Akosombo and Kpong Dam Reop Project Summary Dec2014
Akosombo and Kpong Dam Reop Project Summary Dec2014
Akosombo and Kpong Dam Reop Project Summary Dec2014
STUDY OF
established to examine options for reoperating Akosombo and Kpong hydropower dams and the
electrical grid they supply to enable a more natural flow pattern to be re-established into the
Lower Volta River. This will restore the human food production systems and livelihoods and the
AKOSOMBO AND KPONG DAMS
ecological functions that depend upon natural flow variability, and it may also be possible to
accomplish these improvements while increasing the reliability of and access to water and power
and reducing flood risks. The ultimate output from the project is a technically and economically
feasible reoperation plan. The project will also contribute to a global process of shared learning
on the techniques and benefits of dam reoperation.
!"#$%"&'()'*+%,-./'012'
PROJECT PARTNERS
GHANA EXTERNAL
University Of Ghana
• Institute For Environmental And
Sanitation Studies
• Center For African Wetlands
Traditional Chiefs
The geographic focus is the Lower Volta River from Lake Volta to the mouth of the river near
Ada. This reach of the river is of interest to the project because Akosombo and Kpong dams,
built in 1965 and 1982, respectively, have distorted the natural river flows by storing and
releasing water to meet electricity demand patterns rather than in rhythm with the seasonal
patterns of rainfall and runoff in the catchment area. The Akosombo dam formed Lake Volta,
one of the largest water storage reservoirs in the world. Twenty-five kilometers downstream, the
Kpong dam operates as a run-of-the-river facility with minimal storage to re-turbine the
Akosombo releases. Akosombo and Kpong dams were designed to generate an average of 6,100
GWh/year, which is 95% of Ghana’s electricity consumption. In addition to power generation,
Akosombo provides some degree of flood protection due to its very large storage capacity
relative to inflow, and Kpong supplies a small amount of irrigation (only about 100 ha) for rice
cultivation. Navigation and a robust lake fishery are important additional benefits of the
reservoir.
Like storage reservoirs in general, the function of Akosombo is to store water during seasons and
years of high inflow for power generation during seasons and years of lower inflow. In Ghana,
the demand pattern causes Akosombo to be operated to generate a relatively constant output of
power daily and seasonally. Thus, Akosombo distorts the natural river flows by storing and
releasing water in rhythm with the patterns of electricity demand in the service area rather than
the seasonal patterns of rainfall and runoff in the catchment area. The effect on the downstream
flow pattern is to reduce the peak flows and increase the base flows, effectively eliminating the
dynamic interactions between the river and its floodplains, wetlands, deltas, estuaries, mangrove
and beach environments. These are the great engines of riverine and marine biodiversity and the
environmental services that they provide for the myriad of human livelihoods that are dependent
upon a fully-functioning river system.
By eliminating the annual floods in the Lower Volta River floodplain and estuary, the Akosombo
and Kpong dams have devastated the historic livelihoods of the downstream communities and
the physical and ecosystem processes on which they depend. The results have been a drastic
reduction in sediment flushing and an explosion in the growth of exotic weeds that have choked
off the once lucrative shell fishery, increased the snail vectors for the debilitating bilharzias, and
fostered the formation of a permanent sandbar at the estuary. As sediments accumulate in the
channel, they are no longer replenishing the beaches in Ghana, Togo and Benin, resulting in
massive beach erosion, loss of mangrove habitats and reductions in the productivity of the
Guinea Current and its pelagic fishery. The loss of the annual flood pulse has also reduced
floodplain agriculture as natural flooding no longer leaves rich alluvial deposits that improve soil
fertility in the overlying upland areas.
The overall effect of the loss of agriculture, clam picking, and fishing activities has created
intense poverty and led to a dramatic shift in income generating activities. Some 80,000 people
are directly adversely affected by the change in livelihood. The Volta Basin Research Project
The goal of the Ghana Dam Reoptimisation and Reoperation Project is to contribute to economic
growth and poverty reduction through restoration of downstream ecosystems, food systems and
livelihoods by reoperating the Akosombo and Kpong dams. It will specifically examine
techniques for optimizing major hydropower dams and the electrical grids into which they feed
to enable a more natural flow pattern to be re-established into the Lower Volta River. This
project will improve the reliability of and access to water, food and energy, thereby improving
livelihoods on a local, regional and transboundary level. The beneficiaries of this dam
reoperation project will include: riparian communities downstream of the dam whose food
production, livelihoods, and access to groundwater will be markedly improved, and whose flood
risks will be reduced; residents of Togo and Benin who will benefit from the arrested erosion of
their beaches and mangrove ecosystems, and from the improved production of the ocean
fisheries that depend upon recruitment in the Volta estuary; and consumers of power from
Akosombo and Kpong dams whose reliability will be improved by the hydropower and grid
reoperations.
Project history:
The project is one of a suite of regional investigations to demonstrate the technical and economic
feasibility of re-optimizing the world’s major irrigation, hydropower and flood management
systems to enable their storage dams to be reoperated to restore their formerly productive
floodplains, wetlands, deltas and estuaries in ways that maintain - and can often even enhance -
the existing water supply, power generation and flood control benefits.
• The project application was submitted to the African Water Facility (AWF) for
funding consideration in August 2008.
• The proposal was considered eligible for support under the AWF Operational
Procedures in 2009. The AWF deployed a multi-disciplinary team to carry out a field
appraisal mission to Ghana from 29th September to 6thOctober, 2009 including a field
visits to Akosombo hydropower station and the Lower Volta estuary at Ada. The
mission furthermore met and discussed with partners, such as officials of the Volta
River Authority, academic and research institutes, traditional authorities, community
representatives and other stakeholders.
• The project was approved for funding in July 2010. The first funding disbursement
was made in January 2011.
• A series of meetings were held from March 7-11, 2013 in Accra and around the
project site. In addition to re-confirming support for the project from key Ghanaian
Ministries; NHI and WRC introduced the project to GRIDCo (power transmission
company of Ghana); and began discussions with VRA and the model developers on
data gathering and populating the WEAP model for the Lower Volta Basin.
• Project Steering Committee meeting held in Accra on May 7, 2013. VRA (Charles
Addo) participated in the meeting. In addition, NHI and colleagues from the Purdue
Energy Center held a more in-depth conversation with GRIDCo technical staff and
the role they can play in the project.
• On August 12-13, 2013 a partners’ workshop was held to discuss the progress so far
and the methodology for establishing target flows that will be able to restore the
downstream ecosystem using the data and information which have been collected by
partners.
• The WRC organized a Mid-Term Review program from January 13-24, 2014 “to
assess how well the project is progressing in achieving its objectives.” The program
included several meetings with the AWF and the project partners; facilitated by an
independent consultant to “take stock of work undertaken (by the project) and help
make informed decisions with regards to the achievement of the development
objectives,” including the need for mid-course corrections in the workplan and roles
to reflect the learning that has been achieved in the project so far. […] Findings of the
MTR will contribute to refinement, adjustments and re-allocation of resources for the
success of the project” (Terms of Reference for Mid-Term Review).
1. Determine the flow pattern that will be most advantageous to bring back the
downstream ecological functions and livelihoods.
Project partners set out to determine the pattern(s) of downstream flows that would result
in restoring an array of environmental benefits that have been impaired by the operation
of the dams since 1965. Due to limited empirical data, the likely method to be utilized
will be to assume that the pre-dam hydrograph provided the physical conditions
conducive to the full range of benefits that we now seek to restore, and then to eliminate
features of that hydrograph that either cannot be re-created, or are deemed to be
undesirable. Findings presented at a project workshop in August 2013 suggest that the
environmental restoration objectives will best be achieved through improvements in flow
patterns in combination with physical improvements (e.g. mechanical removal of weeds
and reducing riverbank gradient) in the downstream floodplain.
• Ascertain the physical and economic limitations on the ability of Akosombo and
Kpong dams to release water and generate power. Specifically, we need to ascertain
the feasibility of retrofitting the dam with additional turbines to permit larger releases
of water during the times when a controlled flood is desired.
• Quantify the magnitude of the controlled flood events that can be released from
Akosombo and through Kpong to the estuary without causing catastrophic inundation
downstream that will damage property or endanger lives. Thus, it is also necessary to
ascertain the flood reservation requirements in Lake Volta. This will be
accomplished by changes in land uses in the floodplain to accommodate these larger
flow events. That should allow Lake Volta to retain higher storage levels than it does
under current operations, and thereby increase power output. The challenge is to
figure out how much additional storage it can maintain without creating risks of
floods larger than the targeted controlled floods (bearing in mind, however, that,
axiomatically, there is always some probability of a flood larger than design). The
operations model should allow us to ascertain this storage level.
• Estimate the size of pulses needed to create the hydraulics that will mobilize
sediments downstream of the Kpong dam so that downstream geomorphic processes
can be re-established, including beach accretion.
• The NHI team will determine whether these scenarios provide climate adaptation
benefits in a future of more intense droughts and floods in the Volta River system.
Climate change will require greater capacity to store and channel water in the Volta
river system. This project will test whether Akosombo dam can do a better job of
managing larger floods by utilizing the capacity of downstream floodplain to
accommodate (store and attenuate) controlled flood flows, provided that floodplain
land uses are adapted to this purpose. This work is of vital importance in Africa, the
continent that is already most ravaged by droughts and floods, with often devastating
consequences for the food production systems that are here, particularly, so intimately
connected to natural river functions.
3. Redefining role of the dams in the power generation mix for the Ghana Grid and
WAPP.
Generating the reoperation scenarios that will be assessed for feasibility and effectiveness
(in achieving the project goals while maintaining or improving power system reliability)
will be done jointly by all of the project partners, including at least the entire NHI Team,
VRA, GRIDCo and WRC. This essential task will require a day or two of interaction
among the project team. However, it cannot be done until the previously mentioned tasks
have been completed.
5. Assessing the Reoperation Scenarios using the WEAP Planning Model and the
WAPP System Operations Model
These models will be used to assess (1) physical feasibility and (2) efficacy of the
scenarios to achieve the dual objectives of (A) achieving the restoration flow targets, in
whole or in part, and (B) maintaining or improving power system reliability. The model
runs will be conducted iteratively. After the initial runs, the outputs should reveal which
of these are most robust in terms of the objectives and also suggest how the best
performing can be fine-tuned to improve outcomes. This process should reveal the
optimal reoperation scenario to incorporate into a reoperation plan.
This will be an economic cost-benefit analysis of the “finalist” scenarios run through the
planning models. The NHI Team (the Purdue group) will carry out the power-system
cost-benefit analysis. The costs include the additional capital costs of the reoperation
The additional benefits that can be quantified are the increases in food production and
livelihoods, which will be analyzed by IWMI. However, the challenge here will be
establishing the causal relationships between improved flow patterns and biological
productivity of the estuary—the same problem encountered in attempting to set
empirically-based restoration flow targets.
This project is one of a suite of regional reoperation investigations around the world to
demonstrate a toolbox of techniques that can be widely applied to the current inventory of
major dams and to the next generation of dams to make them more environmentally
compatible. Thus, this project has the dual objective of improving the environmental
performance of the major infrastructure on the Lower Volta River and also of
contributing to a global process of shared learning. We expect this work to result in a
transformation in how dams are sited, designed and operated at the global scale.
The knowledge sharing and dissemination of project results, outputs and lessons learned,
will take place through an online platform; a process of structured workshops; and high
level briefings to the development assistance agencies, dam operators, national
governments, non-governmental organizations and the academic community. The project
will produce reports and workshop presentations for major international water
conferences (i.e. World Water Week) that will show case the project results and to
demonstrate the analytic tools best employed to develop dam reoperation plans and the
broadly replicable reoperation techniques. In addition, both training and knowledge
sharing among the Ghanaian and international partners will be an ongoing, integral part
of the entire project.