(ii) More than 1.0 Acre to 2.0 Acres; (ii) Minimum 20 Kilo Watt peak (KWp)
(iii) More than 2.0 Acres to 5.0 Acres; (iii) Minimum 30 Kilo Watt peak (KWp)
(iv) More than 5.0 Acres. (iv) Minimum 40 Kilo Watt peak (KWp)
All water lifting stations of Irrigation Department Minimum 50 Kilo Watt peak (KWp)
6 having connected load of 100 Kilo Watt (KW) and Or
above 3% of connected load, whichever is higher
Page 1 of 3
(i) This order supersede the order notified vide No. 22/52/2005-5 Power dated 3rd
September, 2014.
(ii) The Departments of Town and Country Planning, HUDA, Urban Local Bodies,
Haryana State Industrial and Infrastructure Development Corporation (HSIIDC),
Industries and Commerce shall incorporate a relevant provision in this regard in
their rules, within three months from the date of issue of notification, to make use
of Solar Photovoltaic Power Plants mandatory. They shall also define the penal
action, procedure, mentioning the amount of penalty, for not complying with the
provisions of this notification as per their departmental rules.
(iii) Departments of Public Works (Buildings and Roads), Haryana State Roads &
Bridges Development Corporation, Public Health, Education (all departments and
Mission mode projects), Health(all departments and Mission mode projects), Social
Justice and Empowerment, Red Cross Societies, Architecture, Housing Board,
Haryana State Agricultural Marketing Board (HSAMB), Irrigation, Forest, Police
Housing Corporation, Tourism, State Universities or any other government building
constructed shall implement the mandatory provisions of installation of Solar
Photovoltaic Power Generation Plant for the buildings constructed by them.
(iv) The Renewable Energy Department being a State Designated Agency for
implementing Energy Conservation Act in the State shall provide all necessary
technical support to the Government Departments/Organizations in preparation of
project proposal, cost estimates, installation of Solar Power Plants and in obtaining
the Central Financial Assistance(CFA) from Ministry of New and Renewable
Energy (MNRE), Government of India (GOI), if available, from the Ministry of
New and Renewable Energy, Government of India, from time to time.
(v) The concerned departments shall designate a District and State level Nodal Officer
to monitor and to report the progress of enforcement of the said decision of the
State Government, to the Renewable Energy Department, Haryana, on quarterly
basis in the formats to be issued by Renewable Energy Department through the
office of respective Additional Deputy Commissioner-cum-Chief Project Officer.
Based on these reports the Renewable Energy Department will do quality/technical
checks. If found not satisfactory then concerned department will take appropriate
penal action as mentioned above.
(vi) The above said organizations/user categories shall ensure the compliance of above
mentioned mandatory provisions, within six months from the date of issue of
concerned department’s new guidelines/notification (as per clause (iii) above), at
their own cost, failing which, the penal action may be initiated by the respective
departments.
Page 2 of 3
of 2001)).” However, if the Power Utilities Department fails to comply with the
directions of the government, then the responsibility shall also be fixed for non-
compliance of the directions.)
(vii) The systems installed shall strictly comply with the technical specifications
prescribed by Ministry of New and Renewable Energy, Government of India/
Renewable Energy Department, Haryana/ Haryana Renewable Energy
Development Agency (HAREDA). The technical specifications may be
downloaded from the website of the Renewable Energy Department
www.hareda.gov.in.
(viii) The user categories of private sector may install the Solar Photovoltaic Power
Plants either from the Channel Partners/New Entrepreneurs/ firms empanelled by
Ministry of New and Renewable Energy or from the firms empanelled by
Renewable Energy Department, Haryana/ Haryana Renewable Energy
Development Agency (HAREDA) and for government departments/organizations,
Renewable Energy Department, Haryana is the approved source, being State
Designated Agency. The list of Channel Partners/New Entrepreneurs/ firms
empanelled by MNRE/HAREDA may be downloaded the website of the
Renewable Energy Department www.hareda.gov.in.
Note: if any of the category mentioned in the mandate above have more than one
complex/unit, then to fulfill their obligation under this notification, they may install
the system in one or more complex, within the State, combining the total
requirement as per notification.
Ankur Gupta
Principal Secretary to Government Haryana,
Renewable Energy Department.
Page 3 of 3