Detailed Quantity Calculation

The document provides calculations for excavation, backfilling, concrete work, steel reinforcement, and unit prices for various construction projects including equipment foundations, transformers, busbar gantries, and trenches. Quantities, dimensions, reinforcement details and material costs are included.

Uploaded by

Mian M Khurram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
118 views24 pages

Detailed Quantity Calculation

The document provides calculations for excavation, backfilling, concrete work, steel reinforcement, and unit prices for various construction projects including equipment foundations, transformers, busbar gantries, and trenches. Quantities, dimensions, reinforcement details and material costs are included.

Uploaded by

Mian M Khurram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 24

1.

2
equipment 2.5m high
No. L W D Qty
Excavation 1 6.75 3 2 40.5
backfilling 33.87725
lean concrete 1 5.45 1.7 0.1 0.9265
concrete
column 3 0.7 0.7 2 2.94
foundation 1 5.25 1.5 0.35 2.75625
5.69625
Steel in foundation
Bar No. No. of bars Cut length wt/unit length wt
455.7

1 7.5 7.5 0.1 5.625


421.875
unit price
350 17,010
600 24,392
7,500 8,339

15,000 102,533

115 62,887
215,159

13500 75937.5
120 50625
126,562.50
1
transformer
No. L W D Qty
Excavation 1 6 4 3 72
backfilling 1 49.428
lean concrete 1 5.2 3.6 0.1 1.872
concrete
Wall 1 5 9 0.3 13.5
foundation 1 5 3.2 0.45 7.2
20.7
Steel in Gantry
Bar No. No. of bars Cut length wt/unit length wt
column 20 500 4.5 1.6 3600
20 128 6 1.6
stirrups 10 120 3 0.56 201.6

foundation 20 148 5.5 2.235 1819.29


1863
unit price
400 28800
800 39542.4
7500 14040

12500 258750

120 223560
564,692.40
1
transformer
No. L W D Qty
Excavation 1 6 6 3 108
backfilling 1 72.4255
lean concrete 1 5.6 5.2 0.1 2.912
concrete
column 2 4 0.6 3 14.4
beam 2 1.25 0.3 0.3 0.225
wall 2 4 0.15 3 3.6
foundation 1 5.5 5.25 0.5 14.4375
32.6625
Steel in Gantry
Bar No. No. of bars Cut length wt/unit length wt
column 20 500 4.5 1.6 3600
20 128 6 1.6
stirrups 10 120 3 0.56 201.6

foundation 20 148 5.5 2.235 1819.29


3266.25
unit price
350 37,800
600 43,455
7500 21,840

14500 473,606

115 375,619
952,320
1
Equipment 1.25m high
No. L W D Qty
Excavation 1 3.5 3.5 1.65 20.2125
backfilling 1 15.7525
lean concrete 1 2.2 2.2 0.1 0.484
concrete
column 1 1.2 1.2 1.65 2.376
foundation 1 2 2 0.4 1.6
3.976
Steel in Foundation
Bar No. No. of bars Cut length wt/unit length wt
column 20 8 2.7 2.25 48.6
stirrups 10 8 2.85 0.62 14.136
Foundation 12 32 1.75 1 56
500
Anchor Bolt Setting
unit price
350 7,074
600 9,452
7,500 3,630

15,000 59,640

120 60,000
1,000
140,796
1
Equipment 1.25m high
No. L W D Qty
Excavation 1 3 3 2 18
backfilling 1 15.9435
lean concrete 1 1.7 1.7 0.1 0.289
concrete
column 1 0.7 0.7 2 0.98
foundation 1 1.5 1.5 0.35 0.7875
1.7675
Steel in Foundation
Bar No. No. of bars Cut length wt/unit length wt
column 20 8 2.7 2.25 48.6
stirrups 10 8 2.85 0.62 14.136
Foundation 12 32 1.75 1 56
177
Anchor Bolt Setting
unit price
350 6,300
600 9,566
7,500 2,168

15,000 26,513

115 20,326
1,000
65,872
1
busbar gantry 16.9 meteper meter
No. L W D Qty
Excavation 1 5.5 5.5 2 60.5
backfilling 49.456
lean concrete 1 4.2 4.2 0.1 1.764
concrete
column 4 0.6 0.6 2 2.88
foundation 1 4 4 0.4 6.4
9.28
Steel in Gantry
Bar No. No. of bars Cut length wt/unit length wt
Column 25 8 3 3.973 95.352
Stripps 10 10 2.5 0.62 15.5
foundation 16 80 5.25 1.6 672
835
Anchor Bolt Setting 4
unit price
350 21,175
600 29,674
7500 13,230

15000 139,200

115 96,048
1,000 4,000
303,327
1
busbar gantry 16.9 meter high per meter
No. L W D Qty
Excavation 1 5.25 5.25 2.25 62.01563
backfilling 48.72788
lean concrete 1 4.7 4.7 0.1 2.209
concrete
column 1 2.1 2.1 1.75 7.7175
column 1 1.8 1.8 1.75 5.67
foundation 1 4.25 4.25 0.5 9.03125
11.07875
Steel in Gantry
Bar No. No. of bars Cut length wt/unit length wt
Column 20 12 2.53 3.1 94
Stripps 10 9 8.5 0.62 47
foundation 16 44 5.2 1.556 356
12 44 5.2 1 229
997
unit price
300 18,605
600 29,237
7500 16,568

15000 166,181

115 114,665
345,255
1
Trench (1000x100)mm per meter calculation
No. L W H Qty unit price
Excavation 1 1 2.8 0.6 1.68 400
backfilling 1 1 1.5 0.6 0.9 600
lean concrete 1 1 2.1 0.1 0.21 7,500
concrete
column 2 1 0.2 0.9 0.36
slab 1 1 1.3 0.2 0.26
trench cover 1 1 1.3 0.1 0.13
0.75 15,000
Steel in Trench
Bar No. No. of bars Cut length wt/unit length wt
column 10 14 2.5 0.62 21.7
10 30 2.5 0.62 46.5
slab 10 14 2.25 0.62 19.53
10 26 1.3 0.62 20.956
trench cover 10 7 2.25 0.62 9.765
10 13 1.3 0.62 10.478
97.5 115

60
672
540
1,575

11,250

11,213
25,250
1
Trench (0.8x1.12 & 0.8x1.12)m per meter calculation
No. L W H Qty unit price
Excavation 1 1 1 0.7 0.7 200.00
backfilling 1 0.3805 550.00
lean concrete 1 1 1.02 0.075 0.0765 7,000.00
concrete
column 2 1 0.15 0.45 0.135
0 1 0.1 0.45 0
slab 1 1 0.72 0.15 0.108
trench cover 0 1 0.72 0.075 0
0.243 13,500.00
Steel in Trench
27.945 120
140
209.275
535.5

3280.5

3353.4
7,518.68
1
Trench (0.8x1.12 & 0.8x1.12)m per meter calculation
No. L W H Qty unit price
Excavation 1 1 1.25 0.7 0.875 200.00
backfilling 1 0.4655 550.00
lean concrete 1 1 1.02 0.075 0.0765 7,000.00
concrete
column 2 1 0.15 0.45 0.135
1 1 0.1 0.45 0.045
slab 1 1 1.02 0.15 0.153
trench cover 0 1 1.02 0.075 0
0.333 13,500.00
Steel in Trench
38.295 120
175
256.025
535.5

4495.5

4595.4
10,057
1
Trench (0.8x1.12 & 0.8x1.12)m per meter calculation
No. L W H Qty unit price
Excavation 1 1 2.25 1.35 3.0375 200.00
backfilling 1 1.0175 550.00
lean concrete 1 1 2.08 0.075 0.156 7,000.00
concrete
column 2 1 0.15 1.12 0.336
1 1 0.1 1.12 0.112
slab 1 1 2.08 0.2 0.416
trench cover 0 1 2.08 0.075 0
0.864 13,500.00
Steel in Trench
99.36 120
607.5
559.625
1092

11664

11923.2
25,846
1
Trench (1.5x1.8 & 1x1.8)m per meter calculation
No. L W H Qty unit price
Excavation 1 1 3.75 1.75 6.5625 200.00
backfilling 1 2.7475 550.00
lean concrete 1 1 3 0.075 0.225 7,000.00
concrete
column 2 1 0.2 1.8 0.72
1 1 0.15 1.8 0.27
slab 1 1 3 0.2 0.6
trench cover 0 1 3 0.075 0
1.59 13,500.00
Steel in Trench
182.85 120
1313
1511.125
1575

21465

21942
47,806