Standard Operating Procedure - Format (Recovered)
Standard Operating Procedure - Format (Recovered)
Standard Operating Procedure - Format (Recovered)
For
Plant Electrical System
Topics
Section Pages
Plant Electrical System
11 415 V Breaker Operating Procedure
11.01 415 V ACB Breaker Operating Procedure
11.02 Plant PMCC/MCC(USS-1&2, SSS-1&2,TGMCC-1&2)
11.03 NEDB
11.04 EDG(Emergency Diesel Generator)
12 6.6 KV Breaker Operation Procedures
12.01 Station Switch Board
12.02 Unit Switch Board 1A
12.03 Unit Switch Board 1B
12.04 Unit Switch Board 2A
12.05 Unit Switch Board 2B
12.06 CHP Switch Board
AC Generator or Synchronous Generator Operation
13 Procedure
13.01 AC Generator Fundamental and Protection's
13.02 AC Generator Excitation System
AC Generator Synchronization and Emergency
13.03 Handling Operation
14 Power Transformer Operation Procedures
14.01 Station Transformer 20MVA
14.02 Generating Transformer 40MVA
14.03 Power Transformer Cooling System
14.04 Power Transformer Protection System
15 220KV Switchyard Operation Procedures
15.01 Switchyard Equipment Details
15.02 GT-1 Transformer Line Breaker
15.03 GT-2 Transformer Line Breaker
15.04 ST-1 Transformer Line Breaker
15.05 CPP Out Going or PP bay Breaker
15.06 Line and Bus Isolators
15.07 220KV Bus-Coupler Breaker
16 Plant DC System
16.01 220V Station Battery(1500Ah) System and Charger
16.02 220V Unit Battery(300Ah) System and Charger
16.03 UPS battery(500Ah) System and Charger
16.04 48V Switchyard Battery System and Charger
16.05 CHP Battery System Charger
17 Plant UPS startup and shutdown procedure
17.01 105KVA UPS system
17.02 Switchyard UPS system
17.03 CHP UPS system
17.04 DM Plant UPS system
19 Plant HVAC system
20 Plant Illumination System
To lay down the procedure for safe operation of man and property of Electrical
systems such as Transformers, Switchgears and to minimize the power
generation downtime.
2.0 SCOPE
This SOP shall be applicable for all LT, HT and EHT electrical systems.
3.0 RESPONSIABILITY
3.1 Technician’s
3.2 Shift Engineer’s
3.3 Executive’s
4.0 ACOUNTABILITY
4.1 HOD Operation
4.2 Shift In charge
5.13 KIOSK – It is a small house placed in outdoor area for protecting the
electrical and electronic devices from Sun light, Dust, and Rain also
maintain the constant room temperature by providing the Air Conditioner.
Intelligent Electronic Devices (IED) are using for continuous monitoring
and controlling the electrical parameters.
5.18 Reactive Power – The power which flows back and forth that mean it
moves in both the direction in the circuit or react upon itself, is called the
reactive power or useless power. It is measured in KVAR or MVAR.
5.19 Apparent Power – The product of root mean square (RMS) value of
voltage and current in a circuit is known as apparent power. It is
measured in KVA or MVA.
11.1 This SOP is applicable for all PMCC/MCC, NEDB, ACDB and
EDG of LT breaker system.
11.2 Here we are using the ABCB (Air Blast circuit Breaker).
11.3 Ensure the all the wiring of breaker control and outgoing cables
connections are made properly.
11.4 Read the instruction manual which is provided by OEM for smooth
operation and maintenance of breakers.
11.5 Ensure the breaker should be tested and commissioned properly by
electrical skilled persons, keep the test report for future use.
11.6 Ensure the availability of AC and DC control supply for breaker.
11.7 Ensure the breaker panel should be grounded properly.
11.8 Ensure the remote and local operation of breaker prior to the
loading.
11.9 Check the AUTO mode operation of breaker.
11.10 Ensure the breaker housing is in clean and good condition, no arc
flashing marks.
11.11 Ensure the breaker spring charging is happening manually and
automatically.
11.12 Ensure the all indications are showing on breaker panel, such as all
three phase supply, breaker position, spring charge, trip circuit
healthy, synchro check, auto trip alarm, DC control supply healthy
etc.
11.13 Ensure the Breaker housing doors are in closed condition.
11.14 Ensure the all maintenance work is completed and work permit is
closed by electrical dept. prior to the taking in service.
11.15 Ensure you are standing on an insulating rubber mat while doing
visual inspection of breaker.
11.16 Operation for closing air circuit breaker
12.1 This SOP is applicable for all vacuum circuit breaker system.
12.2 Here we are using the VCB (Vacuum Circuit Breaker).
12.3 Ensure the all the wiring of breaker control and outgoing cables,
Bus Bars connections are made properly.
12.4 Read the instruction manual which is provided by OEM for smooth
operation and maintenance of breakers.
12.5 Ensure the breaker should be tested and commissioned properly by
electrical skilled persons, keep the test report for future use.
12.6 Ensure the availability of AC and DC control supply for breaker.
12.7 Ensure the breaker panel should be grounded properly.
12.8 Ensure the remote and local operation of breaker prior to the
loading.
12.9 Check the AUTO mode operation of breaker.
12.10 Ensure the breaker housing is in clean and good condition, no arc
flashing marks.
12.11 Ensure the breaker spring charging is happening manually and
automatically.
12.12 Ensure the all indications are showing on breaker panel, such as all
three phase supply, breaker position, spring charge, trip circuit
healthy, synchro check, auto trip alarm, DC control supply healthy,
Service position, Test Position etc.
12.13 Ensure the Breaker housing doors are in closed condition.
12.14 Ensure the all maintenance work is completed and work permit is
closed by electrical dept. prior to the taking in service.
12.15 Ensure you are standing on an insulating rubber mat while doing
visual inspection of breaker.
12.16 VCB Door Opening sequence
12.17 Ensure the VCB is OFF or Open condition.
12.18 Door is in closed position with the padlocking arrangement.
12.19 For Door padlocked to be removed, latch to be opened.
12.20 Door Handle shall be lifted upwards and Door shall be opened.
12.21 VCB Door Closing Sequence
12.22 Ensure the wheel bracket plates are at closed condition.