3G Node B

This document provides 13 steps over 21 minutes to commission a Node-B (6601-E) for a 3G project in Guwahati. The steps include connecting cables and software, formatting drives, transferring software files, configuring the equipment and licensing using the RBS Element Manager. Successful completion is confirmed when 3G calls can be made and the site is defined in the MSS.

Uploaded by

ARUP PAL
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
185 views44 pages

3G Node B

This document provides 13 steps over 21 minutes to commission a Node-B (6601-E) for a 3G project in Guwahati. The steps include connecting cables and software, formatting drives, transferring software files, configuring the equipment and licensing using the RBS Element Manager. Successful completion is confirmed when 3G calls can be made and the site is defined in the MSS.

Uploaded by

ARUP PAL
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 44

13 Steps & 21mins to

Commission Node-B (6601-E)


3G Project – (Guwahati)
6601 Node-B
Software & Cables Required
CABLES:
- Emely Cable (dig. on left)
- LAN Cable
SOFTWARE:
- Total Commander
- File Zilla
- RBS Element Manager
- Basic CV
(CXP9014349%2_R2D01) (File Size –
203MB)
Step-1
• Connect all 4nos E1 in C,D ports of
Junction Box.
• Connect Emely cable to Test Port in CBU
• Connect LAN cable to Ethernet (E) Port in
Junction Box.
• Set Laptop IP:
(IP-169.254.1.2, SUBNET-255.255.255.0, GATEWAY-169.254.1.1)
Step-2
• Connect to HyperTerminal (select COM1 or appropriate
COM port, Restore defaults) and then type subsequent
commands:
- $ reload --
- $ formathd /d
- $ formathd /c2
- Then check if all C2 & D drives have become 0%
- $ vols (/d=0%, /c2=0%)
- $ reload
- $ ifconfig le0 169.254.1.1 netmask 255.255.255.0
Step-3
Then open Total Commander (FTP)
- Select NET – FTP connect, new connection,
session=rbs, hostname=169.254.1.1, username=rbs
- Select the folder containing the Basic CV in laptop and
then press ctrl and drag both c2 and D folder to the
remote client.
// Total time for file transfer takes 300 – 330secs //
- After successful file transfer check in hyper terminal by
command
$ vols (values will be /d=18%, /c2=23%)
Step-4
• $ reload
// Wait till login server ready message appear in
hyperterminal - It takes 90 sec //
Then press enter
Username=rbs
Password=rbs
$ setclock 2011-06-29 16:54:00 //set the current date//
Step-5
• Connect RBS EM – set IP=169.254.1.1
• Select TOOL – Cabinet Equipment Configuration
Go on typing: NEXT – NEXT – NEXT (here select sector
1,2,3) – NEXT (here select ETM position, slot pos=2,
ETM Type=ETMFX11) – NEXT – NEXT – FINISH – YES
// It takes 60 sec for Login Server ready mesg to appear in
hyperterminal then again login to RBS EM //
Step-6
• Connect RBS EM – set IP=169.254.1.1
• Select TOOL – O & M Access Configuration
• Type – NEXT
Click Tick mark on Use Configuration file – browse and select O&M
script.
Type- NEXT-NEXT-NEXT-NEXT-NEXT (here set time)
Time=17:04:23//current time//, Day=29, Month=06, Year=2011, Local Time Zone= IST
. Then Type- NEXT-FINISH-OK
//Here after 10-15secs the lan will get disconnected and we need to
change the laptop IP as per O&M IP, then again it will get
reconnected and Configuration Complete message will appear//
// Also after this step the ETMFX card operation light will become
constant //
Step-7
• Connect RBS EM – set IP=10.142.230.1 //O&M ip//
• Select TOOL – Site Equipment Configuration
Type – NEXT
Click Tick mark on Use Configuration file – browse and
select external.hw.xml script.
Type-OK-NEXT-NEXT
Click Tick mark – configure external alarm control unit
Type-NEXT-NEXT-till page-13 NEXT-FINISH-OK
Step-8
Now we need to create CV so that if
required we can reload from this step.
• Click Software in RBS EM – select CV
• Name=CV_SiteEquip
• Rollback list=Add to List
• Click on Apply
• OK
Step-9
• RBS EM - Select TOOL – Run Command File
Click on: Halt on errors – verbose logging
Browse & select – Iub_EN script and EXECUTE
//Configuration Succeeded mesg will appear at last//
Step-10
Now we need to create CV so that if
required we can reload from this step.
• Click Software in RBS EM – select CV
• Name=CV_IUB
• Rollback list=1
• Click on Apply
• OK
Step-11
Now we will install License in the Node-B:
>Open File Zilla software – Host=10.142.230.1,
username=rbs,passwd=rbs, port=21, quickconnect
>Select the folder containing license in Local site and then
drag the license to c: drive- license in Remote site.
> Now open RBS EM-Licensing-MO properties-Actions-
updatelicensekeyfile –
userid=rbs,passwd=rbs,ipaddress=10.142.230.1,sfile=/c/
license/x912.xml, EXECUTE.
> Then check in features- as per license required details
will be appearing ENABLED & ACTIVATED //if any
featurestate is DEACTIVATED , then right click and select MO properties
and activate it//
Step-12
Now we need to create final CV so that if
required we can reload from this step.
• Click Software in RBS EM – select CV
• Name=CV_License
• Rollback list=1
• Click on Apply
• Set Startable
• OK
SITE READY, MAKE 3G CALL
• Check for alarms in alarm list
• Check if site has been properly defined in
MSS by mgaap:area=all; //to define=
MGAAI:AREA=<CELL_NAME>,SAI=<MCC-MNC-LAC-
SAC>;//
• Check Video call, Packet call.
Cards LED status on Normal Operation
THANK YOU
Amitabh Panda

(NESA CIRCLE)