SI Works PDF
SI Works PDF
Disediakan Oleh:
Unit Geoteknik
Cawangan Pakar & Kejuruteraan Awam
Ibu Pejabat JKR Malaysia
Tkt 10, Menara Tun Ismail Mohamaed Ali
No. 25, Jalan Raja Laut,
50350 Kuala Lumpur
0
CONTENTS
1.0 INTRODUCTION
2.0 THE IMPORTANCE OF SI
3.0 WORKS PROCEDURE FOR SITE INVESTIGATION
4.0 PLANNING OF SITE INVESTIGATION WORK
4.1 SURFACE INVESTIGATION INCLUDES PARTS
4.2 PLANNING SCOPE OF S.I
4.3 GUIDELINES OF PLANNING SITE INVESTIGATION FOR ROAD
PROJECTS
4.4 GUIDELINES FOR PLANNING SITE INVESTIGATION FOR BUILDING
PROJECTS
4.4.1 PLANNING S.I FOR BUILDING PROJECT
4.4.2 SPACING OF BOREHOLE
4.4.3 DEPTHS OF BOREHOLE
4.4.4 INSITU TESTING AND SAMPLING PRACTICE
4.4.5 WATER TABLES (WT) SHOULD BE TAKEN
4.4.6 DISTUBED SAMPLES
4.5 FACTOR INFLUENCING SELECTIONS OF S.I METHODS
4.5.1 GEOLOGICAL NATURE OF THE SITE
4.5.2 TOPOGRAPHICAL NATURE OF THE SITE
4.5.3 TYPE OF INFORMATION REQUIRED
4.5.4 FINANCIAL CONSTRAINTS & TIME RESTRICTION
1
GUIDELINES FOR SITE INVESTIGATION WORKS
1.0 INTRODUCTION
A process of the site exploration consisting of site inspection, boring, sampling and
testing to obtain necessary properties for ground characterization, geotechnical
evaluation and design.
To determine within practical limits, the depth, thickness, extend and compositions
of each soil stratum; the depth, type and condition of rock; the depth and composition
of ground water; the strength, compressibility and hydraulic characteristic of soil
strata as required by geotechnical designers.
Site Investigation generally ranges from 0.1% to 5.0% of the construction cost
depending on the extent and scope of SI required for the project, which in place
depend very much on the possible geotechnical problems identified, the character and
variability of the subsoil properties, the type and nature of project, the experience of
the designer and the existing information available.
2
c) To determine the possible difficulties and problems that may be encountered
by a specific construction method.
2.2 Without SI or inadequate SI, geotechnical design is incomplete and it has been
identified as a main factor accounting for many geotechnical failures, significant
delay and increase in construction cost when the design has to be revised or amended
3
f) Carry out laboratory testing after the study of the bore logs.
b) Site Plan – showing the layout of the proposed structures, utility pipes and
cables, nearby structures/buildings/rivers, other potential hazardous
conditions if any, should also be indicated
4
ground and environmental conditions, either naturally or as a result of the
works, and the effect of such changes on the works, on adjacent works and on
the environment in general.. Usually soil engineer is required to inspect the
site to appreciate actual site and ground problems with particular reference to
terrain, vegetation, swamps, water runoff, stratigraphical formation where
they are exposed.
c) Determine the number and spacing of boreholes or other field tests. (location
and procedure of test, criteria to terminate a borehole should be clearly
specified)
5
f) Prepare list of special precautions for the site investigation supervisor, if any.
4.3 Guidelines for Planning Scope of Works for Road Projects (Refer Appendix C)
4.4.1 For building projects, JKR probes are usually carried out first. The results are
sufficient for shallow foundation design if all the following conditions are complied:-
b) Good bearing layer is above water table and available at about 2m below the
ground and the subsequent strata has better bearing capacity up to at least 3m
below the proposed founding level or 1.5 times the width of footing
whichever is larger.
e) Building is a low rise building (column load less than 1000 KN/column)
Otherwise further SI has to be carried out. This includes one or two or more of the
following methods of soil investigation:-
i. Hand Augering to determine the water table; type and consistency of soil
ii. Motorised Hand Boring
iii. Deep Boring (for any soil where piling is anticipated)
6
iv. Deep Sounding (mainly for alluvial soils where piling is anticipated; also
used to supplement DB results)
v. Plate bearing or pressuremeter tests (for shallow foundation using high
bearing capacity, say 100KN/m2 or more or in fractured rock or soft rock)
vi. Test pit and bulk sampling (shallow foundation or deep excavation)
7
The depth of borehole should extend through any unsuitable or weak soil to a
sufficient depth of soil stratum which is firm or strong and unlikely to undergo
settlements due to the load of the building.
During boring,
At completion of borehole, and
A min of 24hr after completion of borehole
More accurate WT is crucial for deep excavation and stability analysis and can only
be obtained by installation of piezometer and long term monitoring.
Mostly obtained from the split barrel sampler used in SPT, are used for
identification and classification tests.
Some approximate strength and compressibility properties can be
obtained from classification test results based on some correlations.
b) Undisturbed Samples
8
Structural disturbance is kept to minimum and mainly used for
consolidation and strength test
Common undisturbed soil samplers are piston sampler, thin wall samplers,
hydraulic sampler and Mazier samplers
In planning process of site investigation, the following factors that may influence the
selection of site investigation methods have to be considered:-
For alluvial fluvial deposit formation, Deep Sounding is generally suitable; but
need to determined the soil type and ground water table (by Hand Augering or
Deep Boring (DB)/Motorised hand boring(MHB))
For residual soils, DB or MHB are more suitable; but only DB can do rock coring
(not MHB).
Trial pits are only practicable in firm or compact soils or in soft rock, above
water table.
For limestone areas, boulder abundant areas and uncontrolled filled ground, DB
have to be used.
SPT is appropriate for all soils except soft or very soft clay where vane shear test
is more appropriate.
Sampling for undisturbed samples by thin-walled sampler or piston sampler is
only appropriate for cohesive soil with SPT value of about 10 or less.
Disturbances in sampling for soils with SPT value exceeding 15 are unacceptable
unless special measures are taken or Denison or Mazier samplers are used.
Terrain and access condition are important considerations from the point of view
of moving site investigation equipment about.
9
In hilly or steep inclined sites, headings driven (horizontal or inclined drilling)
may be more convenient than vertical boring machine or alternatively use small
portable boring machine.
In waterlogged or swampy areas, some preliminary work to prepare working
platforms or staging are necessary
a) More extensive site investigation means more cost and more time.
b) Deep Sounding (DS) is usually cheaper and faster when compared to Deep
Boring (DB); but when in swampy areas with very soft ground, DS can be as
expensive as DB due to difficulty in getting anchorage load
10
c) Cost of SI is usually within the range of 0.1% to 5% of the construction cost;
therefore to reduce the scope of SI for financial reasons alone is seldom
justified
11
APPLICABILITY OF COMMON FIELD OR INSITU TESTS
Legends:-
11
Appendix C
1.0 General
The extent of the SI mainly depends on the character and variability of the
subsoil and ground water, and the amount of existing information available.
However it should be noted that subsoil conditions of a road alignment are
very sensitive to geological conditions, and so the spacing and location of
boreholes/test pits/types of tests should be more closely related to the detailed
geology of the project area and geotechnical problem/analysis required to be
carried out.
For filling area where embankment is high (> 6m) or the ground is swampy
and consists of compressible soils, adequate number of boreholes and other
12
relevant field test should be carried out to determine the subsoil condition with
particular reference to:-
c) Regime of ground water (and seepage) and its variation (by HA/DB
and piezometers).
13
should only be terminated after reaching very stiff/dense strata (two
consecutive SPT values exceeding 20) for soft ground areas such as in
coastal alluvial soils. In residual soil areas, at least one borehole should
be extended until very hard/very dense strata (SPT value exceeds 50).
f) For low embankment in residual soil areas, one or two hand augering
plus a few JKR probes are sufficient for design.
14
the presence of defective or unstable geological structural
discontinuities and its strength properties. Seismic survey may have to
be carried out for major road projects passing through mountainous
areas involving massive and deep excavation. This is to ensure that
more geological information are made available for slope stability
assessment and also the quantity of rock excavation can be estimated
with reasonable accuracy. Foam drilling and Mazier sampling are only
required for high quality undisturbed samples in determining the shear
strength of the residual soils.
e) At least one test pit (2m deep or more) should be carried out at each
major cut area which form major sources for filling. Bulk sampling for
classification test, CBR, dispersion and compaction test should be
carefully planned for study on suitability and availability of filling
materials.
For major structures like bridges, major culverts and retaining walls, at least
two Deep Boring should be carried out at each site or minimum one borehole
per pier or abutment or maximum spacing of borehole should be 60 m.
15
Additional boreholes should be allowed for bridge approach embankments
especially on soft ground or high embankment areas. Other basic requirements
are as follows:-
a) Bore Depth
b) Field Test
SPT shall be carried out at 1.5 m interval unless otherwise stated by the
designer. In case of soft ground, vane shear test shall be carried out
instead of SPT and interval of testing should be 1 m interval.
16
e) All soil classification test (natural moisture content. Atterberg limits, &
sieve analysis etc.) shall be carried out for all typical disturbed sample
at various distinct strata.
17