Table of Contents: Method Statement FOR Power Factor Correction Capacitors Installation
Table of Contents: Method Statement FOR Power Factor Correction Capacitors Installation
Table of Contents: Method Statement FOR Power Factor Correction Capacitors Installation
FOR
POWER FACTOR CORRECTION CAPACITORS INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1.SCOPE
This procedure to clear the method of the supply, installations of Power
Factor Correction Capacitors for the project.
This document details Power Factor Correction Capacitors Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Check the cable trenches and supports are painted and ready for
permanent installation of the said equipment.
Move the PFCC from the storage area to their designated Locations.
Fully crated panels shipped on a timber sub-base shall be lifted under
the sub-base.
When moving the fully crated PFCC from the storage area to their
Locations of installation using fork lifts, the mast must be as close as
possible to the face of the crate and forks must be fully projected under
the crate. Lift the fully crated PFCC squarely.
Uncrate, unpack and remove the PFCC from its timber base. Care
must be taken to protect the Feeder Pillars from unnecessary
scratches or bents on the panels.
Move in the PFCC using steel pipe rollers to its final location. Care
must be taken to ensure that the PFCC does not over balanced while
being moved to its final locations.
Align the PFCC horizontally and vertically.
Secure the PFCC assembly and ensure that it is fixed properly on its
base.
Remove all unused bolts, nuts, washers and clean the PFCC. Feeder
Pillars side covers and doors shall be put back.
Ensuring that it is properly tightened.
Conduct insulation resistance test on the PFCC to ensure that all joints
are properly insulated.
Raise Request for Inspection for switchgear installation.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
1. Hand Tools
3. Diagonal-Cutting Pliers
5. Side-Cutting Pliers
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper