contract Management Practice
PROCUREMENT
April 2018 GUIDANCE
Contract Management
Practice
Published September 2018 – First Edition
Copyright © 2018
The World Bank
1818 H Street NW
Washington DC 20433
Telephone: 202-473-1000
Internet: www.worldbank.org
Disclaimer
This work is a product of the staff of The World Bank. The findings, interpretations, and
conclusions expressed in this work do not necessarily reflect the views of The World Bank, its
Board of Executive Directors, or the governments they represent.
This section explains the common abbreviations and defined terms that are used in this User’s Guide.
Defined terms are written using capital letters.
Bank The World Bank. IBRD and/or IDA (whether acting on its own
account or in its capacity as administrator of trust funds provided
by other donors).
Bidder A firm or joint venture that submits a Bid for Goods, Works, or
Non-consulting Services in response to a Request for Bids. To
improve readability, the terms “Bid” and “Bidder” are throughout
this guidance written as “bid” and “bidder” respectively.
Contract Except when used with defined terms such as Contract Manager
and Contract Management Plan, the term “Contract” is
throughout this guidance written as “contract.” Given the
Abbreviation / term Full terminology / definition
multiplicity of times that this term appears in this guidance, this
approach improves readability.
Contract Manager For the purpose of this guidance, “Contract Manager” is a generic
term used to refer to a legal entity, a natural person/team
assigned to/ authority vested on/ delegated to manage the
execution of a contract. Depending on the applicable contract
form, “Contract Manager” may refer to:
• a range of contract management arrangements such as
the:
o “Engineer” in FIDIC: Conditions of Contract for
Construction or Conditions of Contract for Plant
&Design build;
o “Employer’s Representative” in FIDIC: Conditions
of Contract for EPC/Turnkey;
o “Project Manager”, for example, in Bank’s SPDs
for Small Works; or
• the Borrower’s internal team when assigned to manage a
contract.
In generic contexts, and in contexts which require reference to
the Borrower such as in managing the Contract Manager
(Engineer, Project Manager etc.), the term “Borrower” is used.
Environmental and Social As described in the Bank’s Environmental and Social Framework.
Commitment Plan
Investment Project Financing The Bank’s financing of investment projects that aims to promote
(IPF) poverty reduction and sustainable development. IPF supports
projects with defined development objectives, activities, and
results, and disburses the proceeds of Bank financing against
specific eligible expenditures.
Procurement The function of planning for, and sourcing Goods, Works, Non-
consulting Services, and/or Consulting Services to meet required
objectives.
Procurement Documents A generic term used in the Procurement Regulations to cover all
Procurement Documents issued by the Borrower. It includes:
GPN, SPN, EOI, REOI, Prequalification document, Initial Selection
document, RFB and RFP, including any addenda.
Procurement Process The process that starts with the identification of a need and
continues through planning, preparation of specifications/
requirements, budget considerations, selection, contract award,
Abbreviation / term Full terminology / definition
and contract management. It ends on the last day of the warranty
period.
VE Value Engineering.
Introduction.............................................................................................. 1
Preamble ..............................................................................................1
Purpose ................................................................................................1
Scope ...................................................................................................1
Structure of the guidance ..........................................................................1
Contract management in Procurement Regulations ............................................2
The fundamentals ...................................................................................... 4
Upstream and downstream phases of a contract ...............................................4
Contract management objectives .................................................................5
Plan, do, check .......................................................................................5
Role of Contract Manager ...........................................................................6
Hard and soft skills...................................................................................6
Teamwork .............................................................................................8
Governance and management .....................................................................8
In-house vs. outsourcing ............................................................................9
Potential pitfalls ................................................................................... 10
Different Fit-for-purpose contract management ............................................... 15
Proportional ......................................................................................... 15
Supply positioning .................................................................................. 15
Managing relationships ............................................................................... 17
Successful relationship management ........................................................... 17
Plan and act early .................................................................................. 18
Relationship mapping.............................................................................. 19
Preparing a Contract Management Plan .......................................................... 22
Why plan ............................................................................................. 22
When to plan ........................................................................................ 22
How to plan ......................................................................................... 22
Contract start-up ...................................................................................... 24
Transition ............................................................................................ 24
Facilitating contract start-up .................................................................... 24
Some bottlenecks affecting contract start-up ................................................ 26
Contract Implementation: Managing time, cost, quality and risk ........................... 28
Three-dimensional approach ..................................................................... 28
Time control ........................................................................................ 28
Cost control ......................................................................................... 29
Quality control...................................................................................... 35
Managing Contract risks ........................................................................... 35
Managing contract change ........................................................................... 37
The need for change ............................................................................... 37
Change management procedures ................................................................ 37
Bank sanctioned firms or individuals............................................................ 38
Managing value engineering ......................................................................... 39
Definition ............................................................................................ 39
Benefits .............................................................................................. 39
VE at the design stage ............................................................................. 40
VE during contract implementation ............................................................. 40
Submitting a VE proposal ......................................................................... 41
Managing contractual disputes ...................................................................... 42
Contract disputes .................................................................................. 42
Dispute management .............................................................................. 42
Contractual remedies ................................................................................. 44
Contractual remedies ............................................................................. 44
Fraud and corruption .............................................................................. 47
Special considerations: Works and Plant contracts ............................................ 49
Project management software ................................................................... 49
Delays due to the Borrower ...................................................................... 50
Variations ............................................................................................ 51
Site visits ............................................................................................ 51
Contract Manager’s documents .................................................................. 52
Design and build contracts ....................................................................... 53
Contractor’s claims in construction contracts ................................................ 55
Construction contracts Taking-over ............................................................. 59
Defect Liability Period ............................................................................ 60
Special considerations: Managing ESHS Risks in Works Contracts ........................... 61
Background .......................................................................................... 61
Relationships and responsibilities ............................................................... 61
Overview of the Roles ............................................................................. 61
Contractor mobilization/contract initiation ................................................... 63
Contract implementation ......................................................................... 65
Contract Taking-over ESHS aspects ............................................................. 68
Defect liability Period-ESHS aspects ............................................................ 68
Special considerations: Goods contracts.......................................................... 70
Supply chain management ........................................................................ 70
Incoterms ............................................................................................ 71
Export restrictions ................................................................................. 72
Delay in L/C processing ........................................................................... 72
Special considerations: Information Systems contracts ....................................... 73
Software license agreements .................................................................... 73
Source code ......................................................................................... 73
Specialist project manager ....................................................................... 74
Systems requirements ............................................................................. 75
Quality of product ................................................................................. 76
Upgrades and discontinued products ........................................................... 77
Transfer of knowledge ............................................................................ 78
Value engineering .................................................................................. 79
Special considerations: Consulting Services contracts ........................................ 81
Supervision .......................................................................................... 81
Contract management ............................................................................. 81
Kick-off meeting.................................................................................... 82
Non-compliant deliverables ...................................................................... 82
Unsatisfactory performance ...................................................................... 82
Approving payments ............................................................................... 83
Time control ........................................................................................ 83
Key risks ............................................................................................. 83
Annex 1: World Bank contracting modalities .................................................... 85
Annex 2: Measuring performance .................................................................. 89
Annex 3: SAMPLE TEMPLATE - Contract Management Plan ................................... 92
Annex 4: SAMPLE TEMPLATE - Contract Mobilization ........................................ 102
Annex 5: SAMPLE TEMPLATE - Contracts Inventory Listing ................................. 105
Contract Management Practice
Introduction
Introduction
Preamble
Project implementation under Investment Project financing (IPF) normally includes procurement activities
needed to attain the project development objectives. The Borrower should be mindful that the pre-
contract award processes (such as comprehensiveness of project documents, proper planning, choice of
contract, appropriateness and quality of Procurement Documents, evaluation of bids/proposals etc.) all
contribute to the success of a contract. The Bank has other guidance in place to support Borrowers in the
pre-contract award processes.
Procurement, including contract management, is a critical component of budget
implementation/execution – as defined within the public financial management cycle. Financial controls
should be in place to ensure that funds are available in a timely manner and are used only for the intended
purposes. If there are issues in the budget planning and approval process, such issues should be identified
well in advance (e.g. during Project preparation) and appropriate arrangements put in place. Undue delays
in making contractual payments puts the Borrower at contractual default, potentially also affecting
contractor cash flow, resulting in contract implementation delays and other complications.
Effective contract management is essential to the delivery of the intended outcomes. This guidance assists
Borrowers in managing contracts (post- contract award) under IPF operations.
Purpose
The purpose of this guidance on Contract Management: Practice (guidance) is to support Borrowers’
contract management practice by illustrating some of the key aspects and issues. It should be kept in mind
that contracts shall be managed in accordance with the contract.
Scope
Contract management is part of the Procurement Process. The processes preceding contract award (such
as procurement planning, selection of contractors etc.) are described in detail in the various procurement
guidance.
This guidance focuses on the contract management activities undertaken during the period from the
award of contract to contract completion. Where applicable, this period includes the defects liability
period and/or warranty period.
1
Contract Management Practice
managing one or more of these categories may prefer to refer to the general provisions followed by the
category/ies of interest.
This guidance comprises of practical short case studies to illustrate relevant contract management
aspects. The guidance also comprises of some templates such as for CMP, which may be modified to suit
the needs of a contract.
There is also a separate excel based Contract Price Adjustment Computation Workbook to support
Borrowers in applying contractual price adjustments.
Section V. 5.97 Aim of contract The aim of contract management is to ensure that all
General management parties meet their obligations.
Procurement In addition, contracts shall be actively managed by the
Provisions Borrower throughout their life to ensure that contractor
performance is satisfactory, appropriate stakeholders
are informed and all contract requirements are met.
Annex I. 2.1 Value for Value for Money (VfM) is to be considered at all stages
Value for money of the Procurement Process, including during contract
Money management.
2
Contract Management Practice
Annex II. 7.1 j. Bank’s prior States that for contracts subject to prior review, if
Procurement review requested by the Bank, the Contract Management plan
Oversight including the KPIs will be subject to Bank’s prior review.
3.11 PPSD specifies The PPSD will identify those contracts requiring a
requirement Contract Management Plan.
for CMP
Annex XI. whole Content of This Annex outlines the requirements for Contract
Contract Annex CMP Management and for monitoring through the Contract
Management Management Plan (CMP).
Annex XIV. 2.1 CMP and PPP Contract management is one of the phases in PPP
Public-Private arrangements.
Partnership 2.2 Resources The Borrower needs to demonstrate that there is
(PPP) adequate institutional capacity to prepare, structure,
procure and manage the PPP project
4.1 Roles The Borrower shall ensure that the output specifications
include how performance will be monitored, including
roles for the government’s contract management team.
3
Contract Management Practice
The fundamentals
The fundamentals
Upstream and downstream phases of a contract
Contract management is the process of actively managing contract implementation to ensure the efficient
and effective delivery of the contracted outputs and/or outcomes.
Effective contract management enables Borrowers to maximize value for money (VfM) in delivering
development outcomes. The focus of contract management is on the activities that are undertaken during
the contract execution/implementation phase, following the award of contract (downstream activities).
However, the success of contract management is strongly influenced by upstream activities such as those
undertaken during the procurement planning, choice of contract, and contractor selection phase.
4
Contract Management Practice
To achieve good contract performance, Borrowers should ensure that the terms of the contract are
adhered to and that both parties to the contract understand their respective obligations. Contract
management also involves a level of flexibility by both parties and a willingness to adapt the contract
terms to reflect any changing circumstances, as appropriate. Good contract management is strengthened
by systematic and efficient planning, execution, monitoring, and evaluation.
5
Contract Management Practice
1. procurement;
2. project management;
3. legal knowledge (at the very least an ability to understand the legal aspects of the contract,
including remedies);
4. financial management;
5. analytics and reporting;
6. administrative, record keeping.
Additional skills may be required because of the subject matter or complexity of the contract. It is
essential to have access to sufficient skills and experience as and when required. For example:
6
Contract Management Practice
Feature Relevance
7
Contract Management Practice
Feature Relevance
Articulate, approachable, persuasive, good verbal and non-verbal
communication, listening skills; emotional intelligence, courteous.
Teamwork
Where a contract management team is formed, a team leader needs to be appointed with authority to
manage the team and clear lines of reporting. The team leader must ensure that the team members are
included and consulted as appropriate. Depending on the size and complexity of the contract, there may
be a core contract management team. Others, often additional experts required for the contract, may
then be called on as required.
Team members need to demonstrate the skills, experience or knowledge for their respective roles. It is
essential that they contribute to the team, are accountable for their areas of responsibility and are able
to communicate effectively to manage risk, coordinate activities and keep the contract to schedule.
8
Contract Management Practice
10. stakeholders are engaged at a level that is commensurate with their relevance to the contract and
in a manner that fosters trust;
11. culture of candid feedback and improvement.
1. In-house: contract management undertaken entirely by the Borrower’s staff, due to availability
of adequately qualified and experienced staff.
2. Outsourced: a specialist contract management entity is contracted by the Borrower to manage
contract implementation. The specialist entity may be: project management firm, engineering
firm, procurement agent.
3. Limited outsourced: the contract is primarily managed by the Borrower’s staff, with additional
resources from external experts, contracted as required. e.g. environmental, safety, IT
systems/solutions.
Outsourcing arrangements should provide sufficient oversight, checks and balances for the Borrower.
In deciding an appropriate outsourcing option, the Borrower would need to assess its capacity, against
the risk/complexity of the contract, in aspects such as:
9
Contract Management Practice
Figure IV– In-house vs. outsourcing: based on risk, complexity, capacity and capability
Potential pitfalls
Although there are a broad range of reasons for failures in contract management, not having the
fundamentals in place is often a major factor for poor performance. Common causes of poor performance
associated with inadequate fundamentals include:
1. insufficient planning prior to the transition from award of contract to the contract execution
phase;
2. poor communication;
3. insufficient resources (capacity and/or capability);
4. inadequate governance and/or confusion of responsibilities;
5. poor decision making;
6. vulnerability to fraud and/or corruption;
7. ineffective risk identification and mitigation;
Good contract management practice demands timely identification and management of issues. Examples
of causes of poor practice, and their consequences are illustrated in Table III.
10
Contract Management Practice
Cause Consequence
11
Contract Management Practice
Cause Consequence
• Decisions aren’t made at the right time, if at
all. Staff who have no authority make
decisions. Decision-making is inconsistent.
• Where the Borrower/Contract Manager fail
to adequately perform their part of contract
management, the contractor may take
control, resulting in unbalanced decisions
that are not always in the Borrower’s
interests.
12
Contract Management Practice
13
Contract Management Practice
After expiry of the Defects Select a contractor to Very high (new Very high
Liability Period remove Works affected contract with (the time needed to
(could have significant by the low-quality potentially higher select a new
implications on budget; time material and complete prices, plus the contractor and the
needed to secure it) the Works as per the cost of removing time needed to
correct specifications all Works execute the new
previously done; contract- could
potential loss of potentially be
use, loss of lengthy)
production etc.)
14
Contract Management Practice
Fit-for-purpose contract
Different Fit-for-purpose management
contract management
contracting modalities
Proportional
The time and other resources applied to manage a contract should be proportional to the size, scope,
complexity, duration, risk, and strategic importance of the contract. One size does not fit all.
For example, low-value, routine purchase for off-the shelf Goods normally require minimal contract
management efforts. On the other hand, a high-value, complex IT system that is strategically important
to the beneficiary agency will need a dedicated contract management team (including specialists), greater
monitoring, evaluation, risk management, sound decision making and relationship management.
Too many checks and balances can result in an overly bureaucratic culture that can delay decision making,
impede contractor payments and stifle value engineering and innovation. Too little control can result in
an undisciplined, crisis management culture. Getting the balance just right is the success to “fit-for-
purpose” contract management.
Supply positioning
A significant factor in designing a fit-for-purpose contract management strategy is identifying how critical
or important the Goods, Works, Non-consulting or Consulting Services are to the Borrower. This in turn,
indicates the approach to be taken to building the relationship with the contractor. For example, the
provision of hospital facilities and services in an at-risk district will be more critical to secure than the
procurement of office consumables (paper and pens) for a public-sector agency.
A useful tool to help this analysis is the “supply positioning matrix”. This is a model that helps Borrowers
to rank, in order of importance, their procurements, based on the value of the contract (including life-
cycle costs, if applicable), and the level of vulnerability (impact and consequences) to the agency if the
supplier (contractor) fails to deliver. If the Goods, Works, Non-consulting or Consulting Services are not
delivered on time, to quality (including environmental and safety standards) and at cost, how will this
affect the delivery of the development needs, and what will be the impact on the beneficiary
stakeholders?
The supply positioning matrix can be used at various phases in the procurement, from the planning and
market research phase through to contract management.
15
Contract Management Practice
The impact of the supply positioning in relation to the approach to contract management is described in
Table V. This is to be read in conjunction with the next section “Managing relationships”, as the two
concepts are closely linked.
16
Contract Management Practice
Managing relationships
Managing relationships
• securing senior level support for the contract • failure to prioritize managing the relationship
• ensuring that the governance arrangements are • discourteous or offensive styles of
robust and fair communicating
• open sharing of information • blame culture
• collaborative relationship (problem solving) • failure to communicate information that is
• ensuring that relationships between the parties important to the other party
are peer-to-peer as far as possible • failure by either party to fulfill its contractual
• ensuring that roles and responsibilities are obligations
clearly understood by all parties
17
Contract Management Practice
Engagement strategies for relationship management with relevant stakeholders would need to be
developed early. These can be included in the Contract Management Plan. The type of strategy and the
amount of resources applied to relationship management need to be in line with the needs of the
18
Contract Management Practice
individual procurement/project i.e. fit-for-purpose. A good start is to map the parties and their respective
relationships.
Relationship mapping
The typical contract management relationships are between the Borrower (project implementing agency,
Purchaser, Employer, Client etc.) and contractors, and the Borrower and consultants. Consultants may in
turn serve as Contract Managers thereby having contract management relationships with both the
Borrower and contractors. In addition, there is often a beneficiary group or stakeholders whose needs are
to be considered. For IPF funded operations, there is also the World Bank. Figure VII provides an example
mapping of these inter-relationships.
19
Contract Management Practice
contract management duties to internal staff to employing consultants to serve as “Engineer”, “Project
Manager”, “Employer’s Representative” etc.
Contractor to contractor
In small scale, less complex contracts, there is often no relationship between contractors. However, in
large scale, complex projects, with many dependencies and multiple contractors and sub-contractors, the
need to coordinate activities and manage these relationships i.e. interface management becomes
essential.
A systematic approach is required to streamline communications, effect good communications and apply
robust reporting systems. This involves identifying critical interactions and monitoring the progress of the
work. The interaction of the contractors could be related to:
1. physical interactions;
2. harmonizing functional requirements;
3. competing contractual obligations;
4. information exchange;
5. utilization of resources;
6. coordinating implementation schedules.
Not having an effective interface management system could negatively impact the cost and schedule of
the contract. Factors to consider when establishing an interface management system include:
1. assign a manager or consultant to be responsible for the interface between contractors and create
an interface team;
2. each contractor identifies a contact person with sufficient authority to work with the interface
manager for each party affected by the interface;
3. clearly define the roles and responsibilities of each interface team member;
4. share regular reports on performance and critical issues;
5. arrangements for effective resolution of differences or conflicts;
6. risk is assigned to the party best able to manage it. Emerging risks are shared and a common
management plan is agreed.
20
Contract Management Practice
The needs of the beneficiary/stakeholder groups should be understood, their requirements and concerns
should be communicated to the contractor/consultant, and the risks and issues formally addressed. This
requires a degree of ongoing coordination and channels of communication, so that end-users/community
groups have a voice. The Borrower should develop a stakeholder engagement plan to keep end-users and
communities engaged during contract execution. This is particularly important in large infrastructure
contracts which have a significant impact on end users/communities. Environmental and Social specialists
would need to actively support these relationships.
1. better control of the contract’s implementation and operational risks, leading to improved
contract outcomes;
2. reduced incidence of fraud and corruption (communities can often act as active watchdogs);
3. better awareness of ESHS issues (including Gender Based Violence (GBV) and Sexual Exploitation
and Abuse (SEA));
4. opportunity to identify and address grievances in a timely manner;
5. increased ownership and sustainability.
21
Contract Management Practice
Why plan
Planning how, when, where and by whom a contract will be implemented, monitored, managed and
administered is an important step to ensure that what is procured will be delivered. A Contract
Management Plan (CMP) provides a structured and systematic approach. An example CMP is provided in
Annex 3.
When to plan
The Borrower begins development of the CMP as early as possible in the procurement process. Preferably,
the plan is expected to be completed when signing the contract. In practice, it may be promptly thereafter.
How to plan
The CMP should be fit-for-purpose. This means that the level of detail and length of the document should
be proportionate to the scope, value, risk, complexity and duration of the contract. Typically, a CMP will
cover some, if not all of the following:
1. contract management roles and responsibilities (ensure that each party has established the
necessary authorizations and delegations for its personnel at the beginning of the contract as this
is an important prerequisite to ensuring that all contracting decisions are valid and enforceable);
2. list of key contacts (e.g. the names and contact details of the key contacts for the Borrower and
the contractor);
3. contract management system;
4. governance structure;
5. contract documents (including key contractual terms and conditions);
6. key milestones (including the critical path);
7. Key Performance Indicators (KPIs) and a description of the standards or measurement process, if
relevant;
8. key contract deliverables (identified and properly described, and updated to account for change
orders during the execution of the contract);
9. reporting requirements (types of reports, times, contents etc.) and lines of reporting;
10. payment procedures consistent with contractual provisions;
11. record keeping requirements and procedures;
12. audit or independent assurance requirements;
13. change management or contract variation procedures;
22
Contract Management Practice
The CMP should be shared with the contractor and all parties involved in contract implementation,
management, administration and governance. The Borrower is advised to discuss the plan with the
contractor (face-to-face) to ensure that it is fully understood, especially the allocation of risks and
responsibilities.
Risk register
A risk register may be initiated in the initial stages of Project preparation (such as the environmental and
social risks identified in the Environmental and Social Commitment Plan) and developed further at key
milestones such as design finalization and preparation of Procurement Documents. The risk register
should be reviewed and updated (with contractor’s input) during contract award/signing of contracts and
included within the CMP as a practical tool to support effective contract management.
23
Contract Management Practice
Contract start-up
Contract start-up
Transition
Transition is the initial period between contract award and the start of contract implementation. In some
circumstances, this transition period may involve a changeover from a previous contractor to a new
contractor. Depending on the nature and circumstances of the contract, the transition may require
planning.
Where such effectiveness/commencement conditions exist, the Borrower should ensure that it meets its
obligations in a timely manner. If this does not happen, it could lead to delays in start-up, cost
compensation requests by the contractor, and even termination of the contract.
Generally, the Borrower/ Contract Manager needs to take the following actions:
24
Contract Management Practice
6. verify adequacy of any insurance policy taken out by the contractor (see below on insurance);
7. if the contract applies a letter of credit as an instrument for payment, ensure that an error free
letter of credit is issued in a timely manner;
8. for Works- related contract, ensure that the contractor has submitted required ESHS
documentation as required by the contract.
Insurance
Insurance provisions are valuable risk management tools. The Borrower has to ensure that:
Amount: Does the insured amount properly cover the requirements of the
contract?
Coverage: Does the policy fully cover all general and specific risks that may occur on
the site?
Continuity: The Borrower should check proof of payment of insurance premiums and
periodically request confirmation from the insurance company (say twice
a year) that the respective policies are still valid.
Validity: Is the policy valid for the entire period required by the contract? Did the
contractor submit the proof of paying the premiums to the insurance
company? If payments are to be made by the contractor periodically, the
Borrower would need to periodically request evidence of payments.
Insured parties: Does the policy expressly name both the Borrower and the contractor as
jointly insured? Policies where only the contractor is insured are not
acceptable as they transfer the entire risk on the Borrower.
25
Contract Management Practice
Exclusions: Are there any exclusions? The Borrower should check the exclusions of
the policies and should request that the insurance company confirm the
exact list of exclusions and their applicability.
Deductibles: These represent the amounts that the insured party must cover from its
own funds when an insured event occurs. Higher deductibles translate
into cheaper insurance premiums, but also in higher risks, because the
contractor and/or the Borrower will need to cover more of the damage.
The Borrower should check the adequacy of the deductibles.
Terms and conditions: Check any terms and conditions that may render the policy invalid and
under what circumstances or events. The Borrower should check any
conditions attached to the insurance policies such as prior notification
requirements and any other clauses that may affect its rights under the
terms of the policy.
Permits
If the Borrower must acquire planning, zoning, building permits or similar permissions for the Works,
these should be obtained early in the process to allow effectiveness/commencement. If the processes for
obtaining such permits is cumbersome or lengthy, the Borrower should plan to initiate the process well in
advance and take adequate measures to mitigate the risk of delays. Such measures may include:
Access to site
A common cause of complications in infrastructure contracts is delay in giving the contractor access to,
and possession of, the site within the time stated in the contract. If no time is stated in the contract, the
Borrower should give the contractor access and possession within such time that enables the contractor
to proceed in accordance with the agreed program.
If the start of the program is delayed, this may result in time extensions for the Works, and increased costs
to the Borrower. Given the consequences, it is good practice that Borrowers prepare themselves well
before award of contract to enable them to readily give the rights of access and possession in accordance
with the contract.
26
Contract Management Practice
Letter of credit
Where the Borrower has to arrange a letter of credit, it is important that this is done in a timely manner
(to allow the Goods to be shipped) and that the letter of credit is in the correct form. Errors in the letter
of credit, require formal amendments, and this process results in delays. Further, as a copy of the issued
letter of credit is a key document for the Bank to disburse funds using the “Special Commitment”
disbursement method, it is important that the letter of credit is operational (e.g. with valid expiry date).
Customs clearance
Even if not normally an effectiveness condition, any expected custom clearance bottleneck should be
addressed by the Borrower as early as possible. Customs clearance can in some places involve complex
and lengthy processes. Delays can be caused by:
27
Contract Management Practice
Contract Implementation: Managing time, cost,
quality and risk
Contract Implementation: Managing time, cost, quality and risk
Three-dimensional approach
Time, cost and quality can be seen as three constraints within which the contract needs to be delivered.
Changes in one constraint may necessitate changes in another to compensate.
The Contract Manager should be mindful of how any change in one constraint could impact the others
and affects the contract risks.
Time control
An essential part of contract management is identifying the critical path. The critical path is the sequence
of activities, which add up to the shortest time possible to complete the contract. Identifying the activities,
the sequencing and other dependencies, and estimating times for completion, are the first steps in
developing a robust and realistic schedule for contract implementation.
1. developing a comprehensive, practical and realistic schedule of key activities (this may include
key deliverables and milestones and projected contract completion date);
2. undertaking a quality assurance check of the schedule including identifying any flaws in logic or
faulty assumptions;
3. ensuring that the Borrower/Contract Manager and the contractor are working to the same
schedule;
28
Contract Management Practice
4. implementing an effective tool or system to track and monitor progress against the schedule;
5. ensuring early intervention when a potential or actual delay is identified;
6. implementing appropriate action to mitigate or manage a delay and recording the decision/s.
Time extensions
The Contract Manager will often be required to decide when it is appropriate to allow a time extension.
How the Contract Manager resolves delays will depend on the facts and circumstances of the delay, and
always based on the contract. These could be, for example, a delay that:
1. is due to the Borrower being in default (e.g. failing to carry out its contractual responsibility which
impacts on the contractor’s ability to progress the work);
2. is due to new or extra work/services not included in the original scope.
Cost control
Managing costs is essential to ensure that the contract is delivered within the contract price. The approach
to managing costs will depend to some extent on the nature of the contract. The Contract Manager should
put in place appropriate financial systems and reporting mechanisms that record the budgeted costs, track
actuals and provide alerts where there are cost overruns. Ideally, the contract management system should
be integrated with the financial management system of the government or the project as the case maybe.
The key elements of a contract inventory report embedded within such a system, are indicated in Annex
5. It would be helpful to have an assigned person for tracking costs against actual and reporting to the
Borrower.
1. The Borrower’s design has flaws. • On discovering the flaws, the contractor notifies the
2. The Borrower’s design is not capable Contract Manager in accordance with the contract.
of being implemented or constructed. • This may trigger a variation order and likely result in a
cost increase.
29
Contract Management Practice
Price adjustment
Some contracts allow the price to be adjusted where, for example, local or foreign inflation is expected to
be high. If applicable, the process for adjusting the price is detailed in the contract, including the
appropriate formula to be applied. Contract cost control mechanisms include monitoring the correct
application of price adjustment provisions, where included in the contract.
A separate excel based Contract Price Adjustment Computation Workbook is available to support
Borrowers in applying contractual price adjustments.
30
Contract Management Practice
The following case studies illustrate the application of price adjustment provisions.
If a foreign currency component (say US$) of the contract price (or a portion of the contract price, such
as pavement work) is made of the costs of fuel, bitumen, equipment and spares for 20%, 30% and 40%
respectively with a fixed portion of 10%, the formula for adjustment of this US$ portion of the Contract
Price would be:
Where F, B and Eq are respectively indices for fuel, bitumen and Equipment respectively, c refers
to the current value of an index and 0 refers to the base value - at the Base Date of the contract
which is normally specified as the date 28 days prior to the bid submission deadline. It is reasonable
to expect that the bidder was aware of the various costs at this Base Date when preparing and
submitting the bid/proposal.
If an index Ix for a given input (input X) from a country (country B) that is different from the country of
the currency of payment (Country A), corrections must be applied. Let us see the variation of the price
of Input X from country A, using its cost converted to the currency of Country A:
(i) at the Base date the measurement of index value for Input X would provide the following data:
[Ix0*value of one unit of currency of country B in currency of country A on the Base Date]
whereas
(ii) at a certain current date, the measurement would provide the following data:
Hence the variation of cost of input X measured from country A, using its cost converted to the currency
of Country A would be:
31
Contract Management Practice
During the same time, the Country B currency has considerably weakened against Country A currency
and the following is observed:
Ix0 = Value of one unit of currency of country B in currency of country A on Base Date = 0.4
Ixc= Value of one unit of currency of country B in currency of country A on current Date = 0.2
Scenario 1: If no correction were applied, the payment would be adjusted by a factor of Ic/I0 (or 2.0),
unduly because the cost of the given input did not fluctuate in the currency of payment, which is the
currency of Country A.
Scenario 2: If the correction were applied incorrectly for instance, by using the following formula in which
the sequence of “country A” and “country B” has been inverted:
The adjustment factor would turn out to be or 2.0 x 0.4/0.2 which equals 4.0! Obviously, the given
payment would be unduly adjusted by a large factor on account of the given input, when actually no
adjustment was justified.
Scenario3: If the correction to the currency of payment is correctly applied the actual adjustment to the
contract price in the currency of Country A (currency of Payment) would be:
The value of which is 1.0, reflecting that no adjustment will be made on account of the given input. Note
that in the real world, the value of this factor may be different from 1.0, but normally not very
substantially.
32
Contract Management Practice
In determining contractual price adjustments, the Borrower/Contract Manager applied the formulae
to the amount of payment due expressed in the local currency, e.g. before converting the amount to
the currency(ies) of payment, and then wrongly added up all the amounts obtained expressed in the
local currency prior to breaking down the resulting sum according to the currency split which is the
method of the said Alternative A.
Such errors defeat the purpose of having a different price adjustment formula for each payment
currency, and may result in excessive payment to the contractor for price adjustment in one or more
of the stronger currency(ies) as the related payment may unduly “benefit” from a higher inflation in
another currency, in particular if the inflation rate in the country of the Borrower is, for example, a
two-digit figure.
33
Contract Management Practice
Replacement of indices
During the term of a contract, the publication of a given price index may have discontinued, or the index
value may have been reset to 100. In such cases, the Borrower needs to proceed with a new index or the
reset index, with some adjustment. If the source of publication of the discontinued index (say Iold)
recommends the use of another applicable index (Inew) from a date i, then after the date i the factor
[Ioldc/Iold0] should simply be replaced with [Ioldi/Iold0*Inewc/Inewi]. The new index takes over from the
old one after “date i”.
There may also be cases when a (technical) amendment to a contract may require modifying the selection
of a specific index or the weightings in the price adjustment provision, e.g. lime was to be used in the
original contract but is deleted early in the contract and cement used instead for soil stabilization. In such
cases, the formula(e) should be amended by contract amendment, to reflect the changes in both the
indices to be used and perhaps the weight of the corresponding inputs (the old and the new ones) in
contract price whenever a renegotiation of unit rate is also necessary.
Formula redesign
Normally, a price adjustment formula established at the time of award of the contract will be used
throughout contract implementation. However, there may be exceptional circumstances which require
that the price adjustment formula be redefined at some point in time during the term of the contract. This
may happen for relatively long execution period contracts, or when the cost of a given input (input
reflected by an Index “I”) is subject to an exceptionally high variation. In such case, the continued use of
the same linear price adjustment formula using same Index “I” may distort the price adjustment.
Box VII – Case study: redesign price adjustment formula during contract term
Assuming Ic is as high as two times the value of I0 at the Time 1, whereas the other indices are supposed not to
have varied at all, the adjustment produced by the formula at Time 1 would be:
Adjusted Price = Base Price* [0.10+ (0.40*0.9/1.10) * Ic/I 1 + (0.30 * 0.9/1.10) * Bc/B1 + (0.40 * 0.9/1.10) *
Cc/C1]
34
Contract Management Practice
Quality control
It is good practice to monitor and assess quality as the contract is being implemented. This ensures that
quality is controlled and consistently delivered. There are many different types of quality management
and control systems. It is important to select an appropriate system or methodology based on the nature
of the contract. The system should be agreed with the contractor and put in place before the contract
commences.
3. Poor quality assurance tests or • Redesign the quality assurance tests or inspections to
inspections do not identify issues with ensure that quality issues are found and dealt with.
the quality being delivered.
4. Fraud and corruption result in inferior • Report suspected fraud and corruption to the Bank.
materials being used and poor-quality • Apply appropriate contractual remedies.
outputs.
1. Has the contractor provided an update of the work program and has the Borrower reviewed this
against the schedule for the release of land (to enable the contractor to proceed without delay)?
35
Contract Management Practice
2. Has the Borrower provided the necessary permits that it is responsible for?
3. Has the Borrower provided the designs and drawings to contractors (when required by the
contract);
4. Have any risks related to the process for making contractual payments been mitigated?
5. Is the process for responding to contractor’s notices operating as envisaged?
Any new risk that is identified should be analyzed, and mitigation measures allocated prior to the risk
materializes and becomes a bottleneck to contract implementation.
36
Contract Management Practice
1. as early as possible during the contract execution phase, establish a formal and documented
change management process consistent with the scope of the contract and contractual change
management procedures;
2. have appropriate forms and clear procedures for requesting a change proposal (or change order),
estimating the change (e.g. scope, costs, implications and risks), and approving the change
proposal (the SPD- Plant, for example, includes relevant change order procedure and forms);
3. clarify who is responsible for what during change management, and ensure that individuals have
clear delegated authority to act, or to escalate change requests where there are issues;
4. familiarize those involved in contract change management (e.g. contract managers, consultants,
contractors) with the procedures, documents, decision making process and record keeping
requirements;
5. identify areas susceptible to change, evaluate risk, and proactively manage those areas;
6. ensure timely communication of change information to the relevant people;
7. make sure all relevant factors are considered when assessing change proposal (e.g. in terms of
technical, quality, impact and risks (including on ESHS, if applicable), time and cost);
8. monitor the change management process to ensure that proper procedures are being followed;
9. ensure that changes are captured as Addenda to the contract, and approved at the appropriate
level specified in the contract;
10. unless contractually justified and/or due to emergency situation, do not order or execute changes
to a contract without the appropriate change documentation;
37
Contract Management Practice
11. comply with the Bank’s requirements for prior review to changes to a contract;
12. adhere to the Bank’s requirements where the changes relate to a contract with a firm that has
been sanctioned by the Bank (see below);
13. keep records of all change orders, including the reasons;
14. at contract close-out, evaluate the changes and their impact/s on the contract cost, schedule and
performance for future use as lessons learned.
The key phrase for such contract amendments is “material modification.” What constitutes a material
modification needs careful assessment on a case-by-case basis.
38
Contract Management Practice
Definition
The term ‘value engineering’ (VE) refers to a technique for improving the value in a contract. Value can
be increased by either improving the function or reducing the cost. It is sometimes described as “providing
the necessary function/s at the optimal cost”.
VE involves a systematic method of analysis. It requires the examination of the function of the contract,
system, product, item of equipment, building, facility, or service, with the objective of improving
performance, reliability, quality, safety, and/or costs (including life-cycle costs). VE could result in the
reduction of time or the substitution of better materials, more efficient methods, or less expensive inputs,
all without sacrificing the needed functionality, longevity, or reliability. The fundamental premise is that
the basic function/s is preserved and not reduced because of a VE improvement.
Benefits
VE analysis could help the Borrower to realize benefits such as:
1. design improvements;
2. cost savings;
3. improved constructability;
4. accelerated incorporation of new materials and construction techniques;
5. elimination of unnecessary functions and establishment of combinations of functions that are
more responsive to the needs of the Borrower;
6. reduced environmental impacts;
7. reduced schedule;
8. reduced risk;
9. improved operations;
10. greater opportunity for stakeholders’ participation in the process;
11. improvement of standards and/or policies.
VE may be undertaken at various stages during the procurement, including:
1. concept design;
2. preliminary design;
3. submitted proposals and before the decision to award the contract;
4. final design stage;
39
Contract Management Practice
1. how the benefits arising from the VE will be shared between the parties;
2. the process for the contractor to prepare and submit a VE proposal;
3. that the VE proposal is prepared at the contractor’s cost, and the decision of whether to adopt
the VE proposal rests solely with the Borrower/Contract Manager;
4. the acceptable reasons for initiating a VE proposal, such as: reduction of costs to the Borrower,
enhanced performance, shortened completion time, or the creation of some other benefit/s to
the Borrower.
Undertaking a VE workshop at the initial design stage may result in enhanced benefits for the contract.
Workshop activities may include:
During contract implementation, VE improvements may be applied if provided for in the contract. A
contractor working on site every day is in a good position to identify VE opportunities and can provide a
fresh approach to the construction methods or materials that could reduce the cost and/or time.
40
Contract Management Practice
Submitting a VE proposal
When the contractor makes the decision to submit a VE change proposal, the contractor would need to
realize that the chance of the proposal being approved depends on the completeness of its preparation
and the demonstrated benefits (value) to the Borrower. Sufficient information must be provided so that
the Borrower/Contract Manager can conduct a thorough evaluation within a reasonable period. Failure
to provide adequate data may result in a request for additional data (which could delay the process) or
may even result in the rejection of the VE proposal.
The following is generally good practice information (for exact required information, refer to the subject
contract), for a contractor’s VE proposal:
1. the proposed change/s, and a description of the difference to the existing contract requirements;
2. sufficient ESHS information to enable an evaluation of ESHS risks and impacts (for Works related
contracts, for example);
3. a full cost/benefit analysis of the proposed change/s including a description and estimate of costs
(including life-cycle costs) the Borrower may incur in implementing the VE proposal;
4. a description of any effect(s), implications or risks of the change on performance/functionality;
5. a description of the comparative advantages and disadvantages of existing contract requirements
and the VE requirements;
6. a justification when an item’s function or characteristic is being changed and any effect of the
change on the end item’s performance;
7. any pertinent objective test data;
8. any contract requirements that must be changed if the VE proposal is accepted, including any
suggested specification revisions.
41
Contract Management Practice
Contract disputes
Contractual disputes could be time-consuming, expensive and difficult. They can damage
Borrower/contractor relationships, cause delays and negatively impact contract execution. They could
also substantially increase the contract price. It is therefore in the interest of contracting parties to work
at avoiding disputes in the first place. This can be achieved, among other things, through developing good
communications and working relationship management with the contractor.
To minimize contractual disputes and complication, all parties would need to effectively carry out their
duties in accordance with the contract. For Works contracts, for example, as mentioned in the section
Special Considerations: Works and Plant Contracts, the Contract Manager (Engineer, Employer’s
Representative etc.) has a key role in effectively handling matters for its determination and claims.
Despite best of efforts, matters may elevate to the level of disputes. When they do, every attempt should
be made to find an efficient and cost-effective resolution including through amicable settlement. The
dispute should be managed actively and positively and at the right level/s. A quick resolution saves time,
money and effort at later stages, if the dispute remains unresolved. On the other hand, delays in
resolution can lead to rapid escalation of costs and further damage to relationships and ultimately
termination of the contract.
Dispute resolution, in its widest sense, is any process which can bring about the conclusion of a dispute.
Techniques range from the most informal discussions, through to formal negotiations, mediation and
arbitration. Arbitration and litigation should be considered as resolution methods of the last resort.
Dispute management
Contracts should set out the procedures to be used when a dispute arises. Often these will focus on formal
processes such as arbitration. For major contracts (such as Works, Plant), the contract documents specify
the role of the Contract Manager (Engineer, Project Manager etc.) in making determinations on claims.
All parties are expected to act in accordance with the contractual provisions in this regard.
1. adjudicator,
2. dispute review expert, or
3. dispute review board.
If the contract provides for the appointment of such a dispute resolution mechanism, contracting parties
should ensure that the mechanism/s is put in place in a timely manner. Trying to establish this mechanism
after a dispute arises is a recipe for failure. Contracting parties should do their part to ensure the effective
operation of the chosen mechanism.
If a party is not satisfied with the outcome of the mechanism in place to settle disputes, it is in the benefit
of the parties to try to settle a dispute amicably before the commencement of arbitration. Amicable
42
Contract Management Practice
settlement if carried out professionally and in good faith could save contracting parties time and cost
while preserving their working relationships.
Arbitration
Contracts with international firms should apply international commercial arbitration in a neutral venue
unless the national regulations and arbitration procedures are acceptable to the Bank. International
commercial arbitration has many advantages compared to national courts. As contracting parties
(contracts with foreign contractors) come from different jurisdictions around the world with different
legal, cultural, political and ethical contexts, international commercial arbitration provides a neutral venue
to settle disputes effectively. Borrowers should utilize this facility if the need arises.
Some of the aspects that may help in preparing for an arbitration include:
1. check the pre-arbitration procedures in the contract and assess whether you have complied with
them;
2. conduct an early case assessment with legal advisors at the outset of the dispute, and review
periodically as the arbitration progresses. This helps to get an early sense of potential outcomes
and costs of the arbitration and make necessary preparation accordingly;
3. brief relevant management/authorities on: what the arbitration will be about, why the parties
have been unable to resolve the dispute, how long the arbitration may take, expected costs and
outcomes;
4. advise concerned staff and managers that an arbitration is about to be initiated so that they will
be readily available (if needed) at the arbitration hearing (if possible, it may be a good idea to
book possible hearing dates in their diaries to ensure their availability);
5. manage the risk of internal and external communications on the issues in dispute: relevant
Borrower staff would need to be advised to avoid any internal or external communications
outside of the established contract management protocol with legal counsel advice;
6. document retention notice: advise all involved to preserve/retain relevant documents by
explaining the nature of the documents and how to retain them. In international arbitration
documentary evidence is very important. Where the contract had a systematic recording
mechanism, this may not be an issue.
43
Contract Management Practice
Contractual remedies
Contractual remedies
Contractual remedies
Contractual remedies are available for both the Borrower and the contractor. The main purpose of such
remedies is:
3. calling ESHS performance security • contractor breaches its ESHS obligations under the
contract.
4. applying liquidated damages (delay • when the contract/sections of contract are not
damages) completed within time stipulated.
1. extension of time for completion, • Borrower is in default of the contract: e.g. delayed
2. cost compensation drawings or instructions, failed to provide access to
and possession of the site.
44
Contract Management Practice
Performance security
The performance security is an important contractual remedy tool. Despite having this provision in the
contract, Borrowers/Contract Managers may not apply/enforce it adequately.
Liquidated damages
Another important remedy instrument that the Borrower/Contract Manager can use is liquidated
damages (or liquidated damages for delay i.e. delay damages).
Contracts normally provide a percentage or an amount to be deducted from the payments due to the
contractor if it fails to deliver the contract within the stipulated time. There is usually a limit on the
aggregate amount (say, 10% of the contract price), and sometimes there is also a contract termination
consideration once the aggregate amount of liquidated damages amount has reached this limit.
It is important to have a payment schedule that allows for the deduction of liquidated damages. For
example, if the payment schedule was front-loaded and the contractor has already received 95% or 100%
of the contract price, the Borrower would need to invoice and pursue the contractor to receive the
damages due through other means.
Termination
Termination of a contract is the ultimate remedy for default. The table below summarizes some of the
key issues observed when Borrowers try to terminate a contract.
45
Contract Management Practice
2. No contractual justification for the • Before initiating the termination, check that
termination. the breach is described in the contract as a
cause for termination.
3. Not complying with termination procedures • Before initiating the termination, check the
as set out in the contract. This may lead to procedures and follow them.
the following issues:
a. manner the contractor leaves the site and
the Borrower entering to have the works
completed;
b. valuation at date of termination;
c. determination of payment including
amounts for any loss or damage.
4. Following termination, lack of timely action • Quickly assess the status of the Works and
by the Borrower in completing the remaining decide the most feasible option to complete
Works leading to deterioration of the the remaining Works e.g. force account, open
components of the contract already delivered bidding, limited bidding, direct contracting
(e.g. an incomplete road is left to deteriorate etc.
for months).
Table XI – Contract termination issues
46
Contract Management Practice
Issue:
Termination due to the alleged contractor’s default was indefensible.
Lessons to be learnt:
1. Understand the provisions of the contract and how they apply;
2. Apply the contract provisions;
3. make payments on time when Work has been delivered in accordance with the contract;
4. be mindful of the consequences of undue delay in payments to a contractor, which in this case,
resulted in stopping site operations because of cash flow problems;
5. “crying foul” after creating a problem does not help.
Box IX – Case study: Borrower causes the problem
Any suspicious F&C related activities should be promptly reported to the Bank’s on the online Integrity
Complaint form:
https://intlbankforreconanddev.ethicspointvp.com/custom/ibrd/_crf/english/form_data.asp
In summary:
1. contracting parties and all those that are involved in the delivery of the contract, are required to
observe the highest standards of ethics and refrain from F&C during the procurement process and
contract execution of Bank-financed contracts. All parties involved in the execution and
management of contracts should therefore hold themselves and their staff to the highest levels
of integrity and professional conduct;
2. contracting parties should take F&C seriously and take appropriate remedial actions (such as
removal of personnel from site and contract termination);
3. the Bank has the right to inspect the Site and/or the accounts and records relating to the
procurement process, selection and/or contract execution, and to have such accounts and records
audited by auditors appointed by the Bank if requested by the Bank;
47
Contract Management Practice
4. any obstruction to impede the exercise of the Bank’s inspection and audit rights constitutes a F&C
with all the consequences.
F&C practices could manifest themselves in different forms. Not all poor contract execution may
necessarily be attributed to F&C. Some examples of F&C red flags include the following:
48
Contract Management Practice
Managing infrastructure contracts such Works and Plant demand additional considerations in addition
to the generic aspects described earlier.
Infrastructure contracts (such as the FIDIC Conditions of Contract for Construction, 2017 (Red Book))
require that the work program is prepared and revised using the programming software named in the
specification (if not stated, the programming software acceptable to the Engineer). There are many types
of software that are based, for example, on tracking the critical path (Critical Path Methodology (CPM)).
The Borrower may choose software which has been reviewed and pre-approved. If the Borrower wishes
to name a software in the specification, it is recommended that at least three choices of software is given,
with the words “or substantially equivalent” added. If not included in the specification, the Borrower
should ensure that the contract management software to be used by the contractor is fit for the purpose
of the contract.
The software chosen to support contract implementation should serve at a minimum to:
49
Contract Management Practice
The Borrower/Contract Manager should use the software to determine if the contract is starting to fall
behind. It may also give an early warning that the contractor is having difficulties that may result in a claim
against the Borrower. This could be done, among other things, by:
1. requiring that major revisions to the contractor’s work program should be preceded by a full
documentation of the status of the contract. Minor revisions (such addition of changes and
unanticipated events to the last update to determine their impact) may be done on a
contemporaneous basis;
2. requiring a full and complete update of the status of the contract prior to modifying the approved
baseline plan;
3. checking that the actual start and finish dates and remaining durations for work in progress
matches the actual situation on the ground;
4. carefully reviewing to determine if the contractor is deviating from its plan and the reasons why;
5. reviewing the near-term critical and near-critical paths so that the risk is mitigated in a timely
manner;
6. checking signs of understaffing or lack of progress on non-critical but soon to be critical activities.
50
Contract Management Practice
Variations
Considerations to managing variations in Works admeasurement contracts. These may include:
1. verifying supporting documents (specifically to check how appropriate or necessary are the
proposed variations);
2. checking how the variation was valued (i.e. were the existing contract rates correctly applied; if
new rates were used, were they correctly constructed based on fair market prices etc.);
3. checking if a change in unit rates would be appropriate or required according to the contract;
4. checking if the time impact (extension of time for completion) has been correctly assessed and is
duly justified;
5. checking if the variation has taken due consideration of ESHS aspects, as applicable;
6. checking the level of approval required for the variation (e.g. approval by the Contract Manager
or Borrower).
Site visits
One of the key responsibilities of the Borrower throughout the execution of an infrastructure contract is
to maintain a good understanding as to what is happening on site. This cannot effectively be done without
inspecting the site. Borrower’s technical experts should be actively involved in the site visits and it is
recommended that the Borrower undertakes joint site visits with the Contract Manager. This will ensure
that any issues identified during the site visits can be discussed with the Contract Manager, and
appropriate action agreed.
The Contract Manager should undertake regular site inspections to ensure activities are progressing in
accordance with the contract requirements. The Contract Manager should ensure that it has the right
skills available to inspect the activities being undertaken and that inspections are regularly carried out
jointly with the contractor.
The types of aspects that are expected to be checked during a site visit inspection include:
51
Contract Management Practice
52
Contract Management Practice
Success factors
Borrowers would need to be mindful of the following factors, which may demand a cultural shift away
from the DBB approach, when managing D&B type contracts:
1. D&B requires a higher level of trust and partnering comparing to the DBB approach;
2. D&B requires the Borrower to develop definitive, functional driven performance criteria as
opposed to detailed design and drawings;
3. D&B is a scope driven effort;
4. the contractor owns the design;
5. establish the contract management team early and keep it together;
6. designers have been doing design for Borrowers and constructors have been doing construction
of the designed Works in the traditional approach (DBB) whereas this approach demands a
construction team integrated with design professionals;
Performance/functional criteria
It is helpful to realize that in DBB, requirements are communicated to the contractor through complete
drawings and specifications. In contrast, the Borrower communicates its requirements for a D&B contract
through the description of the performance/functional criteria. The contractor develops the design based
on the latter.
Design review
In D&B approach, because the contractor owns the design, the Borrower’s/Contract Manager’s design
review, unless otherwise specified, is normally to verify that the design solution/s comply with the
performance criteria. The main reason for this shift is the need to ensure that the design liability remains
with the contractor.
1. breakdown of the design scope into specific features of tasks (that can be designed, reviewed,
approved and constructed in that order) and identify features where the contractor may have
design flexibility;
53
Contract Management Practice
2. identify the features that have limited or no option for variance during the design process so that
there is clear understanding from the outset;
3. identify any design criteria that may have been incorporated by reference in the contract;
4. identify any features whose design is contractually open to interpretation;
5. discuss the list of preliminary design solutions for all features of Works in scope;
6. discuss the Borrower’s/Contract Manager’s review process of design submittals and establish a
communication system;
7. develop a system whereby a difference of professional judgment that is not clearly covered by
contract language can be expeditiously resolved.
Contract administration
DBB contract administration is based on the administration of the design consultants, and their
deliverables, and administration of the construction contractor. In a D&B contract, both the design and
construction are the responsibility of the contractor.
The cultural shift from a DBB to a D&B contract administration demands that both the Borrower and the
contractor create a contract administration system that supports the development of design and is
responsive to the D&B contract. The Borrower/Contract Manager needs to be aware of the time element
in D&B administration and the fact that the contractor expects the Borrower/Contract Manager to
collaborate by expediting design reviews. Given the significance of close coordination during the design
phase, it is recommended to require that the contractor has an experienced design professional to
manage the internal and external coordination during the design phase.
If the Borrower has separate design and construction administration systems, they both need to be
integrated and operating throughout the delivery of a D&B contract.
Payments
The scope of a D&B contract is defined by a set of performance criteria to be completed within a specified
period. This normally requires the contractor to offer a lump sum price (broken down into activities to
facilitate payments). As cost and time are already set-out in the contract, quality is constrained by both
cost and schedule. As a result, at the outset of the contract, it is important to both the contractor and the
Borrower to have a clear understanding and agreement on the requirements for quality.
Constructability
One of the stated benefits of a D&B approach is improved constructability due to significant contractor’s
input during the design phase. Unlike DBB, a D&B contract design can be thought to be under continuous
constructability review. To maximize the benefits of a continuous constructability review, the D&B
contract administration system must play an enabling role to facilitate this critical process.
Progress payments
Borrowers are normally used to unit price contracts where measured quantities of unit price items are
used to compute progress payments and where the risk for quantity overrun is absorbed by the Borrower.
54
Contract Management Practice
The transition to a lump sum D&B contract should be carefully managed to ensure that the contracting
parties understand the financial implications.
Prior to the first progress payment, in order to facilitate payment, the two sides may agree on a schedule
of values i.e. breakdown of each lump-sum item in the contract into component parts of design
deliverables or construction Works for which progress payments may be requested. This essentially
requires the D&B contractor to assign a value for each activity in its program. Such a schedule of values
should include enough details to facilitate continued evaluation of payment application and progress
reports. Upon review and approval by the Borrower/Contract Manager, this allows the development of a
periodic payment estimate to be made for those activities that were underway during the pay period. This
helps the Borrower/Contract Manager to ensure that the contractor’s financial progress reasonably
reflects the physical progress. It also ensures that the contractor continues to get progress payments that
closely follow the physical activities.
Through good contract management practices, the Borrower and Contract Manager are expected to take
measures to avoid situations that lead to contractor’s claims. Some of these measures include:
1. having a thorough understanding of the contract document and how the contract is to be
implemented;
2. ensuring timely payment for successful delivery;
3. ensure that there is a proper definition of scope of works, appropriate specifications and timely
provision of design and drawings (if it is the responsibility of the Borrower);
4. provide timely possession of site;
5. ensure timely responses to contractor’s notices.
The Contract Manager (Engineer, Employer’s Representative etc.) has a key role in making a fair
determination of the matter or claim, in accordance with the contract, taking due regard of all relevant
circumstances. Agreement or Determination is regulated by, for example, sub-clause 3.7 of FIDIC:
Conditions of Contract for Construction, 2017, which requires the Engineer, when carrying out its duties
under the sub-clause to act neutrally between the contracting parties and shall not be deemed to act for
the Employer. Similarly, this matter is treated in, for example, sub-clause 3.5 - Agreement or
Determination of FIDIC: Conditions of Contract for EPC/Turnkey, 2017, which states to the effect that when
carrying out its duties under that sub-clause, the Employer’s Representative shall not be deemed to act
for the Employer.
55
Contract Management Practice
Assessment of claim
The Contract Manager assesses the claim to ensure that the contractor has demonstrated:
1. that it is entitled under the contract (contractually justified) to claim for the cost/time;
2. that it has indeed incurred the additional cost/time, and the extent of the claimed cost/time is
reasonable;
3. that there is a cause and effect between the Borrower’s default and the damages incurred by the
contractor.
Determination of costs
The Contract Manager should carefully check the determination of any costs associated with the claimed
delay. Some examples include:
1. Additional labor or equipment costs: When a contract is delayed due to a matter which is the
Borrower’s responsibility, the contractor may have claimed for additional labor or equipment.
When claiming for labor or idle equipment, the contractor needs to normally show that the labor
or equipment could not have been discharged or used in other activities without risking
unavailability for the contract when needed.
2. Site and home office overhead costs: While direct cost of the contract may reduce during the
delay period, the site and home office overhead costs (normally fixed) continue to accrue during
the delay period. A certain portion of the overhead cost may therefore not be absorbed or may
56
Contract Management Practice
be extended because of the delay. The Contract Manager should ensure that the contractor’s
claim for unabsorbed overhead costs is reasonably demonstrated.
3. Profit: In addition to recovering overhead, the contractor may claim for profit on the additional
costs. The Contract Manager should verify the contract to check whether the relevant contractual
provision allows cost compensation only or cost + profit. Unless the profit % is already specified
in the contract, the Contract Manager should ensure that the claimed profit rate is reasonable.
There are different methods and approaches in the industry to determine ownership and operating costs
i.e. capital recovery by a contractor. The Contract Manager may refer to the most common methods of
calculating ownership and operating costs.
The Contract Manager should assess that the method applied is reasonable and appropriate. For relatively
complex claims, it would be helpful to seek the support of an experienced claims expert, as there is often
a disagreement between the contractor and the Contract Manager as to which costs are to be covered
and how they are calculated.
Overhead costs
Construction claims by their nature may include, as a component, a demand for overhead costs. Both field
overhead, and home office overhead may be elements of a claim incurred because of a delay
1. Field overhead: are direct contract costs such as power, water, communications which may easily
be identifiable.
2. Home office costs: The concept of unabsorbed overhead is based on the assumption that during
a delay period the cash flow that would have been generated by the delayed contract is no longer
available. Thus, home office overhead costs, which in general are fixed, are absorbed by the
contractor’s other activities. The allocable portion of home office overhead costs attributable to
57
Contract Management Practice
delays is however not so straight forward. One method applied by contractors to determine
unabsorbed home office over head is the Eichleay formula (see below). Generally, before the
formula is applied, the contractor is expected to show that it was imprudent or impractical for a
reasonable contractor to take other work during the delay period given the facts and
circumstances.
Eichleay formula
The Eichleay formula is one approach for estimating the amount of unabsorbed home office overhead
resulting from construction delays. Some of the aspects that the Contract Manager may request additional
information from the contractor to support it are:
Home office overhead damages = daily allocable overhead x compensable delay days
Worked example:
The contract price is $10 million. The contractor has suffered compensable delays of 20 days. During
this period, the contractor has 10 contracts whose aggregate value is $80 million. The contractor's
58
Contract Management Practice
home office overhead during this period totaled $2 million. The duration of this project, including
excusable delays is 400 days. The sample calculation of home office overhead damages follows:
Contract’s allocable overhead = 10 x 2/80 = $0.25 m = $250,000
Daily allocable overhead =250,000/400 = $625 per day
Home office overhead damages (unabsorbed overhead) = $625 x 20= $12,500
The contractor may therefore claim $12,500 in compensation for home office overhead that should
have been allocated to this contract because of the increased duration of the contract.
Box XII – Case study: Eichleay formula
59
Contract Management Practice
60
Special considerations: Managing ESHS Risks in
Contract Management Practice
Works Contracts
Special considerations: Managing ESHS Risks in Works Contracts
Background
Ensuring that ESHS requirements are implemented in Works contracts, requires professionals with
appropriate skills to be part of the teams managing and executing the contract. Such professionals may
be required on part time or full-time basis, depending on the nature of the ESHS risks and impacts and
the role they are performing.
Along with the ESHS requirements for the Works, the need for specialist environmental, social or health
and safety skills or experience is established during the preparation of the Procurement Documents.
Guidance and information on how to integrate ESHS requirements into the Procurement Documents
(including for specification of Works and TORs for Contract Managers) is provided in the Procurement
Guidance- Environmental, Social, Health and Safety in Procurement, July 2018.
This section describes the responsibilities of the ESHS specialists (as part of Contract Manager, contractor,
Borrower) during contract start-up/mobilization, contract implementation and contract close-out (taking-
over). It describes not only the responsibilities according to the role/organization, but also, where
appropriate, the interface that these roles may have with each other, and with other bodies such as
regulatory authorities (with the right to inspect and monitor construction activities regarding ESHS
performance).
61
Contract Management Practice
of ESHS performance and outcomes enables the Borrower to identify opportunities for improvement,
address poor performance issues, and take contractual remedial actions as appropriate.
In addition to reviewing the written reports, it is essential to have regular meetings with the Contract
Manager to review ESHS performance as against the contractual requirements and identify any emerging
risks or issues.
62
Contract Management Practice
Regulatory Authority
Contracting parties would need to recognize that in many jurisdictions there are regulatory authorities
whose function is dictated by law. These authorities may undertake periodic inspections to determine
whether activities are being carried out in compliance with applicable laws and regulations and/or permit
conditions. The purpose is normally to uphold the law and not to monitor whether contractual
requirements and obligations are being met. These authorities may have the power to investigate
breaches of the law and take appropriate measures such as invoking judicial proceedings, issuing
instructions to stop the work, issuing fines or to require certain actions to be taken. It is important that
the contracting parties cooperate with them.
The Borrower should ensure that ESHS requirements are discussed during a pre-mobilization meeting so
that all parties have a common understanding and are aware of their obligations. During the meeting the
Contract Manager should agree with the contractor the documents and information that are needed prior
to any activity, to demonstrate effective management of the ESHS risks and impacts, such as method
statements/ safe systems of work. The meeting should involve not only ESHS specialists but also the
responsible managers of the Borrower, contractor, Contract Manager and any other relevant party.
The contractor should be required by the Contract Manager to develop any additional MSIPs to those
agreed at contract award to ensure that all ESHS risks and impacts likely to arise during mobilization will
be effectively managed. These should be subject to the prior approval of the Contract Manager. If the
63
Contract Management Practice
Health and safety management plan is not ready at mobilization, an MSIP describing how the mobilization
activities would be undertaken safely should be prepared.
The contractor should be required to submit, on a continuing basis through mobilization and into
implementation, for the Contract Manager’s prior approval, further MSIPs as needed to supplement those
already agreed to manage the ESHS risks and impacts of ongoing Works.
During mobilization phase, the contractor should identify the technical training required during the Works
and prepare an appropriate plan for the timely delivery of that training. The contractor should ensure that
personnel receive technical training in ESHS matters adequate to perform their duties. This may take the
form of, for example, specialized training courses in remedial actions such as hazardous materials
management and controls, or toolbox talks on safe systems of work. The contractor should keep records
of the training provided.
The Contract Manager should review the training plans and provide comments as necessary to ensure the
training is adequate and appropriate for the activities being undertaken.
64
Contract Management Practice
Contract implementation
During contract implementation, the ESHS specialists’ primary focus is to ensure that the contractual ESHS
provisions are continuously adhered to. This will involve the timely preparation and/or review of
documentation such as contractor’s plans and procedures, undertaking of inspection, supervision, and/or
audit, attending progress meetings, reporting and resolving issues that may occur.
Review and Develop MSIPs - Contractor’s Environmental and Social Management Plan (C-
ESMP)
The MSIPs agreed as part of the contract and during mobilization should continue to be reviewed, updated
and supplemented during implementation to ensure adequate control of ESHS risks ad impacts.
Collectively the MSIPs comprise the Contractor’s Environmental and Social Management Plan (C-ESMP).
As stated in the Conditions of Contract, the C-ESMP should be approved by the Contract Manager prior to
the commencement of construction activities (e.g. excavation, earth works, bridge and structure works,
stream and road diversions, quarrying or extraction of materials, concrete batching and asphalt
manufacture).
The approved C-ESMP (which may comprise a series of MSIPs) should be reviewed periodically and
updated in a timely manner by the contractor to ensure that it contains measures appropriate to the
Works activities being undertaken throughout contract implementation. The updates should be subject
to prior approval by the Contract Manager.
Monitoring the Contractor’s and Contract Manager’s Code of Conduct during Implementation
The Borrower should ensure that the Contract Manager implements and monitors compliance with its
code of conduct effectively.
In monitoring implementation, the Borrower may try to seek evidence of the following:
1. Is the code disseminated as envisaged in the contract? Is it easily accessible to the community
and project affected people?
2. Is the code a condition of employment of the Contract Manager’s staff?
3. What evidence is there of the Contract Manager’s senior team leading by example?
65
Contract Management Practice
4. Does the Contract Manager provide training and ongoing support to its staff? Or provide
information and advice to clarify any aspects of the code?
5. Are training records maintained?
6. Do the Contract Manager’s staff show confidence to challenge others when a breach of the code
is suspected.
7. How are internal and external complaints handled? Are they taken seriously?
8. How is the Contract Manager perceived by the local communities?
The Contract Manager should, in turn, ensure that contractor implements and monitors the contractor’s
codes of conduct effectively. In doing so, the Contract Manager should seek answers to the questions as
above as applied to the contractor.
Evidence on the implementation of the code of conduct could be found in progress reports, behaviors
exhibited in progress meetings, discussions with representative personnel on site, through consultations
with the local communities and the worker and community grievance redress mechanisms. In addition,
the timeliness of the enforcement by the contractor or Contract Manager of disciplinary actions for
violations of the code will indicate how effectively the code is implemented.
The Borrower would need to be mindful of the Contract Manager’s and contractor’s code of conduct and
not take any action or behavior that may undermine it. They should lead by example.
66
Contract Management Practice
a. MSIP/ C-ESMP;
b. Code of Conduct;
c. HSMP/method statements;
d. Accident records;
e. Worker labor records;
f. Progress reports;
g. Induction and Training records;
h. Worker and community grievance.
3. Site visit: For large/complex contracts, a representative sample of the Works may be visited during
the inspection. Selection of the areas to be visited should be informed by the activities being
undertaken, their potential ESHS impacts, locations of sensitive/important environmental and/or
social features, and the need to validate any aspects of the contractor’s documentation. The
issues to be considered during the site visits may include:
a. presence of safety features and equipment such as traffic signs and signals, protective
fencing, machine guards, etc.;
b. labor facilities such as provision of drinking water and wash room facilities;
c. evidence of Good International Industry Practice in relation to, for example:
o Storage and handling of hazardous materials;
o Concrete wash-out facilities;
o Spill kits and water pollution prevention measures.
d. site security arrangements;
e. worker behavior.
4. Corrective actions: At the end of the site visit, an action plan should be agreed with the contractor
to take any needed corrective actions. The action plan should clearly set out what the contractor
should do and by when, and progress in resolving the actions should be checked by the Contract
Manager on a timely basis. If necessary, further remedies to rectify non-compliances may be
applied as discussed below.
Inspections should be documented, and records retained in contract files (minimum information to be
recorded include: date and time, location, activity inspected, inspection observations and relevant data,
corrective actions, if any, inspection team’s name, signature and date).
67
Contract Management Practice
The contractual provisions set out how remedies are to be applied by the Contract Manager in the event
of non-compliance, including with respect to the following:
1. removal of personnel from site (for example, for breach of Code of Conduct, or for repeated
dangerous working practices);
2. withholding payments (for example for not rectifying a non-compliance in the specified time
scale);
3. getting others to rectify the works at the contractor’s expense (for example following repeated
discussions and warnings regarding pollution from asphalt plant);
4. suspension of works (for example at a quarry or borrow pit until the operation can be made safe);
5. performance security (for repeated non-compliances and a lack of willingness to expediently and
effectively address the deficiencies); and
6. termination.
For further detail see the section on Contractual Remedies.
68
Contract Management Practice
1. should inspect the site to identify any negative impacts to the ESHS aspects that may arise during
this period attributable to the contractor;
2. monitor that any dismantling or repair work carried out by the contractor on site does not have a
negative ESHS impact; and
3. monitor that the contractor’s staff involved in any dismantling, repair, reinstallation, retesting etc.
observe the code of conduct.
Upon the end of the defects liability period and issuance of performance certificate, the Borrower’s and
Contract Manager’s ESHS team should ensure that the contractor:
1. removes any remaining contractor’s equipment, surplus material, wreckage, rubbish and
temporary Works from the site;
2. reinstates all parts of the site which were affected by the contractor’s activities during the
execution of the Works and are not occupied by the permanent Works; and
3. leaves the site and the works in the condition stated in the Specification (if not stated, in a clean
and safe condition).
69
Contract Management Practice
1. applicable quality assurance system put in place (such as factory test witnessing, pre-shipment
inspection, acceptance tests);
2. formal acceptance of the Goods;
3. information provided to concerned Borrower/Contract Manager’s staff on the warranty
provisions (duration, coverage, service level agreement, contact information of any service
provider etc.) so that they know what to do in case of defects or malfunction;
4. logistics (transport, insurance, incidental services) to deliver the Goods to the end users;
5. warehousing facilities at the various points of the supply chain including arrangements for e.g.
space, climate control, electricity;
6. inventory control;
7. measures to avoid the risk of obsolescence and pilferage;
8. training of end users on the use of the Goods, if applicable;
9. end users’ satisfaction survey.
For Goods that have a limited shelf life (such as medicines and pharmaceuticals), the Borrower must take
measures to maximize the products’ shelf life. This may include an action plan which details the measures
to be taken. Such an action plan can be included in the CMP. Factors to be addressed in the action plan
may include:
70
Contract Management Practice
Incoterms
Incoterms (known as international commercial terms) are sets of commercial terms published by the
International Chamber of Commerce (ICC). The terms interpret commonly used foreign trade and deal
with the transfer of title and risk in various contracting scenarios. For complete information on Incoterms
refer to the International Chamber of Commerce website.
71
Contract Management Practice
For relevant procurements (such as Goods), the Bank’s SPDs specify the appropriate Incoterms that apply.
The Incoterms that are commonly used in Bank financed contracts are CIP and EXW. The Borrower/
Contract Manager should be familiar with the applicable Incoterms. See Box below.
Export restrictions
Export restrictions may arise due to trade regulations from the country supplying the Goods. Under such
situations, the supplier is released from the obligation to provide deliveries or services. However, the
supplier should have met all of its other contractual obligations including permits, formalities, licenses
etc., in order to be released from its obligations (e.g. see contract provision: SPD, Goods, 1 envelope, GCC
37).
Any risks related to timely processing of an L/C should be identified early (e.g. at the PPSD stage), and
appropriate mitigation measures put in place.
72
Contract Management Practice
Special considerations: Information Systems
contracts Special considerations: Information Systems contracts
This section presents some issues and lessons learned to support Borrowers in some of the issues that
may be encountered in managing information system contracts.
Relevant contract condition: The relevant condition of contract is GCC 16 (“Software License Agreement”)
in the Bank’s SPD: Request for Proposal - Information System. This clause provides that the supplier shall
grant to the Purchaser the original license to access and use the software, including all inventions, designs,
and marks embodied in the software.
Source code
Issue: In custom/bespoke software development contracts the Purchaser does not secure the base source
code from the supplier/developer. This can result in significant problems for the Purchaser including
performance issues, difficulty making modifications and upgrades, delays in the provision of an operating
system and additional costs.
1. custom/bespoke software built by a developer (supplier) for the Purchaser’s specific needs;
2. “commercial of-the-shelf” (COTS) software which is a standard system that has already been
developed for generic needs, tested and launched commercially for use by multiple clients.
73
Contract Management Practice
Having possession of the software source code is critical for custom or bespoke software systems. The
source code allows the Purchaser to make subsequent modifications, bug-fixing, and updates. For COTS
(commercial off the shelf) software and software-as-a-service, the risk is much less, as the developer is
responsible for future modification and regular upgrades of the system
In custom and bespoke software development contracts, the supplier (developer) is often reluctant to
provide the source code to the software that it is developing. This may allow them to charge high prices
for future modifications and upgrades. Even when the Purchaser requests and receives the source code,
it may not have the specialist knowledge to check it on receipt. If the source code that has been provided
is not correct this can result in serious problems when the Purchaser attempts to modify the system at a
later date.
Relevant contract condition: in the Bank’s SPD, GCC 15.4 “Source Code” is specified as:
“the database structures, dictionaries, definitions, program source files, and any other symbolic
representations necessary for the compilation, execution, and subsequent maintenance of the Software
(typically, but not exclusively, required for Custom Software).”
74
Contract Management Practice
Relevant contract condition: The relevant condition of contract (Bank’s SPD- information systems)- GCC
18.1. “Project Manager” states that the project manager shall have the authority to represent the
Purchaser on all day-to-day matters relating to the system or arising from the contract. It is the project
manager that normally gives and receives notices on behalf of the Purchaser.
Systems requirements
Issue: As part of the detailed design, the supplier was to prepare a System Requirement Specification
(SRS). This is the most important document for the development of a successful system.
During preparation of the SRS, the supplier normally needs to have significant consultations and
information gathering with the Borrower, relevant stakeholders and end users. In most cases,
stakeholders and end users provide limited time and information. This could result in the supplier not
getting the information that it needs to design a system that is fit-for-purpose. It could also result in delays
as the supplier makes efforts to try to reach the stakeholders and end users to get answers.
The Borrower should review the final SRS and satisfy itself that there has been a sufficient level of
stakeholder and end user engagement. If not, the Borrower should take the initiative to source the
appropriate information so that it can provide constructive comments on the SRS. Generally, this does
not happen. As a result, there are significant design and engineering changes during contract execution.
This translates into cost and time overruns and risks developing a system that is not fit-for-purpose.
Relevant contract condition: The relevant condition of contract is GCC 21. “Design & Engineering”. It
states that the supplier shall execute the basic and detailed design and the implementation activities
necessary for successful installation of the system in compliance with the provisions of the contract.
75
Contract Management Practice
Situation:
A Borrower was developing a comprehensive MIS system following bespoke software development.
After some consultation with the stakeholders and end users, the developer submitted the SRS for
Borrower’s approval. The Borrower did not have enough expertise in its team and approved the SRS
with minimal comments. During final stage of implementation, it was found many of the required
features were not working as expected, but that the design was consistent with the approved SRS. The
Borrower had to approve change orders and time extensions, resulting in delays and increased costs.
Lessons learned:
1. identify the relevant stakeholders and end users and fully inform them of the proposed systems
development and set expectations in terms of developer consultation;
2. select representatives from the stakeholders and end users to actively engage with the developer
during the development of the SRS, provide constructive feedback on the draft SRS and act as a
sounding board during systems development;
3. facilitate the consultation and ensure adequate dissemination of information;
4. establish a qualified subject manager team to review the feedback from stakeholders and end users
and check that all design factors have been included and are properly stated;
5. involve the stakeholders and end users in reviewing and testing the final proposed product.
Box XVIII – Case study: insufficient stakeholder and end user consultation
Quality of product
Independent testing
Issue: Some IT products provide warranties for long periods (5 or more years). It is sometimes difficult to
judge, on inspection, if these products will last till the expiry of the warranty.
Relevant contract condition: The relevant condition of contract GCC 25. “Inspection and Testing”.
Lessons learned:
76
Contract Management Practice
1. incorporate, as appropriate, independent testing to ensure that the technical specifications and
performance are consistent with the contract requirements;
2. Payments may be linked with the results of the independent tests.
Box XIX – Case study: durability of national ID cards
Relevant contract condition: The relevant condition of contract GCC 25. “Inspection and Testing”
Relevant contract condition: The relevant standard condition of contract (GCC 23 “Product Upgrades” in
Bank’s SPDs). This clause states that at any point during performance of the contract, should technological
advances be introduced by the supplier for Information Technologies originally offered by the supplier in
its bid, and still to be delivered, the supplier shall be obligated to offer to the Purchaser the latest versions
of the available Information Technologies having equal or better performance or functionality at the same
or lesser unit prices.
Similarly, the mentioned condition of contract adds that at any point during performance of the contract,
for Information Technologies still to be delivered, the supplier will pass on to the Purchaser any cost
77
Contract Management Practice
reductions and additional and/or improved support and facilities that it offers to other clients of the
supplier in the Purchaser’s country.
Transfer of knowledge
Issue: The proper transfer of knowledge to run the IT system after hand- over can be an issue. This creates
difficulties for the Purchaser in running the system. There are three ways to operate an ICT system:
Relevant contract condition: The relevant condition of contract GCC 19 “Project Plan”. This clause states
to the effect that the transfer of knowledge is key in IT systems development contracts. A detailed
approach to the transfer of knowledge should be part of Project Plan and which needs to be approved by
the project engineer.
78
Contract Management Practice
Value engineering
Issue: ICT technology is generally subject to rapid changes. During the bidding stage or contract
implementation stage new technology may come on the market, often at a reduced cost. In ICT contracts
the use of value engineering (VE) can be beneficial where solutions exist, or alternate technological may
be developed.
Relevant contract condition: The relevant condition of contract GCC 39.4. “Value Engineering”. The
supplier/developer can give a VE proposal to the Purchaser at any time during the performance of the
contract. The Purchaser may accept the VE proposal if the proposal demonstrates benefits that:
79
Contract Management Practice
center failed then the backup data center will take over. The design was based on an active–passive
mode (meaning that the main data center worked continuously whilst the back-up data center
remained idle). The backup center only worked when the main data center failed. During the contract
implementation stage, the supplier identified that the main data center and backup data center were
within 3 km distance of each other and it was possible to work in an active-active mode (meaning both
the data centers could work simultaneously). In such a scenario, the server and storage size can be
reduced by 30% and the system still capable of working on one data center if other one fails. By
implementing this change the total contract savings was 25% of the contract price.
Lessons learned:
1. the Borrower should encourage VE with a suitable $% supplier incentive included;
2. suitably qualified experts should review the VE proposal to make sure the proposed alternate
solution demonstrates the stated benefits.
Box XXIII – Case study: data center VE
80
Contract Management Practice
Supervision
The Borrower is responsible for supervising Bank financed consulting assignments. The Borrower should
monitor the progress of work, the timely completion of deliverables, the staff months and funds expended
(for time-based contracts), and determine where, within the contract, changes in the scope of work might
be appropriate. The contract normally requires that the consultants submit regular progress reports and
that the Borrower provides comments in a timely manner.
The Borrower should designate a contract manager with adequate technical qualifications, managerial
experience, and authority. In certain instances, involving large and complex projects, a steering committee
composed of high-level representatives of the Borrower and the consultant may be formed to exercise
arm’s length supervision over the assignment through the counterpart project manager and the
consultant’s team leader. The steering committee can be particularly useful when the Borrower’s executing
agency and the consultant have to coordinate their work with other agencies of the Borrower. The
opportunity to report on a regular basis to such a committee can facilitate collaboration and understanding
between the Borrower and the consultant and avoid disputes over technical or other issues.
Contract management
The Borrower must ensure that there is sufficient time spent planning the implementation of the contract.
Some of the internal arrangements that the Borrower may need to make include:
1. assign specific and detailed contract management tasks to the individuals or the team responsible
for contract implementation. The tasks assigned would need to be precise and realistic
(considering the specific experience, expertise and workload of each individual);
2. ensure that counterpart staff are made available, in timely manner, in accordance with the
contract;
3. ensure that facilities to be provided by the Borrower are made available, in a timely manner, in
accordance with the contract;
4. establish sufficient internal procedures (hierarchy, communication, levels of authority, flow of
documents, reporting, verification and acceptance procedures, payment procedures, internal
audit etc.);
5. monitor and evaluate contract implementation risks and ensure effective management and
mitigation measures are taken, including assigning responsibility for their enforcement;
6. coordinate arrangements with third parties (other agencies, end users, beneficiaries etc.),
especially when the Consulting Services are contracted on behalf of end users (e.g. training).
81
Contract Management Practice
Kick-off meeting
A kick-off meeting with the consultant is critical at the start of the consulting assignment. The Borrower’s
Contract Manager and other staff involved in supervision of the consulting assignment would need to be
present. It is also good practice to involve end users of the assignment, if any, at this stage.
Non-compliant deliverables
One of the features of consulting contracts is that the consultant does not provide a performance security.
Given the intellectual nature of the deliverables, it is a challenge to associate consulting services with a
performance security.
In the absence of performance security, the main remedy (short of suspending payments and termination)
available to the Borrower is the non-acceptance of the deliverables and/or reports submitted by the
consultant, the latter when the deliverables fail to meet the requirements of the contract.
Unsatisfactory performance
Poor performance may involve one or more staff of the consultants’ team, or the whole team. Based on
the provisions of the contract, the Borrower would need to advise the consultants to take the necessary
measures to rectify the poor performance.
82
Contract Management Practice
Poor performance should not be tolerated, and the consultants are expected to act quickly to comply with
a reasonable request to improve the performance of the team or to replace any staff member who is not
performing adequately. If the consultant fails to take adequate corrective actions, the Borrower may take
appropriate further remedial actions in accordance with the contract.
Approving payments
Lump sum contracts are paid on the basis of acceptance of deliverables, with no actual verification of the
inputs used by the consultants. Conversely, payments under time-based contracts are made after due
verification of all supporting documents (reports, timesheets, invoices, receipts etc.).
The following aspects are important in the process of verification of payment applications:
1. establish internal control mechanisms for the verification and approval of payment applications,
such as internal audits, double checking etc.;
2. verify professional rates, actual time spent (for remuneration and per diems), unit prices and
quantities (for reimbursable expenditures);
3. verify supporting documents in time-based contracts (timesheets, reports, invoices, receipts etc.);
4. ensure that the appropriate recovery of the advance payment has been deducted from the
payment (in time-based contracts);
5. check that the requested amounts have not been already paid;
6. verify invoices;
7. check if the payment request fits the payment schedule/milestones in the contract.
Time control
The Borrower should monitor implementation against the agreed schedule of work. The following time
control checks should be made:
1. check compliance with the contract milestone dates (submission of deliverables, reports etc.);
2. consider actions to speed up progress and ensure compliance with contractual time for completion
of the assignment.
Key risks
There are some specific risks associated with consulting contracts.
General
In general, the following aspects should be looked for:
1. consultants usually work on multiple assignments for different clients, so they might end up with
more work than they can handle;
2. frequent requests for replacement of staff;
83
Contract Management Practice
3. some consultants may take excessive time to fully understand the needs of the Borrower, the
scope of assignment and the constraints;
4. the consultants may not actually transfer knowledge and capacity building as required by the
contract.
1. because of the flexible nature of the contract, consultants may have the tendency to slow down
the progress of the assignment and seek additional time;
2. the consultant may be over-charging, especially the “home/office” time;
3. the consultant tries to reallocate time from field to home/office activities;
4. payments are not related to actual deliverables;
5. tendency of front-loading: claiming more days at the start of the assignment and delay completion
once most of the money has been paid;
6. use of less senior consultants in the home office that originally agreed in the contract;
7. same consultant charging the same professional time (same days) in two or more consulting
assignments.
1. due to the inflexible nature of the contract, the scope of assignment cannot be easily modified or
adapted to fit the changing needs of the Borrower;
2. when negotiating additional tasks:
a. be aware that the consultant may overestimate the actual input;
b. ensure that the rates used to calculate any additional services are the unit rates included in
the contract;
c. be aware that the consultants may attempt to create a need for more expensive extra
expertise or additional expenses to use higher rates than those provided in the contract.
84
Contract Management Practice
Contracting modalities
The contracting modality selected for a contract defines the allocation of risks, responsibilities and
relationship between the contracting parties.
Good practice is that there is a fair and balanced allocation of risks between the Borrower and the
contractor. The following factors help determine what is fair and balanced. Which party:
Type of Procurement
Type of Contract Goods Works Plant Info. Non- Text Consultants Management
Systems Consulting Books Services
Services
Design and Build
Contract ✓ ✓ ✓
Engineering,
Procurement and ✓ ✓ ✓
Construction
Performance Based
Contracts ✓ ✓ ✓ ✓ ✓
Contract based on
Unit Prices ✓ ✓ ✓ ✓ ✓
Time-based
Contracts ✓ ✓
Reimbursable-cost
Contracts ✓ ✓ ✓
Lump-Sum
Contracts ✓
85
Contract Management Practice
(e.g. foundation). Where the facilities are to be operated by the contractor for a specified time, the
contracting arrangement becomes a Design, Build and Operate (DBO).
The pros and cons of D&B contracts with respect to contract management are summarized in the table
below:
Pros Cons
Potential for better design and construction Borrower has less control over the design work.
coordination.
Borrower is not responsible for any dispute Borrower does not benefit from independent
between design and construction teams. advice and input from design consultant. The
design consultant works for the contractor.
Less risk to Borrower for errors and There is a need to define the functional, esthetical
omissions. and performance requirements upfront.
Could be less administrative burden to More risk to contractor’s design and build team.
Borrower.
1. Scope of Work: both the Borrower and the contractor are expected to have a clear understanding
of their respective roles and responsibilities taking into consideration the contractor’s
responsibility for the design work;
2. Insurance: Borrowers would need to confirm that the contractor’s insurance includes design
professional liabilities;
3. Expertise: the need for professional expertise by the contractor to be able to design the Works in
accordance with the Borrowers requirements and the Borrower to be able to review the designs
and confirm that they meet its requirement.
Lump-sum
Lump-sum payments (linked to milestones) are normally applied to D&B, DBO, Engineering Procurement
and Construction (EPC) and noncomplex Works (such as simple maintenance). However, lump-sum
contracts within the context of Bank financed projects normally refer to Consulting Services contracts.
Payments under lump-sum contracts are normally made upon successful delivery of a contractual
milestone. Payment may be a percentage of the total contract amount. Lump-sum contracts are
appropriate when the deliverables of the Consulting Services can be clearly and accurately specified.
86
Contract Management Practice
In managing lump-sum contracts, the key factors that the Borrower should focus on include:
Time-based
In the context of Bank financed projects, time-based contracts are normally used for Consulting Services
when it is difficult to define or fix the scope and duration of the services (such as supervision of Works that
are dependent on activities of the contractor/s). Time-based contracts need to be monitored very closely
to ensure that the consultants are charging for the time actually spent on the assignment, that
reimbursables are in accordance with the contract and that the quality of services are acceptable. If not
managed closely, time-based contracts can be the source of huge time and cost overrun coupled with poor
quality of services.
Performance-based
Performance-based contracts are result- oriented and payments are made for measurable outputs that
satisfy the Borrowers functional/performance requirements. Performance-based contracts may be
appropriate for road maintenance and rehabilitation, Non-consulting Services, operation of facilities or
other similar contracts where satisfactory performance is the primary focus.
87
Contract Management Practice
1. random sampling;
2. periodic sampling;
3. trend analysis;
4. customer feedback;
5. third party audit.
Admeasurement
Admeasurement can be used in a contract based on unit price. A unit price contract is based on estimated
quantities of items included in the project and unit prices (hourly rates, rate per unit work, volume, etc.).
In general, contractor’s overhead and profit are included in the rate. The final price of the contract is
dependent on the quantities needed to carry out and complete the work.
In a unit price contract, the risk of inaccurate estimation of uncertain quantities for some key tasks has
been removed from the contractor. However, some contractors may submit an "unbalanced bid" when
they discover discrepancies between their estimates and the Borrower’s estimates of quantities.
1. ensuring that payments are made using the unit prices in the contract;
2. ensuring that the quantities are measured using the method of measurement applicable to the
contract;
3. revisiting the unit prices if provided for in the contract.
88
Contract Management Practice
Annex Annex
2: 2:Measuring
Measuring performance
performance
Monitoring of KPIs
Key performance indicators (KPIs) are helpful internal tool for the Borrower to facilitate monitoring
contract performance and to ensure that successful outcomes are achieved. KPIs are only a monitoring
tool and are not a substitute for the contract provisions.
Although the KPI may vary depending on the specific contract, the performance measures normally rotate
around cost, time, quality, ESHS performance (for infrastructure contracts) and stakeholder (end users/
community) satisfaction. The contract performance target should be tangible and measurable. It should be
kept in mind that monitoring performance using KPIs is not necessarily monitoring activities. The detailed
contract execution activities are monitored/ supervised in accordance with the contract and relevant
elements of the CMP (if there is one). The KPIs support these efforts by focusing on key indicators for
successful performance.
If needed, the key performance indicators could include sub-indicators. A color system may be used to
show the monitoring results of the indicators, to guide the focus of attention. The indicators could also be
weighted (out of 100 for example) depending on the relevance to successful contract performance, and
scores given based on the monitoring results. Caution needs to be taken so that such a weighting system
does not end up being a mechanical exercise and thereby losing sight of the realities of the contract. As an
example, % of actual physical completion vs. contractual physical completion over the period may score
9/10. On face value, this may seem that the contract is almost progressing as scheduled (which may as well
be the case). However, it could as well be that a critical path in the program has just started to be affected
and its effect is not yet apparent. If the Borrower loses sight because of the 9/10 performance in this
indicator, the contract could soon start to suffer with significant consequences.
KPIs are only indicators and not an end by themselves. If a certain KPI is not met, the reasons should
immediately be identified, discussed with the contractor as needed, and issues/bottlenecks addressed in
a timely manner in accordance with the contract. As an example, % of actual physical completion vs.
contractual physical completion over the period should be 100% if the contract is being implemented in
accordance with the agreed programme. If this is below 100%, the reasons should be immediately
investigated with focus on the causes. The delay is an effect and the underlying causes could be cascaded
and therefore the need to address the underlying cause. In this example, the cause of the delay could be
because the contractor has started to slow site operations. The underlying cause may be because the
Borrower is delaying payments due and hence the contractor is facing cash flow issues. The real cause is
the undue delay in payments and therefore should promptly be addressed.
Good practice would be that the Borrower:
89
Contract Management Practice
5. includes the KPIs in the items for discussion in progress meetings; and
6. uses the KPIs in post-contract review, and record lessons for future operations.
What tools are available to the Borrower to monitor KPIs? This may include:
1. Gantt chart;
2. CMP reports and updates;
3. procurement plan updates;
4. disbursement reports and withdrawal applications;
5. regular progress meeting minutes;
6. project management software.
Example KPIs- Illustrative only (actual KPIs should be developed depending on the nature, size, risk
and complexity of the subject contract)
Time
1. Measure of physical progress =
% of actual physical completion vs. contractual physical completion over the period
Cost
1. Measure of financial progress =
% of actual paid vs. contractual expected payment over the period
2. Financial progress vs. physical progress: (%):
3. Cost overrun =
actual contract price x 100 (%)
original contract price
90
Contract Management Practice
Quality
1. Number of defects identified during the period.
2. Performance guarantees: % met.
3. End user/ community satisfaction:
a. number of community grievances during period;
b. end user satisfaction survey.
ESHS
1. Lost time due to safety related incidents (%) =
lost time x100 (%)
contract period
2. Number of environmental related breaches.
3. Number of GBV/SEA related breaches.
Box XXV: Example KPIs
91
Contract Management Practice
Annex 3: SAMPLE TEMPLATE - Contract Management
Plan Annex 3: SAMPLE TEMPLATE - Contract Management Plan
Project name:…………………………………………………………………..
Contract description:…………………………………………………………..
Date:…………………………………………………………………………….
Version [0.0]
[Date]
92
Contract Management Practice
93
Contract Management Practice
PROJECT DESCRIPTION
[Insert a brief description of the project under which the contract is being implemented]
The main objectives of the CMP are to ensure that there is a clear understanding of the roles and
responsibilities of the Borrower and contractor.
GOVERNANCE STRUCTURE
[Describe the governance structure relevant to the contract. Where possible include a diagram showing
the key parties, the hierarchy, lines of reporting etc.]
94
Contract Management Practice
RISK MANAGEMENT
Event Risk Impact Likelihood Risk Rating Risk Mitigation Time line Responsible Remark
Action
[insert the
identified
potential
risks.]
95
Contract Management Practice
Contractor Contractor’s
representative:
Consultant Engineer
Contractual Notices
Contractor’s documents
96
Contract Management Practice
97
Contract Management Practice
INSURANCE
Contract Amount / Information
Required
No Type of Insurance Ref. Limit of Expiry date Required
Date
liability
98
Contract Management Practice
1.
2.
3.
RECORDS MANAGMENT
No. Type of Record Owner Responsible Action required Remark
1. [Contract
documents and
any
amendments/]
2. Insurance details
3. [change orders]
4. [notices]
99
Contract Management Practice
100
Contract Management Practice
INTERFACE MANAGEMENT
No. Activity Responsible Remark
1.
2.
3.
101
Annex 4:Management
Contract SAMPLE TEMPLATE - Contract
Practice
Mobilization
Annex 4: SAMPLE TEMPLATE - Contract Mobilization
Contractual
Clause [insert
applicable
Timeline Responsible
Mobilisation Action contractual
(period) party/person
provision
reference, as
applicable]
• Agree on contractor’s
Representative (if already not
named in the Contract)
102
Contract Management Practice
Contractual
Clause [insert
applicable
Timeline Responsible
Mobilisation Action contractual
(period) party/person
provision
reference, as
applicable]
by the Contract
103
Contract Management Practice
Contractual
Clause [insert
applicable
Timeline Responsible
Mobilisation Action contractual
(period) party/person
provision
reference, as
applicable]
• Establish modalities of
communication
104
Contract Management Practice
Project: _________________________________________________
Project No: ____________________ Account No: __________________
Ref. Contract Contractor Effective Expiry Contract Component Disbursement Disbursement Cumulative Contract
Ref. Date Date value / Sub- from previous in the disbursement balance
Number component period reporting
period
1
2
3
4
5
Total
105
For additional information about the World Bank Procurement Framework, including Standard
Procurement Documents (SPDs), Guidance, briefing, training and e-learning materials see
www.worldbank.org/procurement