Part - G Economic Analysis
Part - G Economic Analysis
Contents
Analytical
AnalyticalFramework
Framework
and
andModel
Model
Descriptions
Descriptions
Introduction
Introduction
Part
PartAA
Traffic
Traffic
Part
PartBB
RD
RDModel WE
WEModel RUE
Model Model RUEModel
Model SEE
SEEModel
Model
Part
PartCC Part
PartDD Part
PartEE Part
PartFF
Economic
EconomicAnalysis
Analysis
RD = Road Deterioration Part
PartGG
Nomenclature
Nomenclature
WE = Road Works Effects Part
PartHH
G1 Economic Analysis
1 Introduction
HDM-4 caters for three applications levels commonly used in decision making within the road
sub-sector. The different applications, which are described in more detail in the Applications
Guide, are:
1 Strategic planning
For estimating medium and long-term budget requirements for the development and
preservation of a road network under various budgetary and economic scenarios.
2 Programme analysis
For preparing single or multi-year work programmes under budget constraints, in which
those sections of the network likely to require maintenance, improvement, or new
construction, are identified in a tactical planning exercise.
3 Project analysis
For estimating the economic or engineering viability of different road investment projects
and associated environmental effects. Typical projects include the maintenance and
rehabilitation of existing roads, widening or geometric improvement schemes, pavement
upgrading and new road construction.
For all the three applications, the underlying operation of HDM-4 is based on the concept of
life cycle analysis under a user-specified scenario of circumstances. This involves the analysis
of pavement performance, road works effects and costs, together with estimates of road user
costs and environmental effects, and economic comparisons of different project alternatives.
This chapter describes how HDM-4 is used to determine the benefits and costs associated with
a road investment, and how these are applied in economic analysis and optimisation
procedures to find the best use of available resources.
2 Background
2.2 Optimisation
The purpose of the Strategy and Programme applications is to calculate the economic benefits
derived from maintenance or improvement options, and to select the set of investments to be
made on a number of road sections within a network which will optimise an objective
function.
Programme analysis is concerned with short to medium term planning and preparation where
budget levels are known with reasonable certainty and the objective is to select a set of road
sections and road works within the budget constraint.
Strategy analysis involves the analysis of an entire road network (or sub-network). The
objective is either to determine which types of road works should be applied in order to
maximise economic benefits, or it may also be applied to determine the budget required for a
given long term target road network condition. Thus, the problem can be posed as one of
searching for the combination of investment alternatives that optimises the objective function
under a budget constraint or a road network condition constraint. Note that the set of
investment options to be optimised is user-defined and is not the set of all possible options for
the particular network; hence the problem is not true optimisation since all possible solutions
are not normally considered. Note also that the investment options on any one road section are
mutually exclusive.
The three alternative objective functions provided for the Strategy and Programme
applications are:
This option is used when the problem can be defined as the selection of a combination of
investment options applied on several road sections which maximises the NPV (net
present value) for the whole network subject to the sum of the financial costs being less
than the budget available.
2 Maximisation of the improvement in network condition
The roughness reduction on each road section multiplied by the section length
(∆IRI*Length) is used instead of NPV. Consequently, the arithmetic procedure is similar
to that used for maximisation of economic benefits.
3 Minimise costs of road works to achieve a given target road network condition
This option is used mainly in the Strategy analysis application. The target road condition
defined in terms of the long-term average roughness (IRI) over the whole analysis period
must be specified for each road section. The optimisation procedure is then reduced to a
simple selection of the road work options for which the average IRI (over the analysis
period) is equal to or just below the target IRI and has the lowest total financial cost.
For example, vehicle operating costs, savings in travel time, accident costs.
2 Quantified benefits and costs not expressed in monetary terms
For example, road safety, pollution from vehicle emissions and traffic noise.
3 Non-quantified benefits and costs
The cost of works is derived from the product of the physical quantities involved in the
activity and the unit cost. These are determined for each road section and investment option,
and for each year of the analysis period. The resulting costs are assigned to budget categories
that are user-definable. The following default categories are used in HDM-4:
! Capital (or periodic)
! Recurrent (or routine)
! Special
Budget constraints can be applied separately to each category when required by the economic
analysis and optimisation.
❏ Overheads
! Travel time costs
These costs include passenger travel time costs, and cargo holding time costs.
! Non-motorised transport (NMT)
These costs are evaluated both in monetary and non-monetary terms, and separated into
several different types (for example, fatal, injury, and damage only, and all accidents). Note
users are allowed the flexibility to include or exclude accident costs from an economic
analysis.
These unit costs are specified by the user (see Part D).
! Road user costs
These unit costs include vehicle resources, travel-time values, and road accident
resources (see Part E).
In most cases, unit costs are specified in units-per-quantity. However, some costs are specified
as a proportion of other costs, or as a lump sum.
In addition to calculating economic costs, financial costs are also computed if the user gives
appropriate inputs (for example, unit costs in financial terms).
4 Outline methodology
Road geometry and surface Social and Levels of emissions and energy
texture, vehicle characteristics Environmental Effects used, and number of accidents
4.3 Models
Total life-cycle conditions and costs of sections or road networks can be simulated over a
user-defined period into the future. The inter-dependence between the costs incurred by the
road administration and the road user is recognised, and models are used to predict cost
streams under the various headings.
The models incorporated in HDM-4 contain technical relationships for the following
purposes:
1 Calculation of traffic volumes and flows, and vehicle loading over the road section.
2 Prediction of road deterioration, and works effects and costs, that are incurred in response
to traffic flows, time and the surrounding environment.
3 Prediction of the costs of road use incurred as road condition and traffic flow change over
time.
4 Prediction of accident rates as a function of the road and traffic characteristics, and the
evaluation of accident costs.
5 Evaluation of vehicle emissions and energy use due to different road investment projects.
6 Economic analysis by comparison of the impacts or effects of different road investment
project alternatives.
Enabling economic comparisons to be made for each pair of investment options, using
the effects and costs calculated over the analysis period for each option, and indicates
that generated and diverted traffic levels may vary depending on the investment option
considered.
2 Costs
How annual costs to the road administration and to the road users are calculated for
individual road section options.
3 Optimisation procedures
These are performed after economic benefits of all the section options have been
determined.
The pseudo code that represents the outer analysis loop is given below:
START
Define input data
Loop for each option
Loop for each section
Loop for each analysis year
Calculate traffic over the road section
Calculate total non-discounted net benefits over all the sections (see Figure
G1.2c)
Calculate total discounted net benefits over all the sections (see Figure G1.2c)
Calculate total environmental effects and energy used over all the sections (see
Figure G1.2c)
End loop
Calculate economic indicators (NPV, IRR, BCR, and FYB see Section 5.3.1 and
Figure G1.2c)
End Loop
Perform budget optimisation (for strategy and programme analysis)
Output results
END
LOOP
For each option
LOOP
For each section
LOOP
For each analysis year
CALCULATE
This year’s traffic
over the road section
STORE
Results for evaluation
and reporting phase
Yes
More
Years?
No
Yes
More
Sections?
No
Yes
More
Options?
No
See Figure G1.2c
Economic Analysis and
Comparisons
Optimisation
procedures
Output Results
MODEL
Annual effects and costs
CALCULATE
Road Deterioration
[RD Module]
CALCULATE
Road User Effects
(Speeds, VOC, time costs,
NMT, accident costs)
[RUE Module]
CALCULATE
Road Works Effects
[WE Module]
CALCULATE
Social and Environmental Effects
Social
(emissions
and Environmental
and energy balance)
Effects
(emissions andModule]
[SEE energy balance)
ADD
This year’s exogenous
benefits and costs
Return
LOOP
For each comparison
LOOP
For each analysis year
SET NPVsr = 0
Total net effects TNEsn (1, . . .,n) = 0
LOOP
For each section
CALCULATE
non-discounted Net Benefits
CALCULATE
Discounted Net Benefits at different
discount rates (r)
CALCULATE
Net effects (n)
Yes
More
Sections?
No
CALCULATE
Total net benefits and effects
Yes
More
Years?
No
CALCULATE
Total net effects
Yes
More
comparisons?
No
Return
The procedure for calculating annual road agency costs and road user effects for individual
section options is illustrated in Figure G1.2b and summarised by the following steps:
1 Calculate road deterioration - in the RD module (see Part C)
VOC, travel time costs, NMT time and operating costs, and accident costs - in the RUE
module (see Part E).
3 Calculate quantities and costs for road works - in the WE module (see Part D)
For example, emissions and energy use - in the SEE module (see Part F).
5 Add exogenous benefits and costs
Figure G1.2c illustrates the inner analysis loops for economic analysis and comparison of each
pair of road alternatives.
5 Economic analysis
∆C (m−n)i =
∑C
s
mis - ∑C
s
nis
...(5.1)
where:
∆RAC (m −n ) = ∑ ∆C
i
(m −n)i ...(5.2)
where:
These cost differences provide a relative measure of the increase in costs to the road
administration, of implementing investment option m over base option n.
The difference in the salvage values of works performed under investment options m and n is
a component of the net economic benefits to be included in the last year of the analysis period
(see Section 5.2.4), and is given as:
where:
Vehicle operating benefits due to normal and diverted traffic is calculated as follows:
∆VCN (m−n) =
∑ VCN - ∑ VCN
s
ns
s
ms
...(5.4)
VCNns = ∑ TN
k
nsk * UCnsk ...(5.5)
VCN ms = ∑ TN
k
msk * UC msk ...(5.6)
∆VCG (m−n) =
∑∑ {0.5 * [TG
s k
msk + TG nsk ] * [UC nsk − UC msk ]}
...(5.7)
The summations are over all the motorised vehicle types (k = 1, 2, ..., K) specified by the
user, and all road sections (s = 1, 2, ... ., S) being analysed.
The annual saving in vehicle operating costs is given by the expression:
where:
∆VCN(m-n) vehicle operating benefits due to normal and diverted traffic of investment
option m relative to base option n
VCNjs annual vehicle operating cost due to normal and diverted traffic over the
road section s with investment option j
TNjsk normal and diverted traffic, in number of vehicles per year in both
directions on road s, investment option j, for vehicle type k
UCjsk annual average operating cost per vehicle-trip over road section s, for
vehicle type k under investment option j (where j = n or m)
VCGjs annual vehicle operating cost due to generated traffic over road section s
with investment option j
Vehicle travel time benefits due to normal and diverted traffic are calculated as follows:
∆TCN (m−n) =
∑ TCN - ∑ TCN
s
ns
s
ms
...(5.9)
TCN ns = ∑ TN
k
nsk * UTnsk ...(5.10)
TCN ms = ∑ TN
k
msk * UTmsk ...(5.11)
Vehicle travel time benefits due to generated traffic are calculated as follows:
∆TCG (m−n) =
∑∑ {0.5 * [TG
s k
msk + TG nsk ] * [UTnsk − UTmsk ]}
...(5.12)
The annual savings in travel time costs are given by the expression:
where:
∆TCN(m-n) travel time benefits due to normal and diverted traffic of investment
option m relative to base option n
TCNjs annual vehicle travel time cost due to normal and diverted traffic over
road section s with investment option j
UTjsk annual average travel time cost per vehicle-trip over the road section s, for
vehicle type k, under investment option j (where j = n or m)
TCGjs annual vehicle travel time cost due to generated traffic over road section s
with investment option j
∆TCG(m-n) travel time benefits due to generated traffic of investment option m
relative to base option n on the given road section in the given year
∆TTC(m-n) savings in travel time costs due to total traffic of investment option m
relative to base option n
Non-Motorised Transport (NMT) time and operating benefits due to normal and diverted
traffic are calculated as follows:
∆TOCN(m−n) =
∑ TOCN - ∑ TOCN
s
ns
s
ms
...(5.14)
TOCNns = ∑ TN
k
nsk * UTOC nsk ...(5.15)
TOCNms = ∑ TN
k
msk * UTOC msk ...(5.16)
NMT time and operating benefits due to generated traffic are calculated as follows:
∆TOCG (m−n) =
∑∑ [0.5 * (TG
s k
msk + TG nsk ) * (UTOC nsk − UTOC msk )]
...(5.17)
The summations are over all the NMT types (k = 1, 2, ..., K) specified by the user, and all
road sections (s = 1, 2, ... ., S) being analysed.
The annual savings in NMT time and operating costs are given by the expression:
where:
∆TOCN(m-n) NMT time and operating benefits due to normal and diverted traffic of
investment option m relative to base option n
TOCNjs annual NMT time and operating costs due to normal and diverted
traffic over the road section s with investment option j
TNjsk NMT normal and diverted traffic, in number of vehicles per year in
both directions on road s investment option j, for vehicle type k
UTOCjsk annual average NMT time and operating cost per vehicle-trip over road
section s, for vehicle type k, under investment option j (where j = n or
m)
TOCGjs annual NMT time and operating costs due to generated traffic over
road section s with investment option j
TGjsk NMT generated traffic, in number of vehicles per year in both
directions on road s, for vehicle type k, due to investment option j
∆TOCG(m-n) NMT time and operating benefits due to generated traffic of investment
option m relative to base option n
∆NMTOC(m-n) annual savings in NMT time and operating costs due to total traffic of
investment option m relative to base option n
The benefits from reduction in total accident costs are given by the expression:
where:
The annual savings in road user costs are given by the expression:
∆RUC (m −n ) = [∆VOC (m-n) + ∆TTC (m-n) + ∆NMTOC (m-n) + ∆ACC (m-n) ] ...(5.20)
where:
where:
∆NEXBy(m-n) the annual net exogenous benefits of investment option m relative to base
option n, in year y
EXBjy exogenous benefits for investment option j, in year y, (where j = n or m)
where:
In the last year of the analysis period, the net economic benefits of implementing option m
relative to option n is calculated as:
...(5.23)
where:
NBY(m-n) net economic benefit of investment option m relative to base option n in the
last year of the analysis period Y, and the parameters on the right-hand side
are as defined earlier, but with subscript Y added to indicate the last year of
the analysis period
∑ [1+ 0.01 * r]
NB y(m-n)
NPV(m −n) = (y -1)
...(5.24)
y =1
where:
The higher the NPV, the greater the benefits from investment option m relative to base option
n. If there are no budget constraints, then the choice between the two alternative investments
should be based on NPV. Larger investments will tend to have larger NPVs.
This equation is solved for r° by evaluating the NPV at 5 percent intervals of discount rates
between -95 and +900 percent, and determining the zero(es) of the equation by linear
interpolation of adjacent discount rates with NPV of opposite signs. Depending on the nature
of the net benefit stream, NBy(m-n), it is possible to find one solution, multiple solutions, or
none at all.
The IRR gives no indication of the size of the costs or benefits of an investment; it acts as a
guide to the profitability of the investment - the higher the better. If the computed IRR is
larger than the planning discount rate, then the investment is economically justified.
NPV(m-n)
BCR (m-n) = +1
Cm
...(5.26)
where:
NPV(m-n) discounted total net benefit of investment option m relative to base option n.
This is the Net Present Value at discount rate r
Cm discounted total agency costs of implementing investment option m
If the NPV(m-n) is zero, then (NPV/C)(m-n) is zero. These ratios give an indication of the
profitability of investment option m relative to base option n at a given discount rate. These
measures eliminate the bias of NPV towards larger project options but, like the IRR, they give
no indication of the size of the costs or benefits involved.
100 * NB y °(m-n)
FYB (m-n) =
∆TCC (m−n)
...(5.27)
where:
FYB gives a rough guide to project timing: if it is greater than the discount rate, then the
project should go ahead; otherwise it should be delayed until it satisfies the criterion.
6 Optimisation
The two methods for budget optimisation provided for road works programming and network
strategic analysis are:
1 Total enumeration
where:
∑∑ R
s =1 m =1
smqt X sm ≤ TR qt , q = 1,...., Q; t = 1,...., T ...(6.2)
where:
Ms
∑m =1
X sm ≤ 1, s = 1,...., S ...(6.3)
that is, for each road section s, no more than one alternative can be implemented.
If M is the average number of alternatives for the roads, the problem then has SM (= S x M)
zero-one variables, QT (= Q x T) resource constraints and S interdependency constraints. The
parameters that define the problem size are S, M and QT. Depending on the solution method
used, different problem-size parameters determine whether the method is suitable for the
problem in terms of the computational effort needed.
The total enumeration method provides the user with an unconditionally optimal solution. It
computes the total net present values of all feasible programme selections, and chooses the
one with the highest value. The computational effort required for this may be considerable, so
the method is only feasible when the number of alternatives per investment unit is relatively
small.
NPV - NPV
j i
E = ...(6.4)
cost - cost
ji
j i
where:
In Equation 6.4 above, the incremental NPV/cost can be replaced by the incremental
∆IRI*Length/cost where ∆IRI*Length is the weighted average change in roughness obtained
by comparing the project alternatives using IRI instead of NPV.
The objective of the incremental method is to select road sections successively starting with
the largest NPV/cost ratio (Eji), since this maximises the NPV (net present value) for any
given budget constraint. Where there is more than one investment option on any individual
road section, that with the lowest discounted investment costs is designated the base case
alternative. This method considers all possible options, and compares these incrementally
starting against the base case, by using the incremental algorithm to select the combination
that maximises the selected objective function.
An incremental search technique is used to select the options with successively lower
incremental NPV/cost ratios, ensuring that at any time there is no more than one option per
road section. The process continues until the budget is exhausted for each budget period. The
method is often referred to as the efficiency frontier, which is a line that joins investments
with the highest NPV along the cost axis in a plot of NPV against investment cost (Harral and
Faiz, 1979). In essence, the method seeks out those options that are close to the boundary of
the efficiency frontier. The algorithm is illustrated in Figure G1.3, and is defined in the
following steps:
1. Determine the pre-defined investment options for pre-selected sections and deduct the
financial costs of these options from the available budget in corresponding years. Exclude
these sections from any further optimisation.
2. Determine possible investment options for the remaining sections. If the life cycle
analysis option is being used, set the user-defined base alternatives as the do minimum
for each road section. For the multi-year forward programme, the do minimum option is
that with the delayed capital works.
3. If the total financial cost of the do minimum investment alternatives on each section is
greater than the available budget for any period, then the investment options or budget
constraints must be redefined.
4. Deduct the financial cost of the do minimum investments from the available budget to
determine the remaining budget for each period. Set the do minimum as the first Base
option for each section.
5. Calculate the incremental NPV/Cost ratio for all remaining section-options compared
against the Base option, and all other option pairs with higher economic cost. For
example, consider the following investment options for a particular section arranged in the
ascending order of discounted total economic costs:
options: A, B, C, D, E
The incremental NPV/Cost ratios for these are given by:
Eba Eca Eda Eea ; Ecb Edb Eeb ; Edc Eec ; Eed
6 Delete incremental NPV/cost ratios that are less than the user specified minimum
incremental value (MIV).
7 List the remaining incremental NPV/cost ratios in decreasing order (with the associated
section-option pair codes) and, within each incremental NPV/cost, in the order of
decreasing economic cost. For example, if Eeb = Edb then Eeb is ranked higher.
8 Select the next incremental NPV/cost ratio from the top of the list. If the lower cost
section-option is not the current Base Option for that section, continue searching until one
is found.
9 If the remaining budget is insufficient in any of the periods for the financial costs of
works required for the section-option selected in Step 8 above, then the selected option
should be rejected, and continue searching by repeating Step 8.
10 If the section-option can fit within the remaining budgets for all periods, deduct the net
increase in financial cost of capital works from all corresponding budget periods. Set the
Base option for this section to be that corresponding to the lower cost option for the
incremental NPV/Cost ratio chosen in Step 8. Providing that the remaining list is not
empty, return to Step 8.
The process described above continues until the budget is exhausted or there are no more
section-options remaining in the list. The resulting list of selected section-alternatives
constitutes the optimal work programme.
NPV
E
D
B
C A, B, C, D, E : Section-Alternatives
A
ECONOMIC COST
(relative to Base Option)
Figure G1.3 Efficiency frontier concept
7 References
Harral, C.G. and Faiz, A. (1979)
The highway design and maintenance standards model (HDM): model structure,
empirical foundations and applications. PTRC Summer Annual Meeting, University of
Warwick, 13-16 July 1979. PTRC Education and Research Services, London, UK
PIARC, (1991)
Methods for Selecting Road Investment, Economic and Finance Committee of PIARC,
Paris, France
TRRL Overseas Unit, (1988)
A Guide to Road Project Appraisal. Transport and Road Research Laboratory Overseas
Road Note 5, Crowthorne UK