This document discusses project planning and outlines several key aspects:
1. It defines a project and lists its key characteristics such as a definite start and end time, unique purpose, and temporary nature.
2. The basic elements of project planning are outlined, including work breakdown structure, objectives, general approach, and contractual, scheduling, and resource planning considerations.
3. The major planning stages for water resource projects are described, beginning with desk studies and reconnaissance surveys, then proceeding to appraisal reports, feasibility studies, and engineering design. Careful planning is necessary to properly define a project's scope, time, and costs.
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
47 views
Dpe Notes, Project Planning
This document discusses project planning and outlines several key aspects:
1. It defines a project and lists its key characteristics such as a definite start and end time, unique purpose, and temporary nature.
2. The basic elements of project planning are outlined, including work breakdown structure, objectives, general approach, and contractual, scheduling, and resource planning considerations.
3. The major planning stages for water resource projects are described, beginning with desk studies and reconnaissance surveys, then proceeding to appraisal reports, feasibility studies, and engineering design. Careful planning is necessary to properly define a project's scope, time, and costs.
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7
DPE NOTES , PROJECT PLANNING
Hard to define Scope, Time and
PROJECT PLANNING Cost clearly and with precision PROJECT INCEPTION PROJECT Need Based Projects • A project may be defined as The projects which are realized to “A set of activities, having a start meet with the demands of certain time and a definite end time, utilizing commodity at National level are called Need resources to give the desired results or Based Projects, e.g. energy projects, water objectives.” resources projects etc. • However, the most authentic Social Based Projects definition of the project has been Inception of projects is related to the given by Project Management requirement of Social Sector e.g. Health, Institute (PMI) as Education etc. “A temporary endeavor / task or Business Promotion Projects work undertaken to create a unique product In Corporate Sector, the Enterprise or to deliver services.” may conceive projects to promote their TRIPLE CONSTRAINTS OF A PROJECT business either by expanding the existing production facilities or entering into new areas of business Some Terminologies • Program It refers to an exceptionally large, long-term, objective oriented activity which can be broken into a set of projects. • Task The portions of a project may be referred as tasks. • Work packages The tasks may further be broken down into work package that are themselves composed of work units
PROJECT PHASING & FLOW CHART
Different Phases Of Project
1. Planning & Design Phase
Planning, Investigation & Design
CHARACTERISTICS OF A PROJECT 2. Pre Award Phase
Unique Purpose, well defined Tendering & Award of Contract objectives Temporary in nature 3. Construction Definite beginning and a definite end Implementation Execution Requires Resources from various areas like Men , Material, Hardware, 4. Operational Phase Software, etc Operation and Maintenance Definite Cost Primary Sponsor and/or Customer PROJECT FLOW CHART Involve uncertainty, internal & Inception external Hiring of Consultant Pre Feasibility Study DPE NOTES , PROJECT PLANNING Feasibility Study (PC-II) Detail Design & Preparation of 4. Contractual Aspects Tender Documents (PC-I) Reporting requirements, International Bidding Liaison arrangements i.e. coordination Bid Evaluation mechanism with other agencies Award of Contract involved, Signing of Contract Provisions for subcontracting, Commencement of Work Dispute resolution mechanism, Project Utilization of materials, Completion Technical specifications, Delivery schedules, Operation Variation in works, Outlived Project Mode of payment, Rehabilitation Defects liability, Insurances and performance guarantee WHAT IS PROJECT PLANNING? etc 5. Schedules Project Planning starts with the Vision - the ability to see something that is not Prepare a list of tasks to be carried out. visible to others Estimate the time (hours, day or Complete Road Map to achieve a target months) to complete each task. 6. Resources Rational determination of how to initiate, sustain and terminate a Project Budget (along with cost monitoring and WHY TO PLAN A PROJECT ? control procedures) Elimination or reduction of uncertainty Special resources required in the form Improvement of Efficiency of : Machinery used in construction as well Achievement of better understanding of as O&M, the objective, Qualitatively and Test equipments, Quantitatively Logistics, Providing the basis to manage and Field facilities and monitor the work Special materials. 8. Potential Problems BASIC ELEMENTS OF PROJECT Difficult to anticipate potential difficulties. Possible disaster may be: PLANNING Subcontractor failure, 1. Work Breakdown Structure (WBS) Technical failure, The WBS consists of a simple list of all Strikes, project activities with major activities broken Bad weather, down into sub activities. The project linear Earthquake, responsibility chart is also a part of WBS. Limited resources, Tight deadlines 2. Objectives RESOURCES INVENTORY AND Identify the stakeholders RANKING Comprehensive list of needs It is the first step towards planning and Priorities the needs then subsequent development. It is 3. General Approach often called basic investigation. Managerial and the technical The main purpose of these approaches to the work. investigations is to identify, register and available technologies / materials etc. catalogue the resources DPE NOTES , PROJECT PLANNING (water/hydropower) existing in the river The following issues should be recorded basins areas, districts and provinces. properly: The identified project sites are often – Terrain features such as location ranked according to size, cost, benefits, and placement of structure, geo.- etc. technical problems related etc. Preparation of resources inventories – Infrastructure such as access to and their updation is a continuous project elements, etc. process and should not be stopped at – Settlements and resettlement issues any time. – Availability of construction materials PROJECT PLANNING IN PRACTICE – Environmental issues The major planning stages of projects are: – Multipurpose uses - Desk Studies – Diversion of flow during construction - Reconnaissance Survey and construction of cofferdams. - Appraisal Reports – In case of reservoir and tunnel - Ranking Studies project special attention is to be paid - Pre-Feasibility Studies to geo-technical and engineering - Feasibility Report geology - Detail Engineering Design APPRAISAL REPORT - Preparation of Tender Documents • The appraisal report is the DESK STUDIES presentation of desk studies and • Collection of Data reconnaissance survey which would Relevant data and information are describe the merits and demerits of collected which may include: the project. Infrastructure information • The report must conclude with a Hydrology statement on the viability and Topography suitability of the project under Geology and geo-technical consideration. engineering • The appraisal report will present the Environmental issues either go-ahead signal or the Socio-economic set-up stoppage for further studies. • Analysis of Data RANKING STUDIES Based on available data and After the appraisal report, if there are information, the first step of the desk more than one project, the Ranking study is to establish the main project Studies are carried out in details. parameters such as: Ranking criteria is laid down usually Flow and regulation based on; Needs of the area Need of the area Existing and future water uses, such Potential to be developed as irrigation, drinking and Access to the project area hydropower. Benefits to be derived Environmental constraints. Irrigation or hydropower project RECONNAISSANCE SURVEY Irrigation cum hydropower The desk studies should be followed by project field visits, because plans prepared in Multipurpose project office need verification in the field. The Economic and financial evaluation project layout and its elements are weightage visualised in the actual surroundings to PRE-FEASIBILITY STUDIES check and compare. Alternative • A pre-feasibility study is the second solutions will then be finalised. organised step in the project investigation and planning. DPE NOTES , PROJECT PLANNING • In pre-feasibility study, one or more vii. Finance – its availability and project alternatives are proposed constraints. and studied before selection. SITE SELECTION FOR A RESERVOIR • Pre-feasibility studies may change • The cost of the dam is generally a considerably the layout proposed at controlling factor in the selection of a identification level. reservoir site. • The main purpose of the pre- • The geological formations for the feasibility study is to: reservoir banks, walls etc. should be – Establish demand for the project. such as to entail minimum leakage. – Formulate a plan for developing • The geology of the catchment area this project should be such as to entail minimum – The project is technical, water losses through absorption and economical and environmental percolation. acceptable. • The site should be such that a deep – Make recommendation for future reservoir is formed. A deep reservoir is action. preferred to a shallow one because of FEASIBILITY REPORT lower land cost per unit of capacity, • Feasibility studies are carried out to less evaporation loss and less determine the technical, economical possibility of weed growth. and environmental viability of a • The reservoir site must have adequate project. capacity. • This phase of investigation consist of • Too much silt laiden tributaries should a detailed investigation and study. be avoided as far as possible. • A feasibility study also serves as • The reservoir basin should have a deep basic document for financing. narrow opening in the valley so that the • Feasibility studies are sufficiently length of the dam is minimum. detailed and ensure that during detailed engineering, the feasibility TOPOGRAPGHY of the project is not impaired due to Survey is generally required in the following major alterations in the plan. areas: PRELIMINARY INVESTIGATIONS – The storage basin to determine the The investigations normally includes volume available below various levels, considerations of the following: and the existence of any low saddles i. Physical factors such as topography, around the perimeter. hydrology, geology. – The dam-site to determine : ii. National or International policies; • Quantities of excavation and even the type of dam may be material in the dam; influenced by such policies rather • For setting out the dam structure; than by minimum cost. • For layout of plant, access roads iii. The purpose of the dam and how it and other pertinent structures; fits into existing or future plans for • Site Maps (dam, intake, sediment water conservation and utilization in excluder, forebay, powerhouse, the region. etc.) iv. Availability of resources, both • Scale may be 1:1000 or 1:500 or materials and skills. 1:200 with contour intervals of 1 v. Ultimate safety of the present or meter. future inhabitants of the area. • Reservoir area vi. Environmental impact – river • Scale may be 1:2500 or 1:5,000 morphology, socio-economic with contour intervals of 5 meter. conditions, wild life etc. • Catchment area DPE NOTES , PROJECT PLANNING Scale may be 1:50,000 or 1:25,000 PROJECT CLEARANCE PROCESS with contour intervals of 5 meter. • The important steps involved in the • General maps project cycle are: Scale may be 1:5,000 or 1:10,000 – Planning with contour intervals of 5 meter. – Implementation Hydrological Studies – Operation and Maintenance • Hydrological data are required for the following: • To keep the control on various steps – To ascertain the flow availability for involved in project development and the intended purpose. also control on executing agencies, – Flood estimation to design the the Government of Pakistan has diversion during construction, bottom devised a project cycle which outlets and spillways. comprises: – The present and future water uses – Approval for other purposes such as irrigation, – Review and Monitoring industrial, domestic, navigation, etc. – Evaluation – Existing water rights should be • To remain well informed about a recognised and protected. development project, Government GEOLOGICAL STUDIES of Pakistan has designed different • Studies are required to determine the forms for the purpose of planning, suitability of foundation conditions for monitoring and reporting during dams and other major structures. different stages of project cycle; • Investigations – PC-II Proforma – Core drilling: It is an excellent but – PC-I Proforma costly method. Information, such as – PC-III Proforma physical properties of rock, water – PC-IV Proforma and tightness, depth of weathering, faults – PC-V Proforma zones, etc. can be obtained. • PC-II PROFORMA – Seismic refraction: It is normally It deals with project proposal and used to reduce the amount of drilling works. However, their results need is required for conducting surveys and to be calibrated with core drilling. feasibility studies, in respect of large – Pilot tunnels, shafts, trench and test projects. The objective of this is to get pits are other investigation methods, full justification for undertaking the which may be done according to site project. conditions and information • PC-I PROFORMA requirements. It deals with the preparation of – Simple drilling: It is used in case of projects for implementation. The PC-I is deposited soil to find out the prepared after detailed feasibility study lithology, permeability, density, etc. has been completed. However, detailed of the subsurface. design and drawings are not pre- – Reservoir area should be investigated for reservoir tightness, requisite for the approval and change in ground water level and preparation of PC-I quality, risk of landslides to rapid • PC-III PROFORMA drawdown, stream erosion and This proforma is designed to formation of deltas, etc. furnish information on the progress of – Laboratory testing is required to on-going projects on quarterly basis. analyse the samples taken in the • PC-IV PROFORMA field. DPE NOTES , PROJECT PLANNING
The project completion report on • National Economic Council (NEC)
PC-IV is to be furnished by every It approves all policies and plans Project Director /executing agency only relating to development. It is headed by once, soon after a project is completed. the Country Chief Executive • PC-V PROFORMA (President/Prime Minister). Federal This is to be furnished on an ministers in charge of economic annual basis for a period of five-years ministries, Deputy Chairman of the by the agencies responsible for planning commission and the operation and maintenance of the Governors/Chief Ministers of the projects provinces are its members. PC – I PROFORMA It approves all federal & PC MODEL OF PROJECT CYCLE provincial schemes above Rs. 100 million. • PC-I Proforma for Production • Executive Committee of National Sectors Economic Council (ECNEC) • PC-I Proforma for Infrastructure The Federal Minister of Finance Sectors heads it and its members include • PC-I Proforma for Social Sectors Federal Ministers of Economics, Provincial Governors/Chief Ministers or • Production Sectors their nominees and the provincial – Agriculture Production ministers concerned. It has the following – Agriculture Extension functions: – Industries, Commerce and – To sanction development schemes in Minerals public and private sectors. • Infrastructure Sectors – To allow moderate changes in the – Transport & Communication plan and in the plan allocations – Telecommunication – To supervise the implementation of – Information Technology economic policies laid down by the – Energy (Fuel & Power) National Economic Council (NEC). – Housing, Government Buildings & It approves all schemes above Rs. 100 Town Planning million. – Irrigation, Drainage & Flood Control • Central Development Working Party (CDWP) • Social Sectors The Deputy Chairman of the Planning – Education, Training and Commission heads the CDWP and is Manpower joined by secretaries of the federal – Health, Nutrition, Family Planning ministries concerned and the heads of & Social Welfare the planning departments of the – Science & Technology provincial governments as its members. – Water Supply & Sewerage It scrutinises all the development – Culture, Sports, Tourism & Youth projects prepared by the federal – Mass Media ministries, provincial governments, – Governance autonomous organisation, etc. for the – Research purpose of approval by ECNEC. PROJECT APPROVING BODIES DPE NOTES , PROJECT PLANNING
It is competent to approve development • Economic Co-ordination
project up to certain financial limits. Committee of the Cabinet Projects exceeding the limits are (ECC) submitted for approval to ECNEC. It consists of the Federal Minister for Federal schemes costing between Rs. Finance as head and Federal Ministers 20 million and Rs. 100 million; subject to of economic ministries as its members. the condition that the Ministry of Finance It gives approval to the projects in does not disagree. private sector and keeps vigilance on the monetary and credit situation and • Provincial Development Working makes proposals for the regulation of Party (PDWP) credit in order to maximise production It is headed by the Chairman and exports and to prevent inflation. It Development Board/Additional Chief also co-ordinates the economic policies Secretary and includes Secretaries of initiated by the various divisions of the the provincial departments concerned Government. with development as its members. It scrutinises various projects for approval up to a certain financial limits (Rs.100 PC MODEL OF PROJECT CYCLE M). Projects exceeding this limit are submitted to the CDWP for approval. • Department Development Working Party (DDWP) It is a body for approving development projects for federal ministries/divisions/departments according to their approved financial limits (< Rs. 20 M). It is headed by the respective secretary/head of department. Its members are representatives of Finance Division and concerned Technical Section in the Planning and Development Division.
• Cabinet Committee on Energy
It comprises the Prime Minister as its Chairman, Finance Minister as Vice Chairman, and Minister for Planning and Development, Minister for Petroleum and Natural Resources and Minister for Water and Power as its members. It is responsible to approve plans, policies and development schemes costing more than the powers of approval by the concerned Ministry or Deptt.