Method Statement of Piling Concrete For Fire Water Tank MT
Method Statement of Piling Concrete For Fire Water Tank MT
Method Statement of Piling Concrete For Fire Water Tank MT
RESOURCES .................................................................................................................................5
Personnel .............................................................................................................................5.1
Equipment ........................................................................................................................5.2
Program of work……………………………………………………………………………………6
Preliminary site
investigation………………………………………………………………………………………….6.1
site clearance......................................................................................................................6.3
1. Objective
This document specifies methods and procedure accordance with
construction drawing and adhering to applicable specifications with
consideration to local rules and regulations.
2. SCOPE OF APPLICATION
The scope of this document is confined to civil construction pilling
works, which are listed below. These include material, machineries,
workforce, temporary activities & materials, mobilization and
demobilization of the team & stuff assigned to complete the pilling
scope. All the pilling activities to be performed in accordance with
relevant international codes & standards or recognized good
engineering practice
Method of statement
4. REFERENCE DOCUMENTS
5. RESOURCES
5.1 Personnel
Work will be carried out by qualifies personnel as
below
Civil Engineers.
Surveyor
QA QC civil engineer.
Skilled labors.
5.2 Equipment
Method of statement
6.PROGRAM OF WORK
As per the site condition all the earth works shall be limited to the area
inside the plot boundary.
The entire are required for construction of fire water tank will be
identified and marked with chalk powder (white) and will be barricaded
with a suitable hard barricading material with access
The surveyor should establish all the control point (through primary
datum line) in respect to lines/ grids, lines/cut lines, install and maintain
The reference marks, benchmarks, and maintain them as long as
required for setting out.
Method of statement
7.Sequence of works
Check the pile position, locations, the surveyor will mark the corner of
the pile and the center point by using a short bar in order to identify the
location of the corners and the center line by total station equipment
we will start from pile no.7 to pile no.14 (the red colored pile) as a first
stage for both driven and survey phase. The next stage will be to the
south side of this picture. we will follow this plan in order to reduce the
obstacles that might face us in the field during the installation phase.
also the advantageous of this plan is to get paralleled line of pile which
in turn it will minimize the survey work.
Method of statement
Pitching of the pile is carried out by looping the chain around the pile
approximately 1 m from the end and winching up into the helmet of the
hammer by rig operator
Set up piling rig with the pitched pile over the marked position then the
driver placed the pile onto the ground
Then the driver lowers service winch and proceeds to operate driving
hammer at low drop height until the pile has safely entered the ground
Pile is then driven to the required height which is one meter above the
ground for each phase of pitching process. and as the picture below
Method of statement
The pitched pile dose not satisfy the designated depth in the
drawing in our case. Then we have to pitch another pile, this pile
will join to the bottom of the pitched pile as shown below
Jointing is carried out by placing the pitched pile over the driven
pile, removing dirt that cover of the pitched pile by the assistance
And lowering of the pitched pile on the top of the driven pile by
the rig driver with direction from the assistant. Jointing in our
proposed tie connection
The pile is checked for the vertical plum again. Then the service
winch is lowered and removed
Method of statement
Method of statement
of compaction.
the top of driven pile and after joining process can proceed
Only the authorized person may operate in the vicinity of piling rig
Method of statement