MS - Access Control System Installation
MS - Access Control System Installation
FOR
INSTALLATION OF ACCESS CONTROL SYSTEM
TABLE OF CONTENTS
1. SCOPE
3. LOCATION OF ACTIVITY
4. DEFINITIONS
6. OPERATION
8. RESPONSIBILITIES
9. MANPOWER REQUIRED
15. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations Access
Control system for the project.
This document details the Access Control system Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
Division: Installation
3. LOCATION OF ACTIVITY
Access Control System for the whole building .
4. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
6. OPERATION
Material:
2. The sizes and routes routing will be as per the approved Shop
Drawings.
Installation:
The correct installation of Host controller and Door Controller
which is essential to the success of the system.
All Door Controllers should be networked.
The maximum length of one data line (Door equipment’s to door
controller) must not exceed 90 meters.
Readers are to be wired in to appropriate colored terminals on
the controller’s reader port.
Ensure that the Readers, EM locks , push button, door contacts
are installed and terminated properly
All consoles, terminals, and controllers shall be factory wired
before shipment to the job site.
Controller cabinet doors shall open a minimum of 170 degrees to
avoid blocking personnel movement. Each door shall be
equipped with a cylinder lock, a tamper switch and a piano-type
hinge with welded tamperproof pins.
Provisions shall be made for field wiring to enter the cabinet via
standard knock-outs at the top, bottom and sides of controller
cabinets.
Installation of Wires:
Each wire shall be identified at both ends with the wire
designation corresponding to the wire numbers shown on the
wiring diagrams that will attached in manufacturer
recommendations.
All exposed wiring within the cabinets, consoles, and terminals
shall be formed neatly with wires grouped in bundles using non-
metallic, flame-resistant wiring cleats or wire ties.
All ferrous metal work shall be painted, in accordance with the
manufacturer’s standards.
All cables are to be numbered while laying the cable and wiring
the system. Masking tape or proprietary numbering system can
be used.
Grounding:
Identification
Programming
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings, approved specs and manufacturer
recommendations.
8. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
2. To provide all necessary information and distribute
responsibilities to his construction.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
2. Ensure all the implemented safety measures are adequate to
maintain safe working on the site.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
9. MANPOWER REQUIRED
Charge hand and Experienced Technicians
15. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper