Goods Inwards Inspection: Revision: A
Goods Inwards Inspection: Revision: A
Goods Inwards Inspection: Revision: A
CONFIDENTIALITY
This
document
is
the
property
of
Grant
Walker
Engineering
and
as
such
cannot
be
reproduced
or
altered
in
any
way
without
the
written
permission
of
the
Company.
However
relevant
parts
of
this
manual
will
be
made
available
to
existing
and
potential
customers
upon
their
written
request.
Summary
To ensure that the quality of products and materials received to site in support of contract
requirements is verified where applicable.
Responsibility:
The Project Manager in conjunction with site employees shall be responsible for compliance
with the requirements of this procedure and the resolution of any queries that may arise.
Procedure:
1. On receipt of products or components in response to an agreed requisition, whose
quality needs verification, they shall be placed into quarantine or identified by means of a
label, to prevent their use prior to inspection clearance. Any carriers documentation shall
be signed off “Goods Received Uninspected” to allow release of carrier.
2. If the products are required for immediate use without the benefit of inspection,
agreement shall be obtained from the Project Manager, who will arrange their clearance
at a suitable point during use.
4. All incoming products and materials shall be checked against the incoming delivery
documents.
5. If any non-conformance is found during incoming inspection, it shall be recorded on the
incoming delivery documentation. The non conforming goods will be identified with
respect to the perceived non conformance and placed in Quarantine and the Project
Manager notified.
6. The Project Manager shall discuss the non conformance with the supply source
regarding a solution with minimal effect on the project timeline.
7. If this is not possible actions as detailed in QAP014 [Non Conformance Procedure] shall
be undertaken.
8. Following clearance of incoming goods, the delivery note shall be signed off and the
purchase ledger within drop box updated to signify acceptance.
9. The delivery documents shall be forwarded to the accounts department who will cross
reference them against the purchase requisition to ensure compliance. Any anomalies
shall be referred to the Project Manager for resolution.
10. All goods inwards inspections shall be in accordance with the attached process flow
chart.
Records:
Delivery of Products to
Site Goods Inwards Inspection
Product to Be
Acceptable Inspected Against Non Conformance Found
Delivery Note
Project Manager to
Sign Off Delivery Note
Review Non
to Signify Acceptance
Conformance
Notify Accounts to
Delivery Note to Head Contact Supplier and
Prevent Invoice
Office Accounts Arrange Rectification
Payment
Refer to Non
Conformance
Accounts To Hold Rectified Components
Procedure
Invoice Payment Accepted
[QAP014]
Invoice Cleared