03 Embankment Construction
03 Embankment Construction
EMBANKMENT CONSTRUCTION
1. Scope
This item of work deals with construction of road embankment with approved
materials as per the terms of contract agreement and shall be dealt with in complete
compliance to the technical specifications; placement and compaction shall be carried
out in accordance with clause 305 of specifications.
Drawings used for construction in respect of the alignment, level, cross sections
in respective stretches and other survey detail and relevant technical specifications
viz.clause 305 of technical specification in terms of mandatory guidelines for ensuring
the quality of work.
Prior to the commencement of this work, the materials proposed to be used for
such embankment shall be sourced suitably. Different sources shall be earmarked for
different stretches giving due regard to the load of haulage and most importantly the
suitability and quantum of material availability.
2. Procedure
1. The toe line and centre line are marked and pegs will be driven.
2. The material shall be dumped in site at respective location.
3. The material shall be spread in layers of uniform thickness not exceeding 250 mm
compacted thicknesses over the entire width of the embankment by mechanical
means and will be graded with grader to the required camber.
4. Moisture content of the material shall be checked and extra required will be
added.
5. The moisture content of each layer shall be checked and it should be with in the
range of OMC +1% to OMC -2 percent. If moisture content is found out of these
limits the same will be brought within limits by addition of water or by aeration
as the case may be.
6. The compaction shall be done with the help of vibratory roller of 8 to 10 ton
static weight. Each layer shall be thoroughly compacted to the densities specified
in the specifications which are mentioned at the end of this document for
reference. The rolling pattern will be finalized in trial stretch.
51
7. On compaction of the particular stretch necessary field testing shall be carried
out Field density shall be done in the manner and frequency as specified below.
8. If the required field density is not achieved, compaction shall be continued till
required density is achieved.
9. Loose pockets if any will be removed and replaced with approved material.
10. The above stages shall be repeated till the top level of the embankment is
reached to the specified levels and grades. The top levels shall be checked and
shall be within +20mm and -25mm of designed level.
11. All relevant QA and QC documents will be maintained for all stages of
Embankment Construction.
3. Equipment/Machinery:
Grader 1 No as a minimum.
Tippers 10 Nos as a minimum
Water Sprinkler 1 No as a minimum
Roller 80 to 100KN 1 No as a minimum
4. Material Specifications
Maximum Particle Shall not be more than 75mm or should not be more
size than 2/3rds of compacted layer thickness which ever is
minimum.
7. Traffic
As per the standard construction practices necessary traffic management measures shall
be provided viz. signs, marking flags, lights and flagmen. Fixed signs, barriers and other
traffic control devices shall be maintained in a satisfactory condition till such time they
are required. Throughout the construction period site management shall maintain
public vehicular access along the existing right of way.