Ed PL SPC
Ed PL SPC
Ed PL SPC
DIVISION (15)
PLUMBING WORKS
Index
Section Description
15100 VALVES
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 02 SUMMARY
1 03 QUALITY ASSURANCE
1 03 04 01 Sanitary fixtures
1 03 04 04 Valves
1 04 STANDARD SPECIFICATIONS
1 05 ENGINEER’S DRAWINGS
1 06 SHOP DRAWINGS
1 06 02 Shop drawings are to be new drawings prepared by the Contractor and are
not to be reproductions or tracings of the Engineer’s Drawings.
1 06 03 In preparing shop drawings, establish lines and levels for the work specified
and check the drawings to avoid interference with structural features and
other works.
1 07 COORDINATION DRAWINGS
1 08 RECORD DOCUMENTS
1 09 MAINTENANCE MANUALS
1 09 01 10 Submit in draft form for review and approval prior to final issue
and at least four weeks in advance of completion date of the
system.
1 10 SUBMITTALS
1 10 07 Submit for approval in letters form materials not covered by drawings e.g.
pipes, fittings and incidentals giving ratings and names of manufacturers.
1 10 10 During the progress of the work, submit shop drawings, to 1/20 or 1/10
scale, as required by the Engineer and as specified.
1 14 03 Furnish to other trades templates, patterns, setting out plans and shop details
necessary for proper installation and coordination of adjacent work.
1 15 01 All work is to be guaranteed for a period of one year dated from the final
acceptance of the work by the Owner unless specific components have
longer warranty periods.
1 15 07 During the guarantee period, provide necessary skills and labor to assure
proper operation and to provide regular and preventive maintenance for
equipment and controls, on a continuous 24 hour basis.
1 15 10 Spare parts for normal wear and tear during guarantee period are to be
provided by Contractor.
PART 2: PRODUCT
(Not Applicable)
3 02 01 Verify final locations for rough-ins with field measurements and with the
requirements of the actual equipment to be connected.
3 03 MECHANICAL INSTALLATIONS
3 03 03 Arrange for and provide templates or detailed dimensions for slots, and
openings in the floors, walls, partitions, and other building components, to
allow for mechanical installations.
3 03 12 Install systems, materials, and equipment level and plumb, parallel and
perpendicular to other building systems and components, where installed
exposed in finished spaces. except where otherwise indicated.
3 05 01 Refer to Section “PIPES AND PIPE FITT1NGS” for the installation of pipe
sleeves.
3 05 03 Lay out the work in accordance with approved shop drawings. Furnish and
set in place, in advance of placing of slabs or construction of walls, all
inserts and sleeves necessary complete the Work.
3 06 02 Concrete pads are to be 100 mm high unless otherwise indicated, with steel
reinforcing and necessary bolts, anchors, etc. Where concrete pad is set
directly on concrete floor, provide dowels in floor to tie base to floor.
Coordinate size, locations, anchor bolts, etc.
3 07 02 Field Welding: Comply with AWS Dl.l ”Structural Welding Code – Steel”.
3 08 GROUTING
3 09 PROTECTION OF WORK
3 09 01 Keep all pipe openings closed by means of plugs or caps to prevent the
entrance of foreign matter, and cover all fixtures, equipment and apparatus
as required to protect them against dirt, water, chemical or mechanical
damage both before and after installation.
3 10 01 No piping for water or sewage or any other piping systems not included as
part of the electrical work will be allowed to be installed in any switch gear
room, transformer vault, telephone room or electric closet.
3 10 02 In Mechanical Rooms, where piping runs over motor control centers or other
electrical equipment, provide a sheet metal shield or gutter. Submit shop
drawings showing proposed shielding at each location.
3 11 01 Damage and Touch Up: Repair marred and damaged factory-painted finishes
with materials and procedures to match original factory finish.
3 12 CLEANING
3 14 02 Noise level resulting from equipment and heard in the same building or
nearby buildings is not to exceed 40 decibels as measured with a standard
sound level meter on the ’A’ scale.
3 15 TRAINING
END OF SECTION
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 02 SCOPE OF WORK
PART 2 – PRODUCTS
2 01 SUNDRIES
2 01 01 Pipe Sleeves for pipes passing through walls, floors and roof to be galvanized
steel pipe, two nominal pipe sizes larger than pipe passing through for bare
pipes, and of sufficient size to permit pipe insulation to pass through for
insulated pipes.
2 01 02 Escutcheon Plates to be nickel plated, split ring type, sized to match pipe that
it is to conceal. Plates for pipes passing through sleeves which extend above
floor surfaces to be deep recessed type to conceal sleeve.
2 01 03 Flashing Sleeves: coated cast iron, caulking type, size specifically to fit pipe
and as manufactured by Josam, No. 1840 or approved equal.
2 01 04 Hangers and Supports Fasteners: power driven masonry expansion bolts with
steel threaded studs or internally threaded studs and couplings as required.
PART 3 – EXECUTION
3 01 EXCAVATION
3 02 01 Shop Drawings: submit for approval showing dimensions, arrangement and size
of reinforcement and locations of anchor bolts.
3 02 05 Align And Level Equipment on bases and supports over entire length and width
and shim where necessary to facilitate leveling.
3 02 06 Concrete Bases and Supports to be 150 mm larger all around than equipment, of
height to suit equipment and with top edge chamfered. Plaster and paint or
finish as adjacent and surrounding flooring.
3 02 07 Anchor Bolts: set in oversized sleeves with washers and nuts at bottom. Bolts to
project at least 6 mm above nuts when equipment is fixed to allow for
shimming. Secure during concreting.
3 02 08 Suspended Cradles And Wall Brackets: test to sustain a load eight times actual
operating weight of equipment supported.
3 04 02 Sleeves to be provided for all pipes passing through walls, floors and roofs.
Locate before walls etc. are constructed and fasten securely to prevent
displacement during construction. Plug ends during construction.
3 05 JOINERY
3 06 WATER PROOFING
3 07 01 Clean equipment, material, piping etc. inside and outside by effective and
approved methods to remove loose mill scale, blisters, sand, plaster, paint
droppings. Debris, dirt, oil, grease, labels and all foreign matter. Clean and
brush work in stages as directed before painting or concealing.
3 07 02 Surfaces to Be Painted: clean with wire brush and cleaning solution. Do not
apply paint to wet or damp surfaces.
3 07 03 Black Steel Piping including flanges, bolts, nuts, cast iron valves and
accessories, valve wheels and all ferrous parts are to be painted with two coats
of zinc chromate primer whether or not they are to be insulated. When bare or
exposed to view, they are to be further painted with two coats of approved oil
paint.
3 07 05 Hangers And Supports including clamps, rods, bolts, nuts etc. to be painted
with two coats of zinc chromate primer and where exposed to view with two
additional coats of approved oil paint.
END OF SECTION
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 01 02 The requirements specified in this section apply to all related sections in this
Division. The requirements of all related sections, elsewhere in this division also
apply to this section unless specified to the contrary.
1 02 DESCRIPTION OF WORK
1 03 QUALITY ASSURANCE
1 03 02 Cast, stamp or roll manufacturer's name on each pipe length, and cast stamp or roll
manufacturer's symbol and pressure rating on each fitting.
Copper Water Tubing (Types"K" & "L") (Hard Temper) ASTM B-88, ANSI A23.1
No Hub and Cast Iron Soil Pipe and Fittings ASTM A-74 & Cast Iron Soil
Pipe Institute Standards
H5-72
Service Weight and Extra Heavy Cast Iron Soil Pipe and Fittings CS188-66
Cast Iron Flanged Fittings and Flanges, Standard Weight ANSI B16.1
1 04 SUBMITTALS
1 04 02 Submit piping schedule showing manufacture, pipe or tube weight, fitting type,
and joint type for each piping system.
PART 2 :PRODUCTS
2 01 ACCEPTABLE MANUFACTURERS
AS VENDORS LIST
2 02 PIPING MATERIALS
2 02 01 01 Pipe: Service weight centrifugally spun cast iron soil pipe hub
and spigot coated inside and out; ANSI A1125.1; ASTM A74.
2 02 01 03 Joints:
2 02 02 01 Pipe: No-hub weight, cast iron soil pipe, coated inside and out,
labeled with the CI mark of quality and performance CISPI
301-72.
2 02 02 02 Fittings:
2 02 02 03 Joints:
2 02 03 02 Fittings:
2 02 03 03 Joints:
2 02 03 06 Fittings:
2 02 03 07 Joints:
Fuse welding.
2 02 04 Copper Tubing
2 02 04 02 Fittings:
2 02 04 03 Joints:
Silver brazes.
2 02 05 DWV Copper
2 02 05 02 Fittings:
2 02 06 Copper Pipe
2 02 07 Brass Pipe:
2 03 01 02 Scrape and hand wire brush piping clean with solvent and apply a
primer coat. Wrap pipe using a 50% overlap.
2 03 01 03 Acceptable Manufacturers:
2 03 02 03 Acceptable Manufacturers:
PART 3 - EXECUTION
3 01 INSTALLATION
3 01 01 General
3 01 01 01 Install pipes and pipe fittings as indicated on the plans and elsewhere in
the specifications, in accordance with recognized industry practices which
will achieve permanently leak proof piping systems, capable of
performing each indicated service without piping failure. Install each run
with minimum joints and couplings, but with adequate and accessible
unions for disassembly and maintenance/replacement of valves and
equipment. Align piping accurately at connections, within 1/400mm
misalignment tolerance.
3 01 01 04 Do not run piping through electric rooms, electric spaces, electric closets,
or other electrical or electronic equipment spaces unless unavoidable, and
specifically indicated on the plans, in which case, install drip pan below
and 300mm beyond foot print of such piping. Spill drip pan drain on
floor of adjacent space where flow will be noticed. Do not spill to a
receptacle.
3 01 02 Joints
3 01 02 01 Threaded pipe: In accordance with ANSI B2.1; cut threads full and clean
using sharp dies. Ream threaded ends to remove burrs and restore full
inside diameter. Apply pipe joint compound, or pipe joint tape (Teflon)
where recommended by pipe/fitting manufacturer, on male threads only at
each joint and tighten joint to leave not more than 3 threads exposed.
3 01 02 02 Nipples: Any piece of pipe 200mm in length and less shall be considered
a nipple. All nipples with unthreaded portion 40mm and less shall be
extra heavy. All other nipples shall be of weight corresponding to fitting
connected. Only shoulder nipples shall be used, close nipples will not be
acceptable.
3 01 02 03 Solder: Cut tube ends squarely, ream to full inside diameter, and clean
3 01 02 04 Weld: pipe joints in accordance with ASME Code for Pressure Piping,
B31, and in accordance with recognized industry practice and as follows:
3 01 02 06 Lead Caulk: tightly pack joint with joint packing material. Do not
permit packing to enter bore of finished joint. Clean joint after packing.
Fill remaining joint space with one pouring of lead to indicated minimum
depth measured from face of bell. After lead has cooled, caulk joint
tightly by use of hammer and caulking iron.
3 01 02 08 01 Tees
3 01 02 08 02 Couplings
3 02 01 General
3 02 01 03 Do not put any systems in operation until they have been tested,
inspected, and approved by the Architect. During the progress of the
installation, notify the Architect, at least 48 hours prior to such test or
inspection. Set up and prepare all tests in advance of scheduled test
time. Perform all tests in the presence of the Architect. Submit to the
Architect signed copies of all test reports and approvals and maintain
copy of same at site until acceptance of the work.
3 02 01 04 During the progress of the work, pressure test the various piping
systems including mains, risers, branches and fixture roughing as
directed to permit insulation, general construction and built-in rough
work to proceed.
3 02 01 05 Provide all apparatus personnel and temporary work for tests. Take all
due precautions to prevent damage to the building or its contents as a
result of such test. Pay for all reinstatement of work caused by such
damage to the building or work of other trades caused by such test.
3 02 02 Domestic & irrigation water Piping: fill with water and test to 1-1/2 times the system
working pressure but not less than 1380 kPa with no loss in pressure for a period of
one hour. Test to include all valves if designed to withstand such pressure.
3 02 03 Sanitary Drainage and Vent Piping: cap end or plug as required and fill with water to
produce at least 3 meters head at highest point of section tested. Let stand with no
loss of level for a period of four hours. After water pressure test, fill traps with water
and conduct smoke test.
3 02 04 Storm Drainage Piping: fill with water to produce at least 6 meters head at highest
point of section tested. Let stand with no loss of level for a period of four hours.
3 02 05 02 Test medium pressure systems 3.6 kPa up to 21 kPa with air at 690 kPa
for a minimum of four hours. Test high pressure systems 21 kPa - 100
kPa with air at 690 kPa for minimum of four hours. Test high
pressure systems (greater than 100 kPa) with air at twice the operating
pressure but at a minimum of 690 kPa.
3 02 05 03 Perform radiography test on all welds in gas meter and piping where
operating pressures exceed 20 kPa.
3 02 05 04 Fire Standpipe and Sprinkler System: test in full accord with NFPA
Code requirements but in no case less than 1380 kPa hydrostatic
pressure for a period not less than two
A PVC pipes for gravity sewer Tapered sleeve with solvent All exterior and interior
according to BS 4660 & 5481. & cement joints, and rubber underground sanitary, storm
DIN 19534 ring joints. water & vent piping systems.
B PVC pipes for water supply Socketed pipe for solvent All exterior underground water
according to DIN 8062 - working cement joint or rubber joint. piping system, swimming pool
pressure 10 BAR. circulation piping and irrigation
piping system.
D PVC pipes for soil waste and vent Tapered sleeve with solvent All storm water drainage piping
systems according to BS 4514. cement joints or rubber ring systems inside building
joints. aboveground.
G Galvanized steel pipe. Galvanized malleable iron All piping system inside pump
steam pattern. room
H Black steel pipe. Plain malleable iron All natural gas piping (Mill warp all buried
steam. piping).
I Black steel pipe. Grooved standard Optional for fire standpipe and sprinkler
malleable iron flexible. piping.
J Copper tubing Cast solder brass or All cold, hot and hot water circulating
type “L” wrought copper, 95/5. piping above grade. (65 mm inner diam and
large. (Maximum water working pressure
587 kpa.
K Copper tubing Cast solder brass or All cold, hot and hot water circulating piping
wrought copper, 95/5. buried under- ground or in concrete fill.
Type "K". (Maximum water working pressure 587 kPa.
L Copper Tubing Grooved cast bronze. Optional for all cold, hot and hot water
Type "L" circulating piping above grade 40mm and
larger.
M DWV Copper Copper DWV, 95/5 Optional for indirect waste piping.
Tubing. solders.
N Copper Pipe Wrought copper brazed. All cold and hot water circulating systems.
Type "TP".
O PP-R (Poly Socket-welding by Optional for all cold and hot- water 65
propylene) heating elements or the diam and smaller (Provide deduct alternate
system threaded joints of price evaluation). except for all pipes in
according to adaptor pipe fittings to boiler room, heater room and pump room
DIN8078 DIN 2999 - 1507
forType 3 &
DIN 16962
P CPVC Piping & ASTM D-224H All fire standpipe and sprinkler Piping (Fire
Fittings Ring Main) Installed underground
End of Section
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 02 DESCRIPTION OF WORK
1 03 QUALITY ASSURANCE
1 04 SUBMITTALS
Product Data: Submit manufacturer's data including printed technical literature,
installation instructions, and catalog cuts for materials, parts, devices, finish,
dimensions, detail of valves and piping arrangements, wiring diagrams of
prewired controllers, required control wiring and power wiring diagrams. Written
description of sequence of operation, pump curves indicating service conditions,
written operating instructions including start-up and shut-down. Maintenance
data including written instructions on items requiring periodic maintenance and
parts list and certification that pump have been hydraulically tested for pressure
and flow.
PART 2:PRODUCTS
2 01 ACCEPTABLE MANUFACTURERS
2 02 01 Furnish and install factory packaged three pump constant pressure booster
systems with all controls, motors, valves, etc., mounted on a common
concrete base. The system shall be capable of automatically providing a
constant system pressure with a flow rate range as indicated on BOQ.
System shall require only bolting in place to housekeeping pad and
installation of the shaft columns. Pump construction shall be of the
bronze fitted type with cast-iron casing.
Ship system remounted onto positioning top, rails connected to the base
flange and companion flange, all with required lifting lugs to aid in
installation.
2 02 05 Each pump shall be equipped with thermal safety valve which will open
and discharge water to drain when temperature exceeds 38°C. Contractor
shall run lines to drain. Sequence of Operation:
1-Low suction level cutout circuit to interface with suction tank controls
2 02 09 Factory Prefabrication
The factory shall certify in writing that the water pressure booster system
and its component parts have undergone a complete electric and
hydraulic test prior to shipment. The test shall include a system operating
flow test from zero to 100% design flow rate under the specified suction
and net system pressure conditions using each pump as lead and lag. The
system test may be witnessed by the owner, architect, or Project Manager
by reporting intent to so to the factory.
Certification shall include copies of the test data as recorded by Micro Processor
Base System certifying the following:
2 02 11 Guarantee
The water pressure booster system shall be guaranteed in writing by the
manufacturer for a period of one year from date of issuance of certificate
of practical completion against defects in design, materials, or
construction.
2 02 12 Startup Service
PART 3: EXECUTION
301 INSPECTION
302 ADJUSTMENTS
3 02 01 Pump Operation
3 02 02 Control Operation
3 02 03 Alarm Operation
3 02 04 Alignment
303 INSTALLATION
3 03 01 Completely align and level pumps, motors and bases. Where pumps and
motors are shipped as a unit, realign them in the field.
3 03 05 Construct all apparatus of materials and pressure ratings suitable for the
conditions encountered during continuous operation.
3 03 06 Provide casing connections for vent, drain, suction and discharge pressure
gauges.
End of Section
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 01 01 Drawings and general provisions of Contract, including General and
Supplementary Conditions of the project Specification sections, apply to this
section.
1 02 SUMMARY
1 02 01 This Section includes general duty valves common to most plumbing and
fire fighting mechanical piping systems.
1 02 01 01 Special purpose valves are specified in individual piping system
specifications.
1 02 02 Valve tags and charts are specified in Section "Mechanical Identification”.
1 03 SUBMITTALS
1 03 01 General: Submit the following in accordance with Conditions of Contract
and General Requirement Specification Sections.
1 03 02 Product data, including body material, valve design, pressure and
temperature classification, end connection details, seating materials, trim
material and arrangement, dimensions and required clearances, and
installation instructions.
1 04 QUALITY ASSURANCE
1 04 01 Single Source Responsibility: Provide valves of same type by same
manufacturer. Comply with the requirements specified in the specification.
1 04 02 Provide valves with manufacturer’s name and pressure rating clearly marked
on valve body.
1 04 03 American Society of Mechanical Engineers (ASME) Compliance: Comply
with ASME B31.9 for building services piping and ASME B31.1 for power
piping.
1 04 04 Manufacturers Standardization Society of the Valve and Fittings Industry
(MSS) Compliance: Comply with the various MSS Standard Practices
reference.
1 05 DELIVERY, STORAGE, AND HANDLING
1 05 01 Preparation For Transport: Prepare valves for shipping as follows:
1 05 02 Ensure valves are dry and internally protected against rust and corrosion.
1 05 03 Protect valve ends against damage to threads, flange faces, and weld-end
1 05 06 Do not remove valve end protectors unless necessary for inspection; then
reinstall for storage.
1 05 07 Protect valves from weather. Store valves indoors. Maintain valve
temperature higher than the ambient dew point temperature. If outdoor
storage is necessary, support valves off the ground or pavement in watertight
enclosures.
1 05 08 Handling: Use a sling to handle valves whose size requires handling by
crane or lift. Rig valves to avoid damage to exposed valve parts. Do not use
hand wheels and stems as lifting or rigging points.
PART 2: PRODUCT
2 01 MANUFACTURERS
AS VENDORS LIST
2 02 VALVE FEATURES, GENERAL
2 02 01 Valve Design: Rising stem or rising outside screw and yoke stems.
2 02 01 01 Non-rising stem valves may be used where headroom
prevents full extension of rising stems.
2 02 01 02 Pressure and Temperature Ratings: As scheduled and
required to suit system pressures and temperatures.
2 02 01 03 Sizes: Same size as upstream pipe, unless otherwise
indicated.
2 02 01 04 Operators: Provide the following special operator features:
2 02 01 05 Hand wheels, fastened to valve stem, for valves other than
quarter turn.
2 02 01 06 Lever handles, on quarter-turn valves 150 mm and smaller,
except for plug valves. Provide plug valves with square
heads; provide one wrench for every 10 plug valves.
2 02 01 07 Chain-wheel operators, for valves 65 mm and larger,
installed 1.8 m or higher above finished floor elevation.
PART 3 – EXECUTION
3 01 EXAMINATION
3 01 01 Examine valve interior through the end ports for cleanliness, freedom from
END OF SECTION
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 01 01 Drawing and project general provisions of Contract, including
General and the Supplementary Conditions Sections, of the
project apply to this Section.
1 02 SUMMARY
1 02 01 This Section includes the following piping specialties common
to most mechanical piping systems:
1 02 01 01 Strainers
1 02 01 02 Dielectric insulated unions and flanges
1 02 01 03 Vacuum breakers
1 02 01 04 Water hammer arrestor
1 02 01 05 Escutcheon plates
1 02 01 06 Pipe sleeves
1 02 01 07 Mechanical sleeve seals
1 02 01 08 Fire barrier penetration seals
1 02 01 09 Flashing sleeves
1 02 01 010 Drip pans
1 02 01 011 Masonry bolts
1 02 01 012 Water hammer arrestors (WHA)
1 02 01 013 Floor drains piping specialties furnished as part
of factory-fabricated equipment are specified as
part of equipment assembly in other Division- 15
sections.
1 02 01 014 Pipe expansion joints and flexible pipe
connectors are specified in other specification
sections.
PART 2 –PRODUCT
2 01 PIPING SPECIALTIES – GENERAL
2 01 01 Provide factory-fabricated piping specialties recommended by
manufacturer for use in service indicated.
2 01 02 Provide piping specialties of types and pressure ratings
PART 3: EXECUTION
3 01 STRAINERS
3 01 01 Install strainers full size of pipe run, in accordance with
manufacturer’s installation instructions.
3 01 02 Install pipe nipple and shutoff valve in strainer blow down
connection, full size of connection, except for strainers 50 mm
and smaller installed ahead of control valves feeding individual
terminals. Where indicated, provide drain line from shutoff
valve to plumbing drain, full size of blow down connection.
3 01 03 Locate strainers in supply line ahead of the following
equipment, and elsewhere as indicated, if integral strainer is not
included in equipment:
3 01 03 01 Pumps
3 01 03 02 Temperature control valves
3 01 03 03 Pressure reducing valves
3 01 03 04 Temperature or pressure regulating valves
3 02 DIELECTRIC INSULATED UNIONS AND FLANGES
Install at each piping joint between ferrous and non-ferrous piping. Comply
with manufacturer’s installation instructions.
3 03 VACUUM BREAKERS
Install vacuum breakers where indicated and as determined by Contractor as
required to prevent piping systems from being exposed to vacuum
conditions.
3 04 ESCUTCHEON PLATES
3 04 01 Install pipe escutcheons plates on each pipe penetration through
floors, walls, partitions, and ceilings where penetration is exposed
to view, and on exterior of building, according to the following:
3 04 01 01 Chrome-Plated Piping: Cast-brass, one-piece, with
set-screw, and polished chrome-plated finish. Use
split-casting escutcheons, where required, for existing
piping.
END OF SECTION
Drawings and project general provisions of the Contract, including the General and
Supplementary of the project specifications.
1 02 SUMMARY
This Section includes meters and gages used in plumbing fire fighting systems.
1 03 SUBMITTALS
1 03 04 01 Test plugs.
1 03 04 02 Flow measuring systems.
1 03 04 03 Flow meters.
1 04 QUALITY ASSURANCE
2 02 THERMOMETERS, GENERAL
2 03 PRESSURE GAGES
2 04 PRESSURE-GAGE ACCESSORIES
2 05 TEST PLUGS
2 07 FLOW INDICATORS
2 08 WATER METER
2 08 01 In-line, dry dial, magnetic drive type, manufactured from corrosion resistant
materials and suitable for a working pressure of 10 kg/cm2 and a cold water
temperature of up to 50 deg. C. Meter to be sized for the specified flow rate
at a maximum head loss of 2.5 m water gauge, and to have the
manufacturer’s guaranteed accuracy of +/-5% at the minimum flow rate.
Dial registration to go up to 1,000,000 cubic meter. Meter to have a
combination dial and roller totalizer in a hermetically sealed casing to
PART 3: EXECUTION
3 01 METER AND GAGE APPLICATIONS
3 03 THERMOMETER INSTALLATION
3 04 01 Install pressure gages in piping tee with pressure gage valve located on pipe at
3 04 03 Pressure Gage Needle Valves: Install in piping tee with snubber. Install syphon
instead of snubber for steam pressure gages.
Install test plugs in piping tees where indicated, located on pipe at most readable position.
Secure cap.
END OF SECTION
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 02 SUMMARY
1 03 MSS STANDARD
1 03 03 Select and apply pipe hangers and supports complying with MSS
SP-69.
Design seismic restraint hangers and supports for piping and equipment
suitable for seismic zone of project.
1 05 SUBMITTALS
1 06 QUALITY ASSURANCE
Listing and Labeling: Provide hangers and supports that are listed and labeled
as defined in NFPA 70, Article 100.
PART 2 – PRODUCT
2 01 05 Select only one type by one manufacturer for each piping service.
2 01 06 Select size of hangers and supports to exactly fit pipe size for bare
piping, and to exactly fit around piping insulation with saddle or
shield for insulated piping.
2 03 MISCELLANEOUS MATERIALS
2 03 01 Structural Steel: ASTM A 36/A 36M, steel plates, shapes, and bars,
black and galvanized.
2 03 04 03 Water: Potable.
2 04 RECOMMENDED MANUFACTURES
AS VENDORS LIST.
PART 3 – EXECUTION
3 01 03 Install hangers and supports of same type and style as installed for
adjacent similar piping.
3 02 013 Load Distribution: Install hangers and supports so that piping live
and dead loading and stresses from movement will not be
transmitted to connected equipment. Support piping independently
of equipment.
3 02 014 Pipe Slopes: Install hangers and supports to provide indicated pipe
slopes and so that maximum pipe deflections allowed by ASME
B31.9 ”Building Services Piping” is not exceeded.
Length Thickness
Pipe size
Mm Mm Mm
8 to 90 300 1.22
Mm Mm Mm
15 1.5 10
20 1.8 10
25 2.0 10
32 2.5 10
40 2.7 10
500 3.0 10
65 3.3 13
80 3.6 13
100 4.2 16
125 4.2 16
150 4.2 22
200 4.8 25
250 4.8 25
300 4.8 25
350 6.0 25
400 6.0 28
450 6.0 32
500 6.0 32
550 6.0 38
3 04 EQUIPMENT SUPPORTS
3 04 02 Grouting: Place grout under supports for equipment, and make a smooth
bearing surface.
3 05 METAL FABRICATION
3 05 01 Cut, drill, and fit miscellaneous metal fabrications for pipe and equipment
supports.
3 05 03 Field Welding: Comply with AWS Dl. 1 procedures for manual shielded
metal- arc welding, appearance and quality of welds, methods used in
correcting welding work, and the following:
3 06 ADJUSTING
3 07 PAINTING
3 07 01 Touching Up: Clean field welds and abraded areas of shop paint and paint
exposed areas immediately after erection of hangers and supports. Use same
materials as used for shop painting. Comply with SSPC-PA 1 requirements
for touching up field-painted surfaces.
END OF SECTION
MECHANICAL IDENTIFICATION
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 02 SUMMARY
1 03 SUBMITTALS
1 04 QUALITY ASSURANCE
1 04 01 Comply with ASME A13.1 for lettering size, length of color field, colors,
and viewing angles of identification devices.
2 01 06 Pipes Smaler Than 150 mm: Full-band pipe markers, extending 360 degrees
around pipe at each location.
2 01 010 Valve Tags: Stamped or engraved with 6mm letters for piping system
abbreviation and 13 mm sequenced numbers. Provide a 4 mm hole for
fastener.
2 01 011 Valve Tag Fasteners: Brass wire-link chain, beaded chain, or S-hooks.
2 01 013 Valve Schedule Frames: Glazed display frame, with screws for removable
mounting on masonry walls for each page of valve schedule.
3 01 01 Piping Systems: Install pipe markers on each system. Include arrows showing
normal direction of flow.
3 01 01 011 Locate pipe markers and color bands as follows wherever piping
is exposed in finished spaces, machine rooms, accessible
maintenance spaces (shafts, tunnels, plenums) and exterior non-
concealed locations.
3 01 02 Valve Tags: Install valve tag on valves and control devices in piping systems,
except check valves, valves within factory-fabricated equipment units,
plumbing fixture supply stops, shut-off valves, faucets, convenience and
lawn-watering hose bibbs, and similar roughing-in connections of end-use
fixtures and units. List tagged valves in valve schedule.
3 01 06 Piping Systems: Identify cold water, hot water supply, return, with duct
markers; or provide stenciled signs and arrows showing duct system service
and direction of flow.
3 03 01 Clean equipment, material, piping etc. inside and outside by effective and
approved methods to remove loose mill scale, blisters, sand, plaster, paint
droppings, debris, dirt, oil, grease, labels, and all foreign matter. Clean and
brush work in stages as directed before painting or concealing.
3 03 02 Surfaces to be painted: clean with wire brush and cleaning solution. Do not
apply paint to wet or damp surface.
3 03 03 Black Steel Piping including flanges, bolts, nuts, cast iron valves and
accessories, valve wheels and all ferrous parts to be painted with two coats of
zinc chromate primer whether or not they are to be insulated. When bare or
exposed to view, they are to be further painted with two coats of approved oil
paint.
END OF SECTION
PLUMBING PIPING
PART 1- GENERAL
1 01 RELATED DOCUMENTS
1 02 SUMMARY
1 02 01 This Section includes plumbing piping systems to a point 1.5 m outside the
building. Systems include the following:
1 04 03 Water samples, test results, and reports specified in ”Field Quality Control”
and ’ ”Cleaning” Articles.
1 05 QUALITY ASSURANCE
PART 2 - PRODUCT
2 01 01 General: The application of the following pipe, tube, and fitting materials
and joining methods required for plumbing piping systems are indicated in
Part 3 Article ”Pipe and Fittings Applications”.
2 01 03 Polypropylene pipe:
2 02 VALVES
2 02 01 Refer to Section “Valves” for gate, globe, ball, butterfly, and check valves.
PART 3 - EXECUTION
3 01 EXCAVATION
3 03 01 General: Use pipe, tube. Fittings and joining methods for piping systems
according to the following applications.
3 03 05 Cold and hot water all sizes: CPVC or polypropylene pipe and fittings.
3 03 06 Soil, Waste, and Vent Piping Below Ground: Use UPVC piping and
fittings
3 03 07 Storm Water Drainage Piping Above Ground: Use UPVC piping and
fittings
3 04 VALVE APPLICATIONS
3 04 01 Drawings indicate valve types to be used. Where specific valve types are
not indicated, the following requirements apply:
3 06 01 Make changes in direction for drainage and vent piping using appropriate
Y- branches, Y-branches with 1/8 bends, and long-sweep 1/4, 1/5, 1/6, 1/8,
and 1/16 bends. Sanitary tees and short-sweep quarter bends may be used
on vertical stacks of drainage lines where change in direction of flow-is
from horizontal to vertical. Use long-turn double-Y-branch and 1/8-bend
fittings where 2 fixtures are installed back to back or side by side and have
a common drain. Straight tees, elbows, and crosses may be used on vent
lines. Make no change in direction of flow greater than 90 degrees. Where
different sizes of drainage pipes and fittings are connected, use proper size
standard increasers and reducers. Reduction of the size of drainage piping
in the direction of flow is prohibited.
3 06 02 Lay buried building drains beginning at low point of each system, true to
grades and alignment indicated, with unbroken continuity of invert. Place
hub or bell ends of piping facing upstream. Install required gaskets
according to manufacturer’s recommendations for use of lubricants,
cements, and other special installation requirements. Maintain swab or drag
in piping and pull past each joint as completed.
3 06 03 Install drainage and vent piping at the minimum slopes, except where
another slope is indicated:
3 07 INSTALLATION OF VALVES
3 07 01 Sectional Valves: Install sectional valves close to main on each branch and
riser serving 2 or more plumbing fixtures or equipment connections and
where indicated. Use gate or ball valves for sectional valves 50 mm and
smaller. Use gate or butterfly valves for sectional valves 65 mm and larger.
3 07 04 Check Valves: Install swing check valve on discharge side of each pump
and elsewhere as indicated. Use MSS SP-80, Class 125, cast-bronze body
for 50 mm and smaller piping and MSS SP-71, Class 125, cast-iron body
for 65 mm and larger piping.
3 07 05 Balance Valves: Install valve in each discharge side of each pump and
elsewhere as indicated. Use ball valve for 50 mm and smaller piping and
butterfly valve for 65 mm and larger piping.
3 08 02 Install hangers for horizontal piping with following maximum spacing and
minimum rod sizes:
Up to 3/4 7 3/8
1 7 3/8
1-1/4 7 3/8
1-1/2 9 3/8
2 10 3/8
2-1/2 11 1/2
3 12 1/2
3-1/2 13 1/2
4 14 5/8
5 16 5/8
6 17 3/4
10 22 7/8
12 23 7/8
3 09 CONNECTIONS
3 09 01 Supply Run outs to Fixtures: Install hot and cold water supply piping run
outs, but not smaller than required by plumbing code to fixtures.
3 09 02 Drainage Run outs to Fixtures: Provide drainage and vent piping run outs,
with approved trap, of sizes indicated, but not smaller than required by
plumbing code to plumbing fixtures and drains.
3 09 03 Locate drainage piping run outs as close as possible to bottom of floor slab
supporting fixtures or drains.
3 10 02 Reinspections: When the Engineer finds that piping system will not pass
test or inspection, make required corrections and arrange for reinspection
by the Engineer.
3 10 06 Cap and subject the piping system to a static water pressure of 345 kPa (50
psig) above the operating pressure without exceeding pressure rating of
piping system materials. Isolate test source and allow standing for4 hours.
Leaks and loss in test pressure constitute defects that must be repaired.
3 10 07 Repair leaks and defects with new materials and retest system or portion
thereof until satisfactory results are obtained.
3 10 09 08 Test for leaks and defects in new drainage and vent piping
systems and parts of existing systems that have been altered,
extended, or repaired. If testing is performed in segments,
submit a separate report for each test, complete with a
diagram of the portion of the system tested.
3 11 01 03 Flush piping system with clean, potable water until dirty water
does not appear at outlets.
3 11 01 06 Flush system with clean, potable water until chlorine does not
remain in water coming from system following allowed
standing time.
3 12 COMMISSIONING
3 12 01 Fill water systems. Check compression tanks to determine that they are
not air bound and that system is completely full of water.
3 13 PROTECTION
3 13 02 Place plugs in ends of uncompleted pipes at the end of the day or when
work stops.
END OF SECTION
PART 1 - GENERAL
1 01 RELATED DOCUMENTS
1 02 SCOPE OF WORK
1 02 01 Extent and connect with the existing of cold, hot and potable water
distribution systems work is indicated on Drawings and by requirements of
this section.
1 02 02 Refer to other sections for “plumbing fixtures;” not work of this section.
PART 2 - PRODUCT
2 01 02 Provide materials and products of sizes and types to match piping and
equipment connections.
2 02 BASIC IDENTIFICATION
2 03 01 Provide pipes and pipe fittings complying with “Basic Requirements for
Plumbing and Fire Fighting Materials and Methods “ Pipes and Pipe
Fittings”, and “Plumbing Piping” sections.
2 04 01 01 Pipe escutcheons.
2 04 01 03 Dielectric unions.
2 04 01 06 Drip pans.
2 04 01 07 Pipe sleeves.
2 04 01 08 Sleeve seals.
2 05 01 Provide supports and anchors complying with “Supports and Anchors” and
“Plumbing Piping” sections.
2 06 BASIC VALVES
PART 3 - EXECUTION
3 01 INSPECTION
3 01 01 Examine areas and conditions under which potable water systems are to be
installed. Do not proceed with work until unsatisfactory conditions have
been corrected.
3 04 01 Install underground piping at least 3 m away from any sewer line. Protect
from contamination from any source.
3 04 04 Street Main Connection: Arrange and pay for tap in water main, of size and
in location indicated. Cut into and install new tee for water service in
existing water main, at location indicated, in accordance with local Water
Utility Company requirements. Provide curb valve and curb box as
indicated.
3 04 05 Water Service Piping: Extend water service piping of size and in location
indicated to water service entrance at building. Provide sleeve in
foundation wall for water service entry; make entry watertight. Provide
shutoff valve at water service entry inside building; strainer, pressure gage,
test tee with valve.
3 07 INSTALLATION OF VALVES
3 07 02 Sectional Valves: Install on each branch and riser, close to main, at branch
out to each floor and where branch or riser serves two or more plumbing
fixtures or equipment connections, and elsewhere as indicated.
3 08 01 Piping Run outs to Fixtures: Provide hot and cold water piping run outs to
fixtures of sizes indicated.
3 09 01 Install pipe connections into walls of the existing water reservoirs and
tanks locate correctly and take precautions to prevent dislocation and entry
of the existing pipes. Connections are to have no-leak flanges located
centrally and are to project 50 mm within reservoirs and tanks and 150 mm
beyond outside walls.
END OF SECTION
PART 1 - GENERAL
1 01 RELATED DOCUMENTS
1 02 SCOPE OF WORK
1 02 01 Extent and connect with the existing of soil and waste systems work’s
indicated on drawings and by requirements of this section.
1 02 02 Exterior sanitary sewer system required in conjunction with soil and waste
systems, up to the manholes outside the building, is work of this section.
1 02 03 Flashings required in conjunction with soil and waste systems are included
as work of this section.
PART 2 - PRODUCT
2 01 02 Provide materials and products of sizes and types to match piping and
equipment connections.
2 01 03 Provide fittings of materials which match pipe materials used in soil and
waste systems; preferably the product of same manufacturer.
2 02 01 Provide pipes and pipe fittings complying with section "Pipes and Pipe
Fittings”, and "Plumbing Piping” sections.
2 03 01 01 Pipe Escutcheons
2 03 01 04 Drip Pans
2 03 01 05 Pipe Sleeves
2 03 01 06 Sleeve Seals
2 03 01 07 Floor drains
2 03 01 08 Oil interceptors
2 04 01 Provide supports and anchors complying with" Hangers and Supports and
"Plumbing Piping” sections.
2 06 CLEANOUTS
2 06 01 Cleanouts to be full size, square head, brass, screwed plugs fitted Cleanouts
shall be easily accessible. Provide a minimum clearance of 600 mm for the
rodding.
2 06 03 Cleanouts in suspended soil pipe shall consist of cast brass tapered screw
plug in fitting or caulked Plain end piping in interstitial space or above
ceiling may use plain end blind plug and clamp
2 06 04 Floor cleanouts shall have external frame with square adjustable scoriated
secured nickel bronze top. Unit shall be vertically adjustable for a
minimum of 50 mm. When a waterproof membrane is used in the floor
system, provide clamping collars on the cleanouts. Cleanouts shall consist
of ”Y” fittings and 3 mm bends with brass or bronze screw plugs.
Cleanouts in the resilient tile floors, quarry tile and ceramic tile floors shall
be provided with square top covers recessed for tile insertion. In the
carpeted areas, provide carpet cleanout markers
2 07 FLOOR DRAINS
2 07 02 Material: UPVC.
2 08 01 Type: Oil and sand interceptor for separating and removing sand and oil
from workshop wastewater.
2 08 09 Cleanout: Integral.
2 08 011 Descriptive Function: to separate sand and oil of waste water from
workshop before connection to main drainage.
3 02 04 Gravity line after slow down chamber must be greater than pressure line
diameter.
PART 3 - EXECUTION
3 01 EXCAVATION
3 03 INSPECTION
3 02 01 Examine substrates and conditions under which soil and waste systems are
to be installed. Do not proceed with work until unsatisfactory conditions
have been corrected in manner acceptable to Contractor.
3 04 01 Install soil and waste piping in accordance with "Pipes and Pipe Fittings”,
and "Plumbing Piping” sections.
3 04 02 Lay horizontal pipes at uniform slope of not less than 1% and not more
than 3%.
3 04 04 Avoid unnecessary turns and offsets and run wastes as direct as possible
from sanitary fixtures to vertical stacks.
3 04 05 Vent sanitary fixtures to prevent siphon age of traps and air binding.
3 04 06 Slope vent pipes and connect to drip back into soil or waste pipe by
gravity.
3 04 07 Where connected to a horizontal soil or waste pipe connect vent pipe above
centerline of soil or waste pipe. Vent pipe is to rise vertically or at an angle
of not more than 45 degrees from vertical to a point at least 150 mm above
flood level rim of fixture before offsetting horizontally or before
connecting to branch vent.
3 04 08 All gravity waste drain lines inside the building with vertical drops over 6
m shall be provided with joint restraint on the vertical drop and horizontal
offset or branch below the vertical drop. Joint restraint shall be
accomplished by threaded, soldered. Or grooved joints or a combination of
pipe clamps and tie- rods as detailed in NFPA 24. Vertical joint restraint
shall be provided from the fitting at the bottom of the vertical drop through
every point up to the riser clamp at the floor penetration of the floor above.
Horizontal joint restraint shall be provided from the same fitting at the
bottom of the vertical drop through every joint on the horizontal offset or
branch for a minimum of 18 m or to anchoring point from the building
structure. Joint restraint below ground shall be accomplished by thrust
blocks detailed in NFPA 24.
3 04 09 Penetrations: Where pipes pass through fire partitions, fire walls, smoke
partitions, or floors, install a fire stop that provides an effective barrier
against the spread of fire, smoke and gases. Completely fill and seal
clearances between raceways and openings with the fire stopping materials.
3 04 010 At floor penetrations, completely seal clearances around the pipe and make
watertight with sealant.
3 04 011 Connect vent pipes to vent stack at least 150 mm above floor level rim of
highest fixture served by vent.
3 04 012 Vent pipes above roof are to pass through flashed and waterproofed
sleeves.
3 05 06 Install soil and vent piping pitched to drain at minimum slope of one
percent (1%).
3 05 09 Lay pipes to uniform slope not exceeding 3% and true to line and grade.
3 05 010 Lay pipes at not less than 600 mm below finished grade and not closer than
1 m to bearing walls and footings.
3 05 011 Free vertical drop of sewer pipe into manhole is not to exceed 450 mm
from invert of pipe to invert of manhole.
3 05 014 Join concrete pipes by inserting a layer of jute or hemp dipped in Portland
cement slurry into joint base. Fill remaining space with cement mortar
(1:2), ram and trowel mortar to form 45 degree taper with pipe barrel.
Clean pipe interior to remove mortar.
3 08 INSTALLATION OF CLEANOUTS
3 08 02 Install floor and wall cleanout covers for concealed piping. Select type to
match adjacent building finish.
3 09 01 Install flashing flanges and clamping device with each stack and cleanout
passing through waterproof membranes.
3 11 03 Coordinate with soil and waste piping as necessary to interface floor drains
with drainage piping systems.
3 11 05 Floor drains to be provided with deep seal P-traps except where noted on
the drawings or in the specifications.
3 11 09 Position floor drains so that they are accessible and easy to maintain.
3 12 01 Provide soil and waste piping run outs to plumbing fixtures and drains with
approved trap, of sizes indicated.
3 13 01 Test soil and waste systems in accordance with section "Plumbing Piping”
section.
3 14 01 Clean, flush, and inspect soil and waste piping in accordance with Basic
Requirements for Plumbing and Fire Fighting", "Pipes and Pipe Fittings”
and ”Plumbing Piping” sections.
3 15 02 Walls: plaster internally with two coats cement and sand (1:3) to total
thickness of 15 mm.
3 16 02 Access: opening in top with recess to accommodate cast iron cover and
frame.
3 16 03 Floors: Form by hand with cement mortar to size and shape of sewer.
Changes in sewer size to be gradual and even. Floors to have gradual slope
from side walls to central channel. Half pipe inverts may be used in straight
through inspection chambers.
3 16 05 Walls: Plaster internally with two coats cement and sand (1:3) to total
thickness of 15 mm.
3 16 07 Caulk and repair leaks if approved or remove entire work and rebuild at no
extra cost.
3 16 09 Covers are to fit frames. Replace if found to rattle under traffic. Plugging,
END OF SECTION
PART 1: GENERAL
1 02 01 Extent and connect with the existing of storm water systems work is
indicated on drawings and schedules, and by requirements of this section.
PART 2 – PRODUCT
2 01 02 Provide roof drain and gutters materials and products of sizes and types to
match piping and equipment connections.
2 02 01 Provide pipes and pipe fittings complying with “Pipes and Pipe Fittings”
and “Plumbing Piping” sections.
2 03 02 Pipe Escutcheons
2 03 05 Drip Pans
2 03 06 Pipe Sleeves
2 03 07 Sleeve Seals
2 04 01 Provide supports and anchors complying with “Supports and Anchors” and
“Plumbing Piping “sections.
2 05 EXPANSION JOINTS
2 06 06 Outlet: Bottom.
2 07 ROOF DRAINS
2 07 06 Outlet: Side.
2 08 01 Provide roof drains and gutters of size as indicated on drawings; and type,
including features, as specified herein.
2 08 03 Roof drains to be flashed with 2.7 kg (6 pound) sheet lead and secured with
flashing clamps.
2 09 01 MCopy and edit paragraph and subparagraphs below for each type of
stainless-steel channel drainage system required. If only one type is
required, drawing designation may be omitted.
2 09 09 Grates: heavy duty and of width and thickness that fit recesses in channel
sections.
2 09 013 Covers: Solid ductile, cast or gray iron, of width and thickness that fit
recesses in channel sections, and of lengths indicated.
PART 3 - EXECUTION
3 01 INSPECTION
3 01 01 Examine substrates and conditions under which storm water systems are to
be installed. Do not proceed with work until unsatisfactory conditions have
been corrected.
3 02 01 Install storm water piping in accordance with “Pipes and Pipe Fittings” and
“Plumbing Piping” sections.
3 02 03 Avoid unnecessary turns and offsets and run storm water piping as direct as
possible from storm water drains to vertical stacks.
3 06 02 Install roof drains and gutters in a completely watertight manner with the
roof. Install ’drain flashing collar or flange so that no leakage occurs
between roof drain and adjoining roofing. Maintain integrity of waterproof
membranes, where penetrated.
3 06 06 Install roof drains and gutters at low points of surface areas to be drained,
or as indicated.
END OF SECTION
PART 1 - GENERAL
1 01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1 02 SUMMARY
A. This Section includes the drinking fountains, water coolers and related components:
1. Drinking fountains.
2. Pressure water coolers.
3. Water-station water coolers.
4. Remote water coolers.
5. Fixture supports.
1 03 DEFINITIONS
A. Accessible Drinking Fountain or Water Cooler: Fixture that can be approached and
used by people with disabilities.
C. Drinking Fountain: Fixture with nozzle for delivering stream of water for drinking.
F. Remote Water Cooler: Electrically powered equipment for generating cooled drinking
water.
G. Water Cooler: Electrically powered fixture for generating and delivering cooled
drinking water.
A. Product Data: For each fixture indicated. Include rated capacities, furnished
specialties, and accessories.
D. Operation and Maintenance Data: For fixtures to include in emergency, operation, and
maintenance manuals.
1 05 QUALITY ASSURANCE
C. NSF Standard: Comply with NSF 61, "Drinking Water System Components--Health
Effects," for fixture materials that will be in contact with potable water.
D. ARI Standard: Comply with ARI's "Directory of Certified Drinking Water Coolers" for
style classifications.
F. ASHRAE Standard: Comply with ASHRAE 34, "Designation and Safety Classification
of Refrigerants," for water coolers. Provide HFC 134a (tetra-fluoro-ethane) refrigerant,
unless otherwise indicated.
1 06 EXTRA MATERIALS
A. Furnish extra materials described below that match products installed and that are
packaged with protective covering for storage and identified with labels describing
contents.
1. Filter Cartridges.
2 01 DRINKING FOUNTAINS
a. Pedestal:
b. Receptor(s):
a. Murdock, Inc.
b. Stern-Williams Co., Inc.
2. Description: ARI 1010, Type PB, pressure with bubbler, Style F, freestanding or
Style FW, flush-to-wall water cooler.
a. Oasis Corporation.
b. Elkay Manufacturing Co.
2. Description: ARI 1010, Type PBC, pressure with bubbler and compartment,
Style F, freestanding water cooler.
2. Description: Accessible, ARI 1010, Type PB, pressure with bubbler, Style W,
wall-mounting water cooler for adult -mounting height.
2. Description: Accessible, ARI 1010, Type PB, pressure with bubbler, Style WS,
semi-recessed water cooler.
2. Description: ARI 1010, Type PB, pressure with bubbler, Style RE, recessed
water cooler.
2 05 FIXTURE SUPPORTS
1. Josam Co.
2. MIFAB Manufacturing, Inc.
3. Smith, Jay R. Mfg. Co.
4. Tyler Pipe; Wade Div.
5. Watts Drainage Products Inc.; a div. of Watts Industries, Inc.
6. Zurn Plumbing Products Group; Specification Drainage Operation.
B. Description: ASME A112.6.1M, water cooler carriers. Include vertical, steel uprights
with feet and tie rods and bearing plates with mounting studs matching fixture to be
supported.
PART 3 - EXECUTION
3 01 EXAMINATION
A. Examine roughing-in for water and waste piping systems to verify actual locations of
piping connections before fixture installation. Verify that sizes and locations of piping
and types of supports match those indicated.
B. Examine walls and floors for suitable conditions where fixtures are to be installed.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
A. Use carrier off-floor supports for wall-mounting fixtures, unless otherwise indicated.
B. Use mounting frames for recessed water coolers, unless otherwise indicated.
E. Use chrome-plated brass or copper tube, fittings, and valves in locations exposed to
view. Plain copper tube, fittings, and valves may be used in concealed locations.
3 03 INSTALLATION
A. Install off-floor supports affixed to building substrate and attach wall-mounting fixtures,
unless otherwise indicated.
B. Install mounting frames affixed to building construction and attach recessed water
coolers to mounting frames, unless otherwise indicated.
C. Install fixtures level and plumb. For fixtures indicated for children, install at height
required by authorities having jurisdiction.
D. Install water-supply piping with shutoff valve on supply to each fixture to be connected
to water distribution piping. Use ball, gate, or globe valve. Install valves in locations
where they can be easily reached for operation. Valves are specified in Division 15
Section "Valves."
E. Install trap and waste piping on drain outlet of each fixture to be connected to sanitary
drainage system.
F. Install pipe escutcheons at wall penetrations in exposed, finished locations. Use deep-
pattern escutcheons where required to conceal protruding pipe fittings. Escutcheons are
specified in Division 15 Section "Basic Mechanical Materials and Methods."
G. Seal joints between fixtures and walls and floors using sanitary-type, one-part, mildew-
resistant, silicone sealant. Match sealant color to fixture color. Sealants are specified in
Division 7 Section "Joint Sealants."
3 04 CONNECTIONS
A. Water Cooler Testing: After electrical circuitry has been energized, test for compliance
with requirements. Test and adjust controls and safeties.
3 06 ADJUSTING
A. Adjust fixture flow regulators for proper flow and stream height.
3 07 CLEANING
A. After completing fixture installation, inspect unit. Remove paint splatters and other
spots, dirt, and debris. Repair damaged finish to match original finish.
END OF SECTION
SECTION 15440
PLUMBING FIXTURES
PART 1: GENERAL
1 01 RELATED DOCUMENTS
1 02 SUMMARY
1 02 03 01 Accessories, appliances,
appurtenances, and equipment specified
in other sections. Requiring plumbing
services or fixture-related devices, as
indicated.
1 03 SUBMITTALS
1 04 QUALITY ASSURANCE
1 06 EXTRA MATERIALS
PART2 : PRODUCTS
2 01 ACCEPTABLE MANUFACTURERS
AS VENDORS LIST
2 03 WATER CLOSETS
2 04 TOILET SEATS
2 05 FLUSHOMETERS
2 05 04 01 Non-hold-open feature.
2 05 04 02 Wheel handle stop.
2 05 04 03 Metal push button actuation.
2 05 04 04 Seat bumper on stop.
2 05 04 05 Hydraulic push-button actuator.
2 05 04 06 Bedpan washer diverter valve, spray
head, and support.
2 05 04 07 Trap primer connection.
2 05 04 08 Furnish flush meters with factory-set or
field-adjusted maximum
2 06 LAVATORIES
2 07 SINKS
2 08 02 WASTE
UPVC standard "P" traps with drain fitting and stainless steel
strainer.
2 09 SHOWER RECEPTORS
2 010 SHOWERS
2 011 BATHTUBS
2 012 BIDETS
2 013 010 Supply and drain plumbing service fittings not listed
above shall be as specified and as scheduled.
2 014 GENERAL
2 016 01 Provide all hangers, supports, brackets, etc., for the proper
installation of water closet, urinals, lavatories, sinks, etc.,
requiring support. Supports to be in accordance with the
manufacturers recommendations and when built into
partition or walls, to be set as the construction progresses.
2 018 DISPOSERS
PART 3: EXECUTION
3 01 EXAMINATION
3 02 APPLICATION
3 03 016 Install all water closets such that toilet seat will remain
upright when listed.
3 04 CONNECTIONS
3 07 PROTECTION
3 08 FIXTURE SCHEDULE
END OF SECTION
WATER HEATERS
PART 1: GENERAL
1 01 SECTION INCLUDES
1 01 01 Supply and installation of electric, gas and oil fired water heaters.
1 02 RELATED SECTIONS
1 03 REFERENCES
1 03 01 01 ANSI Z 21.10.1 Gas Water Heaters Vol. I Storage Water Heaters with
Input Ratings of 75,000 Btu per Hour or Less.
1 03 01 02 ANSI Z 21.10.3 Gas Water Heaters - Vol. III Storage, with Input
Ratings Above 75,000 Btu per Hour, Circulating and Instantaneous
Water Heaters.
1 04 02 Fabrication details of mild steel flues for oil fired water heaters and
stainless steel twin-wall flues for gas fired water heaters.
1 05 QUALITY ASSURANCE
1 05 01 Manufacturers: Firms regularly engaged in the manufacture of water heaters
and ancillary equipment and fittings whose products have been in satisfactory
use in similar service for not less than 10 years.
PART 2: PRODUCTS
2 01 02 The pressure type water heaters shall be manufactured of heavy gauge copper
or steel with copper lining and high density magnesium anode protection rod,
all as shown on the Drawings and all suitable for the above working and test
pressures.
2 01 04 The water heaters shall be suitable for use with an electrical power supply of
220 V, 1 phase or 380 V, 3 phase 60 Hz as shown on the Drawings and
Schedules.
2 01 06 Water heaters over 300 liters capacity shall be fitted with one or more
immersion heater banks; the immersion heaters being of the embedded type, of
incalloy or titanium.
2 01 07 Each heater shall be provided with its own removable control thermostat,
continuously variable between 35 – 60 oC wired for stepped control. A separate
high limit manual reset thermostat shall be incorporated with sensing element
immersed in the water.
2 01 09 The step control panel shall be mounted externally on the finished surface of
the heater and be fully wired to the heaters and tested before site delivery. A
panel door with interlock isolation from mains when opened shall be provided,
the control panel shall have test buttons, heater indicator lamps and power-on
lamp wired in, where shown on the Drawings. The heater shall also have a 7-
day time clock programmed for up to 96 on-off operations and skip-a-day
feature and shall also control the circulation pump.
2 01 010 All water heaters shall have a thermometer calibrated in oC mounted on the
outer casing of the heater.
2 01 011 All wall mounted units less than 200 liters capacity will require 2 safety
valves.
2 02 OIL-FIRED WATER HEATERS
2 02 01 Shell shall be designed for system working and test pressures and as confirmed
by manufacturer.
Provide:
2 02 02 Steel shell with glass lining.
2 02 02 01 Two 75 mm handhole cleanouts.
2 02 04 Controls
2 02 04 01 Manual reset high temperature cutout.
2 02 05 Provide emergency oil shut-off valve at point of entry to plant room activated
by heat detector over each burner any by manual push-button by each door.
2 02 06 Provide complete heavy gauge 3 mm thick mild steel flue and flue dilution
system from equipment to atmosphere. Flue to be assembled in flanged lengths
and be of all welded construction.
Flue to be insulated with 50 mm thick fiberglass fixed with wire mesh and clad
with 0.8 mm thick aluminum stucco for its entire length.
Interlock flue dilution fan with water heaters to allow firing only when fan is
running.
2 03 02 Burner to be suitable for firing with LPG of a quality obtained from National
Gas Company.
Provide:
2 03 02 01 Gas shut-off valves.
2 03 02 03 Electric ignition
2 03 03 Controls
2 03 03 01 Manual reset high temperature cutout.
3 01 PIPEWORK CONNECTIONS
3 01 02 All drain points, vent and safety valve discharge pipes shall be extended to
discharge over a tundish, which shall be piped to the nearest floor drain.
Tundish pipework shall be concealed.
3 01 03 The Contractor shall ensure that all the pipe and electrical connections to each
water heater are easily accessible for maintenance and that the heater can be
removed and replaced with the minimum of disturbance to the system.
3 02 01 All hot water service pipework shall be visibly examined and tested before
being concealed or built into the structure.
3 02 01 02 The final tests will be as of A (1) but shall also include that each
draw-off tap and shower fitting meets the approved suppliers
specification.
3 02 02 Carry out combustion and heat balance testing of each gas and oil fired boiler,
by manufacturer’s Engineers, and issue test report to the Engineer.
3 03 02 Provide instructions and training to the Owner’s staff for the operation and
maintenance of the equipment. Provide a minimum of 1 day in the class and 1
day on the job training. Each training session shall be 6 hours long.
END OF SECTION