01 G E N E R AL
01.01 This specification covers the materials, tools, facilities and quality
requirement for surface preparation and painting of steel structures,
equipment, piping, ducts, chutes, wood work etc.
01.03 The term “painting” referred herein covers rust preventive, fungus/insects
preventive and decorative coating along with surface protection of the
following area but not limited to the areas indicated below.
01.05 T h e c o m p l e t e p a i n t s ys t e m f o r a n y i t e m i n c l u d e s t h e f o l l o w i n g b a s i c
activities:
All the above coats shall be of quality paint products and of approved
m ak e . T h e s c o p e o f w o r k s h a l l a l s o i n c l u d e s u p p l y o f a l l p a i n t m a t e r i a l s a s
per specification described herein.
01.06 I f t h e c o n t r a c t o r d e s i r e s t o a d o p t a l t e r n a t i v e p a i n t s ys t e m f o r a n y s p e c i f i c
i t e m f o r a n i m p r o v e m e n t o r e q u i v a l e n t t o t h e s ys t e m s p e c i f i e d h e r e - i n o r
as per recommendations of paint manufacturer, may do so subject to
purchaser’s approval in advance.
02 S U R F AC E P R E P AR AT I O N
02.02 All surfaces shall be cleaned of loose substances, and foreign materials,
such as dirt, rust, scale, oil, grease, welding flux, etc. in order that the
prime coat is rigidly anchored to the virgin metal surface. The surface
preparation shall confirm to pictorial representation of surface quality
g r a d e o f S we d i s h S t a n d a r d s I n s t i t u t i o n SIS – 055900 or equivalent
standards such as SSPC – VIS – 1.67 or DIN 55928(Part 4) or BS 4232 or
IS 1477 – 1971 (Part I)
02.03 The acceptable surface preparation quality / grade are described under
e a c h p a i n t s ys t e m . T h e p r o c e d u r e s i n c l u d e s o l v e n t c l e a n i n g , h a n d t o o l
cleaning, power tool cleaning, blast cleaning, wood surface cleaning,
f l a m e c l e a n i n g a n d p i c k l i n g . T h i s wi l l e n s u r e s u r f a c e q u a l i t y a s r e q u i r e d
by the specific primer paint. For ready reference surface preparation
quality grade to be adopted in respect of SIS 055900 and DIN 55928
(part-4) is given in Annexure-01.
T h e s u r f a c e s h a l l b e c l e a n e d b y w i p i n g , i m m e r s i o n , s p r a yi n g o r v a p o u r
c o n t a c t i n g o f a s u i t a b l e s o l v e n t o r wa s h i n g wi t h a n e m u l s i o n o r a l k a l i n e
solution to remove oil, grease, dirt, old paint, etc. Solvent cleaning shall
n o t r e m o v e r u s t , s c a l e s , m i l l s c a l e s o r we l d f l u x . T h e r e f o r e , b e f o r e
a p p l i c a t i o n o f p a i n t , s o l v e n t c l e a n i n g s h a l l b e f o l l o we d b y o t h e r c l e a n i n g
procedures as stated in subsequent clauses.
surface scales are removed by hand tools or power tool cleaning. The
extent of removal of adherent scales is varied, depending on the
application and are defined by the surface quality grades Sa1, Sa2, Sa2.5
and Sa3 in the order of increasing cleanliness. The blast cleaning is not
recommended for sheet metal work.
T h e s u r f a c e i s c l e a n e d b y r a p i d h e a t i n g b y m e a n s o f o x ya c e t yl e n e f l a m e
to loosen the adherent scales, followed immediately by wire brushing.
T h i s m e t h o d w i l l r e m o v e l o o s e l y a d h e r e n t m a t e r i a l s a s we l l a s m o s t o f t h e
a d h e r e n t s c a l e s a n d m i l l s c a l e s . I n o r d e r t o m i n i m i ze o r p r e v e n t d i s t o r t i o n
f l a m e c u t t i n g s h a l l n o t b e u s e d o n m em b e r s h a v i n g t h i c k n e s s o f 6 m m a n d
lower.
02.03.06 Pickling
In this method the surface is cleaned of mill scales, rust or rust scales by
c h e m i c a l r e a c t i o n o r e l e c t r o l ys i s o r b o t h .
03. P AI N T AP P L I C AT I O N
03.01 Paints
03.01.03 In the event of conflict between this general procedure on painting and
the paint manufacturer’s specification, the same shall be immediately
brought to the notice of the Purchaser. Generally in cases of such
conflicts, manufacturer’s specifications/recommendations shall prevail.
03.01.04 B e f o r e b u yi n g t h e p a i n t i n b u l k , i t i s r e c o m m e n d e d t o o b t a i n s a m p l e o f
paint and establish “Control Area of Painting”. On Control Area, surface
preparation and painting shall be carried out.
(i) Viscosity
(ii) Adhesion/Bond of paint in steel surfaces
(iii) Adhesion/Simulated salt spray test.
(iv) C h e m i c a l a n a l ys i s ( p e r c e n t a g e o f s o l i d s b y w e i g h t )
(v) Normal wear resistance as encountered during handling & erection.
(vi) Resistance against exposure to acid fumes, etc.
03.01.06 W h o l e q u a n t i t y o f p a i n t f o r a p a r t i c u l a r s ys t e m o f p a i n t s h a l l b e o b t a i n e d
f r om t h e s a m e m a n u f a c t u r e r .
03.01.07 The main Contractor shall be responsible for supply of paints and this
responsibility shall not be passed on to the sub-contractor.
03.01.09 T h i n n e r s wh e r e v e r u s e d s h a l l b e t h o s e r e c o m m e n d e d b y t h e p a i n t
manufacturers and shall be obtained in containers with manufacturer’s
name and brand name of thinner legibly printed, failing which the thinner
is liable to be rejected and shall not be used.
03.01.10 All paint containers shall be clearly labeled to show the paint
identification, date of manufacture, batch number, special instruction,
shelf life etc. The container shall be opened only at the time of use.
03.01.11 All paints shall be stored in accordance with the requirements of laid
down procedure by the paint manufacturer.
03.01.14 The colour code of the finishing paint to be followed shall be intimated to
the successful Tenderer after finalisaiton of order. The undercoat shall
have different tint to distinguish the same from the finishing coat.
03.01.15 The Contractor shall furnish paint manufacturer’s test report or technical
data sheet pertaining to the paint selected. The data sheet shall indicate
a m o n g o t h e r t h i n g s t h e r e l e v a n t s t a n d a r d s , i f a n y, c o m p o s i t i o n i n we i g h t
p e r c e n t o f p i g m e n t s , v e h i c l e s , a d d i t i v e s , d r y i n g t i m e , v i s c o s i t y, s p r e a d i n g
rate, flash point, method of application, quality of surface preparation
required, corrosion resistance properties and colour shades available.
03.02 General
03.02.01 Each coat of paint shall be continuous, free of pores and of even film
t h i c k n e s s wi t h o u t t h i n s p o t s .
03.02.02 Each coat of paint shall be sufficiently dr y before application of next coat.
03.02.04 Z i n c r i c h p r i m e r p a i n t s wh i c h h a v e b e e n e x p o s e d s e v e r a l m o n t h s b e f o r e
finishing coat is applied shall be washed down thoroughly to remove
soluble zinc salt deposits.
03.02.05 T h e m a c h i n e f i n i s h e d s u r f a c e s s h a l l b e c o a t e d w i t h wh i t e l e a d a n d t a l l o w
before shipment or before being put out into the open air.
03.02.06 Areas which become inaccessible after assemble shall be painted before
a s s e m b l y ( a f t e r o b t a i n i n g p a i n t i n g c l e a r a n c e f r om t h e i n s p e c t i n g a u t h o r i t y)
after requisite surface cleaning as specified.
03.02.07 P a i n t s h a l l n o t b e a p p l i e d wh e n t h e a m b i e n t t e m p e r a t u r e i s 5 d e g C a n d
below or 45 deg C and above. Also paint shall not be applied in rain,
wind, fog or at relative humidity of 80 % and above unless the
manufacturer’s recommendations permit. Applications of paint shall be
o n l y b e s p r a yi n g o r b r u s h i n g a s p e r I S 4 8 6 – 1 9 8 3 a n d I S 4 8 7 – 1 9 8 5 .
03.02.08 Primer paint shall be applied not later than 2 – 3 hours after preparation
of surface, unless specified otherwise.
03.02.09 Edges, corners, crevices, depressions, joints and welds shall receive
special attention to ensure that they receive painting coats of the required
thickness.
03.02.10 Surfaces which cannot be painted but require protection shall be given a
coat of rust inhibitive grease according to IS 958 – 1975 or solvent
deposited compound according to IS 1153 – 1975 or IS 1674 – 1960.
03.02.11 Surfaces in contact during shop assembly shall not be painted. Surfaces
which will be inaccessible after assembly shall receive minimum two coats
of specified primer.
03.02.12 Surfaces to be in contact with wood, brick or other masonr y shall be given
one shop-coat of the specified primer.
03.03.02 If more than 50% of the painted surface of an item requires repair, the
entire item shall be mechanically cleaned and new primer coats shall be
applied followed by intermediate and finishing coats as per painting
specification.
03.03.03 A l l f i e l d we l d e d a r e a s o n s h o p p a i n t e d i t e m s s h a l l b e m e c h a n i c a l l y
cleaned (including the weld area proper, adjacent areas contaminated by
w e l d s p a t t e r o r f u m e s a n d a r e a s wh e r e e x i s t i n g p r i m e r p a i n t i s b u r n t ) .
S u b s e q u e n t l y, n e w p r i m e r a n d f i n i s h i n g c o a t s o f p a i n t s h a l l b e a p p l i e d a s
per painting specification.
03.03.04 T h e f i r s t c o a t o f f i n i s h p a i n t a t s i t e s h a l l b e a p p l i e d p r e f e r a b l e wi t h i n t h r e e
months of the shop paint.
03.04 Structural
03.04.01 All fabricated steel structure, fabricated steel pipes, etc. shall have a
m i n i m um o f t w o c o a t s o f p r i m e r p a i n t b e f o r e d i s p a t c h t o s i t e .
03.04.03 All structures shall receive appropriate number of primer and finishing
coats in order to achieve overall DFT as per design
drawings/specification.
03.05.01 Total DFT for heat resistant paints should not exceed 100 – 120 microns,
otherwise flaking occurs (as per paint manufacturer’s recommendations).
03.05.03 Primer coat should not be applied on the surfaces having temperature
condition more that 120 deg C.
04 P AI N T I N G S C H E M E S
F o r a c o m p l e t e p a i n t i n g s c h e m e o f a n y i t e m b e i n g p r i n t e d , a l l t yp e s o f
p a i n t s a r e t o b e p r o c u r e d f r o m t h e s a m e m an u f a c t u r e r a s a p p r o v e d b y t h e
purchaser.
04.01 Legend
T yp e o f p a i n t p r o d u c t s l i k e P 1 t o P 9 , I 1 t o I 4 a n d F 1 t o F 1 0 h a v e b e e n
specified under Annexure-02.
04.03 The colour code for different applications are indicated in Annexure-04.
W herever colour codes are not specified, the same is to be mutually
agreed between the Purchaser and Contractor.
05. G U AR AN T E E
05.01 T h e C o n t r a c t o r s h a l l g u a r a n t e e t h a t t h e p h ys i c a l a n d c h e m i c a l p r o p e r t i e s
of the paint materials conform with the specification of paint products.
05.02 The Contractor shall submit internal test reports from paint manufacturers
regarding the quality of paint whenever asked by the
Purchaser/Consultant.
05.03 Guarantee period shall commence from the date of completion of finishing
coat of paint. The guarantee period will be indicated depending on the
t yp e o f s u r f a c e p r e p a r a t i o n a n d s ys t e m o f p a i n t i n g . T o f u l f i l l t h i s
obligations the Contractor may obtain from the painting manufacturer,
guarantee for the performance of paint/painted surfaces.
Annexure-01
Surface Preparation Grade
Annexure - 02
P AI N T M AT E R I AL S
01. P R I M E R P AI N T S ( P )
01.01 P r i m e r P a i n t – P 1 ( P h e n o l i c – Al k y d B a s e d )
A s i n g l e p a c k a i r d r y i n g p h e n o l i c m o d i f i e d a l k yd c o m p o s i t i o n w i t h z i n c
phosphate as a primer paint conforming generally to IS : 2074.
DFT/Coat - 80 microns
0
Temperature resistance - Upto 80 C dry heat
A t w o p a c k a i r d r yi n g E p o x y p o l ya m i d e r e s i n b a s e d r e d o x i d e - z i n c
phosphate primer.
A t w o p a c k a i r d r yi n g E p o x y p o l ya m i d e w i t h zi n c d u s t o f a t l e a s t 9 2 % z i n c
dust on the dr y film
A t w o p a c k a i r d r yi n g p o l yv i n yl b u t yr a l r e s i n b a s e d w a s h p r i m e r w i t h r u s t
inhibitive pigments.
DFT/Coat - 8 microns
0
Temperature resistance - Upto 65 C dry heat
A t wo p a c k h e a v y d u t y z i n c d u s t r i c h s i l i c a t e p r i m e r wh i c h p r o t e c t s t h e
surface with just a single coat.
A ir dr yi n g t im e - T o t op c o a t 16 ho ur s
DF T / c o at - 60 m ic r o ns
T em per at ur e r es is t a nc e - Up to 45 0 d eg C dr y h e at
01 . 08 P ri m e r P a in t – P8 ( H i g h B u i ld Co al T a r Ep o x y)
A t wo p ac k c o l d c ur ed H. B. ep ox y c o a l tar c o at i ng – no pr im er is r e qu ir e d.
M ix i n g r a ti o - B as e : Ha r d e ner ( 4: 1b y v o l .)
A ir dr yi n g t im e - 48 ho ur s ( h ar d dr y)
F u l l c ur e 7 d a ys
DF T / C oa t - 10 0 m ic r o ns
01 . 09 W o o d V a rn i sh - P 9
A ir dr yi n g t im e - 16 ho ur s f or a pp l ic at i o n of
to p c o at .
Co v er ag e - 10 t o 1 4 s q . m /l it r e
02 . INT E RM EDI AT E P AI N T S ( I)
02 . 01 In t er m e d i at e P ain t - I I ( P h e n o l i c al k yd b a s e d )
A s i n g le p ac k hi g h b u il d p h en o l ic b as e d p a in t wit h m ic ac e o us i r on ox id e
( M 10) .
A ir Dr yi n g T im e - 4 to 6h o ur s ( to uc h dr y) -
2 d a ys ( ha r d d r y)
DF T /C o at - 7 5 m ic r ons ( m in)
T em per at ur e r es is t a nc e - Up to 10 0 d eg C d r y h e at
Com pa t ib l e wi t h - P r im er P 1
02 . 02 In t er m e d i at e P ain t - I 2 ( Ch lo ro ru b b e r b a s ed )
A s i n gl e p ac k a ir dr yi n g h ig h b u i ld c h l or o b a s ed pa i nt wi th MIO .
A ir Dr yi n g T im e - 1 5 m i nu t es ( to uc h dr y)
- 24 ho ur s ( h ar d dr y)
DF T /C oa t - 70 m ic r o ns ( m i n )
T em per at ur e r es is t a nc e - U pt o 6 5 d eg C d r y h e at
Com pa t ib l e wi t h - P r im er P 2, P 3 & P 4
02 . 03 In t er m e d i at e P ain t - I 3 ( P V C – Al k yd B a se d )
P VC C op l o ym er - Res i n 1 : 1
P igm e nts - M ic ac e ous ir o n ox i d e ( MIO )
DF T /C oa t - 80 m ic r o ns ( m i n)
T em per at ur e r es is t a nc e - Up to 80 d e g C dr y h e a t
Com pa t ib l e wi t h - Pr im er P2 & P 3
02 . 04 In t er m e d i at e p ai n t - I 4
A t wo p ac k a ir dr yi n g h ig h b u il d e p ox y r es in bas e d p ai n t wi t h MI O .
A ir dr yi n g t im e - 6 to 8 ho ur s ( t o uc h d r y)
- 7 d a ys ( f u l l c ur e)
DF T / c o at - 10 0 m ic r o ns
0
T em per at ur e r es is t a nc e - Up t o 1 80 C dr y h ea t
Com pa t ib l e wi t h - Pr im er P4 & P 5
03. F I N I S H P AI N T S ( F )
Finish paint costs shall be applied over primer coats and intermediate
coats after proper cleaning and touch up of primed surface.
A s i n g l e p a c k a i r d r y i n g h i g h g l o s s p h e n o l i c a l k yd m o d i f i e d s yn t h e t i c
enamel paint suitably pigmented.
A s i n g l e p a c k a i r d r yi n g p o l yu r e t h a n e e n a m e l o f h i g h g l o s s a n d h a r d f i n i s h
suitably pigmented.
A t w o p a c k a i r d r yi n g b i t u m i n o u s a l u m i n u m p a i n t .
A r e a d y m i x e d o i l - a l k yd b a s e d s yn t h e t i c e n a m e l p a i n t o f h i g h g l o s s a n d
hard wearing properties.
Compatible with - P8
A s i n g l e p a c k a i r d r yi n g p l a s t i c i z e d c h l o r o r u b b e r p a i n t s u i t a b l y p i g m e n t e d .
A P V C – C o p o l ym e r a l k yd b a s e d e n a m e l .
DFT/Coat - 40 microns
A t w o p a c k a i r d r yi n g e p o x y p o l ya m i d e e n a m e l s u i t a b l y p i g m e n t e d .
A s i n g l e p a c k s yn t h e t i c r u b b e r b a s e d a l u m i n i u m p a i n t .
Annexure - 03
PAINTING SCHEME
2P8 200
Notes: -
1. Painting scheme of all fabricated steel structures, fabricated pipe work, building
s t r u c t u r e , c o n v e yo r g a l l e r i e s , p i p e t r e s t l e s e t c . i s i n d i c a t e d i n t h e T e c h n i c a l
Specification of steel structures.
2. Primer Paint
3. Finish Paint
I n c a s e o f A l u m i n i u m c l a d d i n g f i n a l p a i n t i n g wi l l n o t b e r e q u i r e d .
ANNEXURE - 04
COLOUR CODE
The colour codes are mentioned for all the items including pipe work. Shades of finish coat of paint applied
over respective item indicated below are tentative and subject to alteration as per Purchaser’s request or due
to compatible paint system adopted. The service for which colour code/bands are not specified are to be
mutully agreed for by the Purchaser & the Contractor.
3. Pipe work
Colours shall be as given below. The base colour shall be applied throughout entire length except
on surfaces of materials such as asbestos, aluminium, brass, bronze, galvanized steel, stainless
steel and other corrosion resistant alloys and rubber / synthetic polymers. In such cases
identification colour bands of at least 500mm width shall be provided near each branch, valve and at
distances not exceeding 10m either as local colour coatings or coloured adhesive type of suitable
material or label attached to the pipe work. Additional identification bands superimposed over the
base colour shall be provided near each branch, valve and at distance not exceeding 10m. The
bands shall be atleast 25mm wide except in care of double bands where the first band shall be about
100mm wide. Direction of flow shall be clearly marked on the pipelines at intervals not exceeding
10m and all branches and change of directions.
Note : For these services, hazard marking as per fig. 4C of IS:2379 shall also be provided.