Sample Computation-Excavate and Transport

The document provides cost estimates for two back fill works projects in Pananaogan, Bato, Catanduanes. The first project estimates costs of 37,360 for excavating and hauling 90 cubic meters of material over 1 day using an excavator, dump trucks, diesel fuel, and labor. The second larger project estimates costs of 213,000 to excavate and haul 1250 cubic meters over 5 days using similar equipment and resources at a larger scale. Both projects provide breakdowns of equipment costs, fuel costs, and labor costs to complete the excavation and hauling work.

Uploaded by

rolandtrojas
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
2K views

Sample Computation-Excavate and Transport

The document provides cost estimates for two back fill works projects in Pananaogan, Bato, Catanduanes. The first project estimates costs of 37,360 for excavating and hauling 90 cubic meters of material over 1 day using an excavator, dump trucks, diesel fuel, and labor. The second larger project estimates costs of 213,000 to excavate and haul 1250 cubic meters over 5 days using similar equipment and resources at a larger scale. Both projects provide breakdowns of equipment costs, fuel costs, and labor costs to complete the excavation and hauling work.

Uploaded by

rolandtrojas
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

NAME OF PROJECT: BACK FILL WORKS

(Counterpart project for the Construction of Sea Wall Project


of the KALAHI-CIDDS of the DSWD)
LOCATION: Pananaogan, Bato, Catanduanes
DETAILED ESTIMATE
QUANTITY UNIT ITEM UNIT COST AMOUNT

I - EXCAVATION & HAULING (EST EST. QTY: 90 cu.m


A. EQUIPMENT (6 1 days
1 unit Hydraulic Excavator (1.0 cu.m) 12,000.00 12,000.00
Excavator Capacity = 1 cu.m
Efficiency = 75%
Net Capacity = 0.75 cu.m
Time per swing = 120 sec.
Rest= 20 min
No. of Cycles per hour= 20 cycles/hr
Productivity = 15 cu.m/hr
90 cu.m/day
Fuel Consumption = 20 L/hr
120 L/day

2 unit Dump Truck (6 wheeler) 6,000.00 12,000.00


Typical Capacity = 6 cu.m
Avg. Hauling Distance= 0.8 km
AHD 2-way= 1.6 km
Speed= 12 km/hr
Time per 2-way Trip = 8 min
Stand-by Time (Hauling)= 24 min
Stand-by Time (Disposal)= 2 min
Total (Haul. and Disp.) = 34 min
No. of Trip per hour= 1.8 trip/hr
15 trip/day
Productivity= 90 cu.m/day
Fuel Consumption = 17 L/hr
136 L/day

256 ltrs Diesel Fuel 35.00 8,960.00


Subtotal 32,960.00
B. LABOR 1 days
QTY ITEM UNIT COST AMOUNT
1 H.E. Operator 550.00 550.00
2 Truck Drivers 350.00 700.00
3 Helpers 250.00 750.00
Subtotal 2,000.00
Item Total 34,960.00
Contingency 2,400.00
TOTAL PROJECT COST 37,360.00
Prepared by:

ROLAND T. ROJAS
OIC Municipal Engineer
NAME OF PROJECT: BACK FILL WORKS

DETAILED ESTIMATE
QUANTITY UNIT ITEM UNIT COST AMOUNT

I - EXCAVATION & HAULING (EST EST. QTY: 1250 cu.m


A. EQUIPMENT (6 5 days
1 unit Hydraulic Excavator (1.0 cu.m) 15,000.00 75,000.00
Excavator Capacity = 1 cu.m
Efficiency = 75%
Net Capacity = 0.75 cu.m
Time per swing = 80 sec.
Rest= 5 min
No. of Cycles per hour= 41.25 cycles/hr
Productivity = 30.9375 cu.m/hr
247.5 cu.m/day
Fuel Consumption = 17 L/hr
136 L/day

2 unit Dump Truck (6 wheeler) 6,000.00 60,000.00


Typical Capacity = 6 cu.m
Avg. Hauling Distance= 0.8 km
AHD 2-way= 1.6 km
Speed= 12 km/hr
Time per 2-way Trip = 8 min
Stand-by Time (Hauling)= 12 min
Stand-by Time (Disposal)= 2 min
Total (Haul. and Disp.) = 22 min
No. of Trip per hour= 2.7 trip/hr
22 trip/day
Productivity= 132 cu.m/day
Fuel Consumption = 17 L/hr
136 L/day

1360 ltrs Diesel Fuel 50.00 68,000.00


Subtotal 203,000.00
B. LABOR 5 days
QTY ITEM UNIT COST AMOUNT
1 H.E. Operator 550.00 2,750.00
2 Truck Drivers 350.00 3,500.00
3 Helpers 250.00 3,750.00
Subtotal 10,000.00
Item Total 213,000.00
Contingency
TOTAL PROJECT COST 213,000.00
Excavator Capacity = 1 cu.m
Effeciency = 75% (varies based on the type of material to be excavated)
Net Capacity = 0.75 cu.m
Time per swing (unload, swing, fill, swing) 20 sec
0.333333 min
Rest taken by the operator/hour = 5 min
No. of Cycles per hour = 165 cycles/hr
123.75 cu.m/hr

http://www.allinterview.com/showanswers/163706/calculate-productivity-construction-equipment-like-excavator-dozer-rock-b