Department of Education: Guadalupe Heights Integrated School

The document outlines a program of work for the construction of pathways at Guadalupe Heights Integrated School in Tacloban City, Philippines. The program will construct 15 meters of pathway to the principal's office, 10 meters from Grade 6 to Kindergarten, and 15 meters from Grade 5 to the exit gate. An additional 30 meters of pathway will be built beside other classrooms. The construction will use cement, sand, lumber and labor over 5 days with a budget of 10,500 Philippine pesos, beginning on June 4, 2019.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
257 views2 pages

Department of Education: Guadalupe Heights Integrated School

The document outlines a program of work for the construction of pathways at Guadalupe Heights Integrated School in Tacloban City, Philippines. The program will construct 15 meters of pathway to the principal's office, 10 meters from Grade 6 to Kindergarten, and 15 meters from Grade 5 to the exit gate. An additional 30 meters of pathway will be built beside other classrooms. The construction will use cement, sand, lumber and labor over 5 days with a budget of 10,500 Philippine pesos, beginning on June 4, 2019.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Republic of the Philippines

Department of Education
Region VIII
Division of Tacloban City
GUADALUPE HEIGHTS INTEGRATED SCHOOL
Brgy. 105 San Isidro (Suhi), Tacloban City 6500
ID #500982

PROGRAM OF WORK

I. Program Title: Construction of Pathways


1.1. Entrance to the principal’s office 15 meters.
1.2. From Grade 6 Sangyaw to Kindergarten 10 meters.
1.3. From Grade 5 Mabini side to the Exit gate 15 meters.
1.4. Beside Grade 1, Grade 7, Grade 6 30 meters.

II. Types of construction: Connecting pathways

III. Allocation (Budget): Php. 10, 500.00

IV. Construction Start: June 04, 2019

V. Completion: 5 days

VI. Finance / Sponsored by: Brigada Eskwela Fund 2019

VII. Bill of materials:

PARTICULARS OR # UNIT COST AMOUNT


(Php) (Php)

4 cubic course sand 0409 750.00 per cubic 3, 000.00


10 sacks of cement 0409 250.00 per sack 2, 500.00
Water - - -
2 x 3 x 12 coco lumber - Used construction -
material
TOTAL EXPENSES 5, 500.00

VIII. Labor / Manpower needed:

1. 1 skilled mason (500/day), 2 laborers (250/person/day)

IX. Mode of construction / Detailed:

1. Layout of desired area.


2. Preparation of materials for pathway construction.
3. Mixing cement and coarse sand with water.
4. Clearing the area ready for cementing.
5. Cementing pathways.
6. Ten to fifteen days (10-15) seasoning period.
X. Working plan sketch:
School Exit Gate

Pathway

Pathway
Principal’s
Office Pathway

SCHOOL GATE

Prepared by:

LEONARDO E. FERNANDEZ
Brigada Eskwela Coordinator

ELEANOR R. SABIT NEMFA ENGRACIAL WENA B. CEMANES


Program / Innovation Committee Technical Working Committee Infrastructure Committee

Approved by:

LARRY. P. PEÑALOSA, Dev. Ed. D.


School Brigada Eskwela Chairman