Assignment 3-: Open Rubric
Assignment 3-: Open Rubric
QUESTION 1:
1.1. Expert judgment is an estimation technique based on the advice of knowledgeable staff,
whereas, Analog technique is where a similar, completed, project is identified and its actual
effort is used as the basis of the estimate.
1.2. A. Euclidean Distance= square-root of ((target_parameter1 – source_parameter1)2+
(target_parametern – source_parametern)2)
C. Project O/ option c.
QUESTION 2:
Open Rubric
QUESTION 3:
3.1.
3.1.1. A.
[F]
[C]
3 WEEKS
4 WEEKS
[H]
[A] 3 WEEKS
2 WEEKS [E]
8 WEEKS
*END
• BEGIN [G]
[D]
2 WEEKS
3 WEEKS
[B]
3 WEEKS
A - 0: 2 weeks: 2
B - 0: 3 weeks: 3
C - 2: 4 weeks: 6
D - 3: 3 weeks: 6
E - 6: 8 weeks: 14
F - 6: 3 weeks : 9
G- 14: 2 weeks: 16
H- 16: 3 weeks: 19
The earliest project completion date is week 19.
The Backward Pass:
H-16 : 3 weeks: 19
G- 14: 2 weeks: 16
F – 13 : 3weeks : 16
E – 5: 8 weeks: 13
D – 2: 3 weeks: 5
C – 1 : 4 weeks: 5
B – 0 : 3 weeks: 3
A – 0: 2 weeks: 4
C. The activity float time is a measure of much the start or completion of an activity may be
delayed without affecting the end date of the project.
3.1.2.
A. B,D,E,G,H.
B. A,C,F,H. 12 WEEKS.
C. 19 WEEKS.
3.2. Dummy Activities are used to link the completion of an activity to start of another, where
logical errors may arise due to 2 paths within a network having a common event, they help by
making it easier to distinguish the activity end points.
Question 4:
E 5 6 7 6 0.33