MS Project
Overview
Prepared By
Maher Al-Mohamad
ERP Functional Analyst
Objectives
• Projects management Basics
• Getting started with MS Project
• Creating a project ( Tasks, Resources, …)
• Views and Reports
[email protected]
Projects Management
Introduction
A Project is
A temporary endeavor
undertaken to create a unique
product, service, or result.
[email protected]
Project Life Cycle (Phases)
• Initiation Planning
• Planning
Execution
Initiation Closure
•
• Closure Execution
[email protected]
Projects Management is
The application of knowledge, skills, tools, and techniques
to project activities, in order to meet or exceed stakeholder
needs and expectations from a defined project - balancing
the following:
• Scope, time, cost, and quality
• Stakeholders’ expectations
• Requirements (needs) vs. unidentified requirements (expectations)
[email protected]
PM Process Groups
Monitoring and Controlling
• Initiating Planning
• Planning
• Executing Initiating Closing
• Monitoring and Controlling
• Closing Executing
[email protected]
Project Life Cycle with PM
Project Manager
A project manager is a professional in the field
of project management.
Project managers can have the
responsibility of the planning,
execution, and closing of any
project.
[email protected]
MS Project
Microsoft Project is a project management
software program, which is designed to assist a
project manager in developing a plan, assigning
resources to tasks, tracking progress, managing the
budget, and analysing workloads.
[email protected]
Note
Microsoft project expert isn’t a replacement for
the project manager.
Microsoft Project doesn’t ensure a successful
project if a person doesn’t understand project
management. However, Microsoft Project can assist
a project manager in becoming more effective.
[email protected]MS Project
Getting Started
Start a new project
The MS Project interface
Toolbar
Ribbon
Main Screen
components
Schedule a Project from a Start or Finish Dates
Setting working Days
Gantt Chart
Task Spreadsheet Gantt Diagram
[email protected]
Working with Tasks List
Adding the essential data of tasks :
Task name
Duration (D, W, H, M, Mo)
Predecessors
Task Information
Task Mode, Milestones, Summary, Sub Task, …
Task Relationships
Creating Tasks Relationships
Note:
MS project will calculate dates
based on the durations of the tasks,
their relationships and the start date
set for the project, however it is
possible to change the starting date
of a task (if necessary) By double
clicking on a Task or milestone, and
using the fields related to the dates
(Start or Finish).
FS Finish-to-Start Relationship
Predecessors
Duration
FS
Task/Resources
Successors
[email protected]
SS Start-to-Start Relationship
Predecessors
SS
Task/Resources
Successors
[email protected]
FF Finish-to-Finish Relationship
Predecessors
FF
Task/Resources
Successors
[email protected]
SF Start-to-Finish Relationship
Predecessors
SF
Task/Resources
Successors
[email protected]
Overlap
Predecessors
Overlap
Task/Resources
Successors
[email protected]
Lag
Predecessors
Lag
Task/Resources
Successors
[email protected]
The Critical Path
CP is the flow of tasks, of which, a delay in any one of
these tasks will cause a delay to the project.
It is the longest path through the project network
diagram and the shortest possible time to complete
the project.
[email protected]
Showing Critical Path
Project Statistics
Working with Resources List
You can use the Resource Sheet to create a list of
the people, equipment, and material resources.
Assigning Resources to Tasks
1. Assign Resources Using Task List Resources Name Column
Assigning Resources to Tasks
2. Assign Resources Using Task Information, Resources Tab
Assigning Resources to Tasks
3. Assign Resources Using Resource Tab
Over allocated Task Resource
Complete adding Task Resources
Project Statistics – Cost Updated
Task Usage View
Network Diagram View
Task Form
Resources Form
Resources Using View
Team Planner View
Calendar View
Resource Overview Report
Cost Overruns Report
Printing the Project Map