Application of Tile Grouts 0
Application of Tile Grouts 0
grouts
Corner joints
Aesthetical problems
or or or or
1- Substrate preparation
Ensure that the joints are clean, free from residual or excess material. Grouting should be done no
less than 24 hours after tiling application with a standard setting adhesive or 3 hours after tiling with
a fast setting adhesive.
2- Method of application
Mix the product and let it rest for a few minutes before starting the appli-
cation.
Fill the joints using a rubber trowel. Cementitious grouts like weberjoint
perfect or weberjoint or weberjoint deco should be applied diagonally and
pressed into the joints to fill them completely.
Clean the applied areas with a damp sponge to remove the excess mate-
rial when the tile grout hardening process begins.
When the grout is completely dry, clean the tiles using a dry cloth.
weberjoint perfect can be used to fill joints from 1.5 to 20 mm (CG2WA).
weberjoint deco can be used to fill joints from 1 to 7 mm (C62WA).
weberjoint can be used to fill joints from 1.5 to 4 mm width*
weberjoint thick can be used to fill joints from 4 to 10 mm.
weberjoint glitter, a decorative cementitious grout with metallic effect can
be used to fill joints from 1.5 to 7 mm on internal walls.
* For joints less than 1 mm or below, consult our technical department
3- Special areas
For exceptional performance, apply weber epox easy, an epoxy tile grout for high traffic areas, large
public pools,factories, etc...
www.sodamco-weber.com
When applying grouts, allow the application to be properly dried and cured before stepping or
Note
walking on it. It is not advisable to immediately move furniture or heavy appliances on tiles until
the grouts are completely cured and hard enough to resist the expected abrasion and com-
pression.