Project: Employer: Supervision: Main Contractor: Staff / Labour Histogram With Cost

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4
At a glance
Powered by AI
The document outlines staffing requirements and associated costs for a construction project over multiple periods.

The project involves employing staff for a pipeline construction work. It details staffing needs and costs for both indirect and direct manpower categories.

Staff are categorized as indirect manpower including supervisory roles and support functions, and direct manpower for roles like welders, fitters and masons. Costs are provided for each category and staff type per month.

Project:

Employer:
Supervision:
Main Contractor:
STAFF / LABOUR HISTOGRAM with COST

Mobilization 2019 2020


PROFFESSION Staff COST Catagery wise
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Indirect Manpower
DGM (Const.) 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25
Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Section Engineer 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2
Senior Electro-Mechanical
Engineer 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25

Site Engineer 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2
Planning Engr. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Quantity Surveyor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Indirect Manpower

Draftsman 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2
Office Engineer
Lab Technician 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Document Controler 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Foreman 1 1 1 2 2 3 3 3 5 6 6 6 6 6 6 6
Support Team Foreman 1 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3
Surveyor 2 2 2 3 3 3 3 4 4 4 4 4 4 4 4 4
HSE Adviser & Safety
Officers 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2

Storekeeper 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2
Chainman 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6
Tea boy 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2
Watchman 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Total Indirect Manpower 22 23 23 28 28 32 33 35 38 39 39 39 39 39 39 39

Direct Manpower
HDPE Pipe Welder 0 0 2 2 2 4 10 12 14 16 18 20 19 19 18 18
Chargehand/Asst CH 1 1 1 1 1 3 6 7 8 9 10 11 10 10 9 9
Banks man/
Flag man 1 1 1 1 1 3 6 7 8 9 10 11 10 10 9 9
DI/HDPF Pipeline
Steel fixer Team-(12 Gang) 1 1 1 1 1 2 5 6 7 8 9 10 10 10 9 9
Carpenter 1 1 1 1 1 2 5 6 7 8 9 10 10 10 9 9
DI/HDPF Pipeline
Team-(12 Gang)

Helper 4 4 4 4 4 10 25 30 35 40 45 50 48 48 44 44
Pipe fitter 0 0 2 2 2 5 14 17 20 23 26 29 28 28 25 25
Total-A 8 8 12 12 12 29 71 85 99 113 127 141 135 135 123 123
Mason 1 1 2 2 2 1 1 1 1 2 4 6 6 6 8 8
Steel fixer 1 1 1 1 1 1 1 1 1 2 4 6 6 6 8 8
Carpenter Casting Yard + 1 1 1 1 1 1 1 1 1 2 4 6 6 6 8 8
Chambers
Chargehand/Asst CH +Electrical fittings 1 1 1 1 1 1 1 1 1 2 4 6 6 6 8 8
Helper 2 2 2 2 2 2 2 2 2 5 12 18 19 20 26 26
Electrician 1 1 1 1 1 1 1 1 1 2 3 5 5 5 7 7
Total-B 7 7 8 8 8 7 7 7 7 15 31 47 48 49 65 65
Helper 0 0 0 0 0 0 0 0 0 0 0 8 13 15 20 20
HC/Disinfection
Pipe fitter 0 0 8 9 10 0 0 0 0 0 0 4 7 8 11 11
Total-C 0 0 8 9 10 0 0 0 0 0 0 12 20 23 31 31
Operator 0 1 6 7 9 13 17 23 24 25 26 26 28 28 28 27
Plant & Vehicle
Driver 0 4 8 9 10 12 13 13 14 14 17 17 17 17 17 16
Total-D 0 5 14 16 19 25 30 36 38 39 43 43 45 45 45 43
Total Direct Manpower (A+B+C+D) 15 20 34 36 39 61 108 128 144 167 201 231 228 229 233 231

Grand Total 37 43 57 64 67 93 141 163 182 206 240 270 267 268 272 270

Prepared:__________________ Checked: __________________ Approved: ________________


2021
Oct Nov Dec Jan Total Total cost

0.25 0.25 0.25 0.25 -


1 1 1 1 -
2 2 2 1 -
0.25 0.25 0.25 0.25 -

2 2 2 1 -
1 1 1 1 -
1 1 1 1 -
2 2 2 2 -
-
1 1 1 1 -
1 1 1 1 -
6 6 5 4 -
3 3 3 3 -
4 4 3 3 -

2 2 2 2 -

2 2 2 2 -
6 6 6 6 -
2 2 2 2 -
2 2 2 2 -
39 39 37 34 -

16 8 0 0 -
8 4 0 0 -
8 4 0 0 -
8 4 0 0 -
8 4 0 0 -
39 19 0 0 -
22 10 0 0 -
109 53 0 0 -
8 4 0 0 -
8 4 0 0 -
8 4 0 0 -
8 4 0 0 -
25 12 0 0 -
7 4 0 0 -
64 32 0 0 -
18 15 10 0 -
11 8 5 0 -
29 23 15 0 -
25 22 16 12 -
15 13 12 11 -
40 35 28 23 -
213 120 28 23 -

252 159 65 57 -