The FIDE Digest
The FIDE Digest
The FIDE Digest
Contractual Relationships
Considerations and Relationships
Overview of the right steps of initializing a project:
The employer has to examine what he wants to achieve.
What responsibilities can he accept and what will be assigned to others.
The engineering design has to take place.
Contracts documents are prepared
- Everything shall be well if all parties knew their obligations, rights and performed in accordance to the
contract; otherwise, trouble starts.
The Employer
First Task
- Develop the concept of the project, examine its feasibility and prepare a cost plan.
- He shall have determination, authority, finance and energy to proceed not only to design and build, but also
to operate, maintain and support the project throughout its life cycle.
- It is important if he has adequate technical and commercial resources.
Second Task
- Secure the political and legal support of his government to be able to obtain all necessary decrees, statues and
regulations.
- Has to be able to obtain adequate supplies: water, raw materials, labor, staff etc...
- Assist the contractor to import/export necessary parts of the plant for the project.
Third Task
- Design Team has to be appointed to develop:
- Size, shape and location of the project.
- Functional requirements of the project.
- Prepare positive plans for any procurement, construction and operation.
Fourth Task
- Appoint a supervisor Engineer (who is the same as original or another engineer) by a separate contract other than
the Contract between the Employer and the Contractor. The details of this contract are not disclosed to the
contractor.
- The contract between the Engineer and the Employer includes but not limited to:
- Feasibility studies, designs
- Preparation of the Tender Documents
- Assessment of Tenders
- Supervision of the Works, commissioning and testing.
- This Engineer shall be named in the contract
- The Engineer shall determine with the Employer:
- Conditions of Contract.
- The pre-qualification phase of the selection of the contractor.
- Tender Documents.
- The employer shall consider along with the engineer
- Financial plans, insurances, performance bonds, advance payments, TOC, tests and other things to be
considered are all stated in the book.
Fifth Task
- Decide which contract type to be used.
- FIDIC Red Book
- is recommended for Re-measurable civil contract.
- Not recommended for Lump Sum or Cost Plus.
- Better not to be modified to fit a contract other than Re-measurable.
The Engineer
- The Engineer is not a party to the contract between the Employer and Contractor.
- Has Certain duties and responsibilities which are explicitly
Pre-Contract
- The engineer is involved with number of activities necessary for contract documents to be issued and deal with the
matters necessary to obtain competitive Tenders form selected contractors.
- Ensure the availability of sufficient funds to honor the Engineer’s Certificates for payments.
- Employer shall confirm the availability of site and governmental permissions required.
- Engineer start to do the time schedule.
- The Engineer has to know from the Employer:
o The commencement date.
o Whether the works are required to be done in sections or as a whole
o How will Tenderer Contractor be to be invited to Tender.
o The Engineer would be wise if he informs the employer that he has to deal fairly between the Employer
and Contractor.
Tender Procedure
- The Engineer shall ensure that Tenderers.
o receive the same Tender information.
o receive equal opportunities to visit.
- The engineer should supervise the receipt, security and opening of the Tenders at the appointed time.
- Once the tenders are open, the engineer must:
o study each one carefully, correct errors o examine method statements and
o programmes if submitted with the Tender, o qualifications
and pay particular regard to any
o shortlist made up for the Employer to study o past experience of the Contractors
o recommend, with reasons, the most suitable Tenderer he believes will best serve the interests of
the Employer
Post-Contract
- The Engineer / Engineer’s Representative should
- record daily all matters of site interest such as
weather conditions.
Progress.
Contractor's plant and labor on site, whether working or otherwise.
- Make regular visits to the Site to be kept fully updated as to progress.
- Arrange regular site meetings and the preparation and agreement of the minutes of meetings should
follow as soon as possible, preferably the day after.
- Shall respect the laws and customs of that country.
- Have authority to make minor alterations to design as may be necessary
- Must the approval of the client before any major modification UNLESS Emergency.
The Contractor
Pre-Tender
- The contractor must be certain that he:
- can provide the resources
- have enough financial resources
- can provide skilled workmen, supervisors, materials, equipment.
- Know how to acquire what he does not possess.
- Money he will pay in Tendering Process will not be recovered.
- Has skill to price work competitively
- Has to follow the conditions of the contract
- Has to follow the instruction of the Engineer
- Has to finish on time.
- Complies with the law of the country.
Selected Clauses
Engineer’s Representative and Assistants
- The Engineer is entitled to appoint a Representative who is usually resident on Site and has specific duties and
authorities delegated to him by the Engineer.
- any failure by the Engineer's Representative to disapprove any work, materials or plant does not stop the Engineer
exercising his overriding authority to disapprove and giving instructions for rectification.
- Engineer may select and who might possess no suitable qualifications to properly perform the duties delegated to
him.
- If the explanation given makes it necessary to change the order of such listed priorities, then a change to the
contract is necessary.
- the resolution of ambiguities and discrepancies could affect the Contractor:
variations, additional works and omitted works
changes to the Contractor's method of construction (c) delays or suspension
matters concerning Sub-Contractors
extra expenditure if the Contract period is extended.
- the most important to the Contractor are the Drawings.
- Drawings are usually issued by the Engineer.
- All Drawings to be issued by the Engineer should be available in sufficient detail, in time, and in such a
sequence as to permit the Contractor to proceed with the Works without delay or disruption.
- If the Engineer fails to do this
the Contractor has to give proper notice to the Engineer as to his requirements.
If the Contractor discovered, he will incur extra cost or delay if a Drawing or further instruction is
not given within a reasonable time by the Engineer
o he should give notice to the Engineer, with a copy to the Employer, stating what is
required and giving his forecast of any delay or disruption he is likely to suffer.
o If after all this the Engineer fails, or is unable, to issue any Drawing or instruction within
a reasonable time for which the Contractor has given notice, and if the Contractor suffers
delay and/or extra cost
the Engineer will, after due consultation with the Employer and the Contractor,
give an Extension of Time and determine the amount of such extra costs to be
added to the Contract Price.
o However, if any delay on the part of the Engineer to issue any Drawings or instruction is
caused by, in whole or in part, the failure of the Contractor to submit Drawings,
Specifications or other documents which are his responsibility under the Contract,
the Engineer must take into account such failure when making his determination.
-
Site and Access
- The employer is responsible to make the Site available for work to be performed.
- Site has to be subjected to detailed survey, report on geological nature of the hydrological and sub-surface
nature.
o This information is needed for
The Engineer for design purpose.
The Contractor for determining construction method and to price the tender.
- The contractor shall bear all the costs required for the Access route as well as their permits if necessary.
- The prudent Contractor who visits the Site will be able to examine
o The terrain.
o The local and surrounding conditions.
o facilities available to him and his staff.
o Make a realistic Tender and cover all his obligations should he obtain the Contract.
- Sometimes the access to site is given partially according to the sequence of construction.
Programmes
- During the preparation for a Tender, the contractor makes an overall assumption of estimate time, cost which
he can by which establish his profit.
- This outline program will enable him to fulfil his obligations for the construction of the Works and to complete
the Works within the Time for Completion required by the Tender Documents.
- Purpose of such a construction programme
o set out the Contractor's timing of the various stages of the Works in calendar form
o identify the timing of those matters over which he has no direct control such as:
Site and access
production of further Drawings and details by the Engineer
the delivery to the Site of Plant and materials provided by the Employer
- The need for a detailed programme to be part of the Tender is not covered by the standard form.
- The need for the Contractor to submit a programme after a number of days from the date of the Letter
of Acceptance is
- This programme is submitted for consent of the Engineer, which is not required within any specified
time after submission.
- The Contractor has the right, to expect the Engineer's requirements for the program to be kept to a
normal cost expenditure as might be found in the Specification or elsewhere in the Contract
Documents so that any cost over and above these requirements will qualify as an increase to the
Contract Price.
- A program needs to demonstrate the timing, sequence and how the contractor intends to complete the works.
- If the schedule is unsatisfactory for the Engineer, he can request a further programme designed to enable the
works to be Completed on Time.
- The engineer can ask the contractor to give him a general description of the methods of construction;
however, this approval does not have to be obtained.
- The Contractor is asked by the employer/engineer to submit the detailed program only after he entered into a
legally binding contract (Letter of Acceptance)
- The contractor can claim that the rates specified in the BOQ are applicable for the time schedule stated in the
program; accordingly, the contractor claim to change the rates if the program was affected by the employer.
- The contractor will pay liquidated damages only If he did not complete within the time of completion in the
Appendix to tender + any extension, he will not pay if he passed the time of his program if his program is to be
finished before the time of completion.
- Tendering for work of civil engineering in foreign countries requires the ability to forecast risks
associated with climatic conditions which in turn involve additional costs.
- If the Employer provides data on climatic conditions this should also become part of the Tender.
Therefore, if any such climatic data proves to be wrong, the Contractor might be justified in
thinking he has a claim against the Employer.
- Contractor can claim additional costs arising from unforeseen physical conditions during the
execution of the Works, but not for unforeseen climatic conditions.
- It is difficult to apply to obtain an extension to the Time for Completion on grounds of bad
weather, because it is necessary for the Contractor to prove that the weather conditions causing
him the trouble are 'exceptionally adverse'.
- If the Contractor encounters any other problem caused by weather or natural disasters he may
seek to recover his additional costs by arguing that it was one of the Employer's Risks whereby he
undertook to carry the costs should damage be caused by the forces of nature against which an
experienced Contractor could not reasonably have been expected to take precautions.
Fossils
- Discovery of fossils, coins, articles of value or antiquity, structures etc, on the Site usually causes
more of an inconvenience to the Contractor than major physical obstructions.
- Contractor must tell the Engineer and carry out his instructions for dealing with the situation.
- If the Contractor suffers delay or incurs extra cost by following the Engineer's instructions
o an Extension of Time and an addition to the Contract Price will follow after due
consultation by the Engineer with the Employer and the Contractor
- will recover the costs only
- the Engineer who must give instructions as to what he requires to be done, the consequences of
what was actually done following these instructions could be treated as being a Variation and the
Contractor paid accordingly
- the influence on the Contractor's anticipated cost of the Works could be significant and could
include some of the following:
Defective Work
- Defects Liability Certificate because it is the Engineer's confirmation to the Employer that the
Contractor has completed all the Works and remedied all the defects to the Engineer's satisfaction.
This certificate has to be issued within 28 days after the expiry of the number of days stated as
being the Defects Liability Period in the Appendix to the Tender, or, if the Works have been done
in sections or as parts of the Permanent Works, is to be issued after the expiration of the Defects
Liability Period of the last Section or Part to be completed.
- The Engineer will only issue his Defects Liability Certificate when the contractor have completed
remedying of defects, shrinkages or other faults.
- Defective work or defects only come into proper prominence around the time the Contractor
makes a request to the Engineer for a Taking-Over Certificate.
- Before the Engineer issues a Taking-Over Certificate he will carry out an inspection and if he is
satisfied, he will issue the certificate to the Employer with a copy to the Contractor within twenty-
one days of receiving the notice from the Contractor. If there remains work to be done before he
can issue his Taking-Over Certificate, he will specify to the Contractor exactly what is required.
Only after this work has been done will a Certificate be issued. This has to be within a period of
twenty-one days after the satisfactory completion of the specified works.
Claims
Presentation of Claims
- Any claims which the Contractor wishes to present must be made before he submits to the
Engineer a Statement at Completion
- The Contractor can reduce the risk of failure with his claims if he makes a point of including all
of them with his monthly Application for Payment even if at the time he is unable to place a
detailed valuation on his claim.
Historical background
- It is helpful to give any historical data affecting the subject matter of the claim and to make all
necessary references to other documents to enable the reader to appreciate the background.
Contractual Argument
General
- The contract has to record actual costs he incurs in carrying out the work and to keep site
diary updated on daily basis and that proper labour and plant records are maintained, and if
possible, for them to be agreed with the Engineer's Representatives as being statements of fact
- The contemporary records relating to any claim start from the actual timing of the 'event' rather
than to the giving of notice
Supporting data
- This data may include items, wherever possible, such as: Site records; photographs; Site Diaries;
daily weather reports; charts and maps; instructions; quality control documents; programmes;
Drawings
Financial
- detailed comparison between the costs anticipated by the Contractor when tendering compared
with the costs incurred when actually doing the work and being affected by the circumstances
which gave rise to the claim, and any consequential costs.
Application of Clause 53
Statement of Completion
- The Contractor has to submit to the Engineer a Statement of Completion not later than 84 days
after the issue of the Taking-Over Certificate for the whole of the Works, including amounts or
estimated amounts of all claims.