Project Management & Supervision Student Resource Guide
Project Management & Supervision Student Resource Guide
1. Course Overview 3
1.1 Setting the foundation - Module review .................................................... 3
1.2 Goal.......................................................................................................... 3
1.3 Objectives ................................................................................................ 3
2. Guiding Principles 4
2.1 Objectives ................................................................................................ 4
2.2 Client Service ........................................................................................... 4
2.3 Guiding Principles .................................................................................... 5
3. Initiating Phase 7
3.1 Objectives ................................................................................................ 7
3.2 Preliminary Cost Estimate (Bid requirements and practices) ................... 7
3.3 List of Stakeholders .................................................................................. 8
3.4 Risk/Reward Analysis............................................................................. 10
3.5 Project Scope Statement ........................................................................ 10
3.6 Construction File .................................................................................... 12
3.7 Development Regulations ...................................................................... 13
3.8 Building Permit Required Documents..................................................... 14
4. Planning Phase 17
4.1 Objectives .............................................................................................. 17
4.2 Scope Management Plan ....................................................................... 19
4.2.1 Finalize the preliminary scope statement ............................................. 19
4.2.2 Work Breakdown Structure .................................................................. 20
4.2.3 Develop scope management plan ....................................................... 22
4.3 Schedule ................................................................................................ 23
4.4 Cost Control Plan ................................................................................... 27
4.5 Cost Control Tools ................................................................................. 29
5. Executing Phase 42
5.1 Objectives .............................................................................................. 42
5.2 Executing the Project Plan ..................................................................... 42
5.3 Scope Management Plan ....................................................................... 43
5.4 Scenarios ............................................................................................... 44
Guide
6. Monitoring/Controlling Phase 52
6.1 Objectives .............................................................................................. 52
6.2 Conduct Daily Site Visits ........................................................................ 52
6.3 Update Your Daily Log ........................................................................... 53
6.4 Keep Track of Inspections ...................................................................... 53
6.5 Monitor Safety ........................................................................................ 53
6.6 Required Inspections ............................................................................. 58
6.7 OH&S - Ontario ...................................................................................... 63
6.8 Workplace Hazardous Materials Information System (WHMIS) ............. 64
6.9 Workplace Safety & Insurance Board (WSIB) ........................................ 65
6.10 Monitoring Variances ............................................................................ 65
6.11 Monitoring Risk ..................................................................................... 65
6.12 Monitoring Procurement ....................................................................... 66
7. Closing Phase 67
7 .1 Objectives............................................................................................... 67
7 .2 Substantial Completion/Performance ..................................................... 67
7.3 Pre-Occupancy Detailing ....................................................................... 69
7.4 Pre-Occupancy List ................................................................................ 70
7.5 Pre-Delivery Inspection (PDI) ................................................................. 70
7.6 Warranty ................................................................................................ 72
8. Resources 74
estimating ii
Project Management & Supervision - Student Resource
Guide 1
All rights reserved. No part of this publication may be reproduced or transmitted
in any form or by any means electronic or mechanical including photocopying,
recording or through the use of any storage and retrieval system without written
permission of Training Ontario.
The information provided in this student resource guide is solely for the user’s
information and convenience and, while thought to be accurate and functional, it
is provided without warranty of any kind. If in doubt, please refer to the current
regulations in your area. Training Ontario, its agents, employees or contractors
will not be liable to you for any damages, direct or indirect, arising out of your
use of the information contained in this student resource guide.
estimating 2
1. Course Overview
Welcome to the Project Management and Supervision presented by Training
Ontario.
This training program is designed to enhance the knowledge and requisite skills
to manage the construction of residential housing classified in Part 9 of the
Ontario Building Code.
1.2 Goal
The goal of this training program is to provide you with a general understanding
of project management principles that should be applied to successfully manage
residential home building projects.
Discuss considerations for the nine knowledge areas as they apply to the five
phases of the project lifecycle.
Apply the project management tools and principles during the various phases
of residential home building projects.
Guide 3
2. Guiding Principles
Remember to establish realistic
This section will provide you with general expectations from the beginning.
information about course content. It will The client may be expecting their
discuss the fundamentals of client service. home to look like the show
home, but if they haven’t paid for
2.1 Objectives the extras, they may be
disappointed.
At the end of this module you will be able:
Different customers have different priorities. Make sure you know your
customer’s (Are they hyper-focused on budget? Do they have scheduling
demands that have made for tight timelines? Are they most concerned with the
quality of materials and craftsmanship?).
As you learned in the online module, you can help manage expectations with
clear communications.
Key Points
Regardless of your interaction level with the customer, it’s important to know
the basics about client relations.
This course is designed around the five phases of the project lifecycle that you
reviewed online. See figure 1: Five Phases of the Project Lifecycle.
Consider the familiar constraints of a project: scope, time, cost and quality as
well as human resources, communications, risk and procurement. These will be
revisited in a more extensive discussion of the project plan components.
Planning
Initiating Closing
Monitoring/ Executing
Controlling
The involvement of PM at this phase will vary, but here are some typical actions
that should be taken during initiation:
Order-of-magnitude (ballpark).
o Quickest and easiest to perform.
o Based on a common multiplier (e.g. price per square foot).
o Not always reliable, has a +/- 35% margin of variation.
o Ballpark is better for standard homes, not reliable for customized homes.
Approximate (top-down).
o Uses historical data.
o More reliable than ballpark, +/- 15% margin of variation.
o Uses past projects that are similar in scope/type.
o More time consuming, but also more reliable and realistic.
Guide 7
o Better for builders who repeatedly build small homes.
Manage
Keep Closely
Informed
Interest
Keep
Monitor Satisfied
Influence
Key points
The Influence/Interest grid exercise may illuminate people that you need to
get in touch with right away.
It will also come in handy in the planning phase when you create a
Throughout this process please don’t work alone; consult with trades,
employer, employees and colleagues
Guide 9
3.4 Risk/Reward Analysis
You should be aware of the risks and rewards of your project, and make sure
that everyone closely involved in the project knows what they are. Perhaps
there are some risks that you are aware of that weren’t considered, such as
personal experience with a community group that opposes construction.
Keep the lines of communication open with the person in your organization that
does this analysis. You may learn more about your company’s objectives, and
you may be able to spot problems and work on solving them early on.
Risk Reward
If the project fails, will you go bankrupt? Will you be able to enter new markets?
Scope Statement
Project Objective
To construct a high-quality, custom home within five months at cost not to
exceed $550,000
Deliverables
Milestones
1. Permits approved—March 5.
2. Foundation poured—March 14.
3. Dry in. Framing, sheathing, plumbing, electrical, and mechanical inspections
passed—May 25.
4. Final inspection—June 7.
Technical Requirements
1. The home will be built to the specifications and design of the original
blueprints provided by the customer.
2. Owner is responsible for landscaping.
3. Refrigerator is not included among kitchen appliances.
4. Air conditioning is not included but rough-in is included.
5. Contractor reserves the right to contract out services.
6. Contractor is responsible for subcontracted work.
7. Site work limited to Monday through Friday, 8:00 A.M. to 6:00 P.M.
Guide 11
3.6 Construction File
Consider the following questions when reviewing the construction file:
Purchase agreement with Are addenda and specifications reflective of each other?
addendums Is there something in the agreement you think may not
be correct?
Are the addenda clear, and are they all there?
Construction Contract Type of contract: Build and sell or build only?
Land Owner: Client, developer, builder?
Payment schedule
Building permit/stamped Are there any changes to the plans or specifications
building plans and shop required as part of the permit approval process including
drawings special requirements?
Building plans and shop Do the specifications make sense when you compare the
drawings–working set plans to the grade slip?
Will that affect other components such as the number of
stair risers or the need for hand rails?
If specifications call for added elements such as
windows, do the plans reflect this?
Building specifications Are addenda and specifications reflective of each other?
Are specifications too limited in scope? Example: using
brand names in a spec. If that brand is not available,
you could be in breach of contract
Are they too vague? Example: Rebar in the foundation.
If where or how much is not stated, there can be
misunderstandings.
Be specific without being too prescriptive.
Land developer What variables exist?
information/grade slip Does this look right?
Plot plan Are any variances you have found accounted for?
Zoning: Zoning by-laws dictate the land uses permitted in each zone of a
municipality. Make sure the project is compatible with the zoning bylaws.
Permits: You must acquire all necessary permits. There are a number of
permits that are required: Building Permit, Development Permit and Sub
trade Permits. Some jurisdictions allow building permits to be released in two
stages:
o Very common; most urban and many rural lands have easement or right-
of-way agreements.
o Usually registered on the certificate of title to the property.
o Remain with the land and are automatically transferred from one owner to
another as the land is sold.
o Remain on the title until the holder of the easement discharges their rights
from the certificate of title.
Examples:
Required for additions, decks, accessory buildings and some exterior work
Required when work has the potential to affect bulk water runoff
lintels)
Location of plumbing fixtures
Smoke alarm locations
If engineered roof trusses are going to be used then the truss layout and
designs are required
Hip or girder trusses must be noted on the floor plans
* Please note: Partial roof framing plans may be required to indicate loading
conditions affecting the existing structure and new addition.
3.8.5 Elevations
3.8.6 Cross-Sections
HVAC designs are part of the Energy Efficiency requirements outlined in the
Ontario Building Code (OBC). These must be provided by a certified individual.
estimating 16
4. Planning Phase
4.1 Objectives
Key points
The purpose of this phase is to answer the questions that need to be answered
before moving to the execution phase.
The best way to answer these questions is to develop your project plan, which is based
around PMI’s 9 knowledge areas.
estimating 18
4.2 Scope Management Plan
The scope management plan will specify how major changes will be handled,
including how the change will be planned, priced and implemented. To develop
this portion of the project plan, you will:
Confirm that the preliminary scope statement reflects the current project goals
Specify:
- Products and services you offer
- Products and services you do not offer
Key points
• The scope must specify the products and services you offer and do not
offer, in the context of this project.
Example: initial client meeting called for a 3,500 square foot home.
During contract negotiations, the client decided to increase the floor plan
The work breakdown structure (WBS) is a chart that shows all the work required
to complete a project.
4. Add details to the high-level structure (consider lead time and remember to
add time contingencies in case of delays).
o Add lower level details / tasks required to complete each high-level task.
o There is no hard-fast rule about how wide or how deep to make the WBS:
use your best judgment and learn from past experiences.
o Be sure to adapt the WBS to each project. The flexibility of the WBS
makes it the greatest asset to the planning process.
o Consider using a coding system as a quick reference.
The goal is to show how the work will be done, not how much it will cost, who
will do it or when it will be done.
Key points
Meet with people who will help you develop the WBS.
For large projects, this could include your project team, the general contractor
and subject matter experts.
For small projects, you could wind up developing the WBS by yourself.
To save time, you can start with a WBS that you used for another project.
Remember to consider what you learned from past projects. Ask yourself
where you lost or made up time.
estimating 20
Figure 5: Sample Work Breakdown Structure
Visit the Reference section of the online course to print the enlarge view of the
above sample work breakdown structure.
Guide 21
4.2.3 Develop scope management plan
Key points
The scope management plan will specify how major changes will be handled,
including how the change will be planned, priced and implemented.
The definition of a major change will depend on the project.
The project plan should identify who can approve major changes and what
would be the process for completing this change.
Your company should have a policy already in place for major changes. If
not, you should develop one for each project.
Questions
To complete the construction schedule, you will typically take the following six
steps:
2. Sequence tasks: place them in the order that they will need to be completed.
Once you have a list of all the tasks that need to be completed to get to the
end of the project, you will place them in the order that they will need to be
completed.
Remember: A list of tasks that looks good on paper may not work on the job
site! Seek input from colleagues, employees and sub-contractors to find their
particular requirements or preferences for their involvement.
3. Estimate required resources for each task. If tasks are being outsourced to
sub-contractors, they will be responsible for this step. If you are completing
tasks with internal resources, you will need to ensure you have sufficient
funds, equipment and workers to complete the work. Follow the steps below:
Use the task list as a guide to assign equipment and workers to each
task.
4. Estimate duration of each task: There are many different ways to develop an
estimate. Start by assigning realistic time for each task, given optimal working
conditions, and then add a contingency. You can use the critical path method
Guide 23
(see figure 6: Example of a 50 day critical path).
To estimate duration:
o Estimate best case and worst case scenario, then take the average
o Double the best case scenario
o Add standard safety time, in case anything arises.
o Critical path method
The critical path method is a project management tool used to identify the
longest sequence of tasks required to complete a project.
In the example (figure 6), the critical path is 50 days. The alternate path is 30
days. Tasks D and E will be completed at the same time as tasks B and C. If
something happens that would delay either task D or E (such as poor
weather conditions, permits not being provided on time or errors in
deliveries), then the critical path may change.
Important note: The critical path method does not take into account
resources. If the same employee is supposed to work on tasks B and D, then
task D would need to be moved up in the critical path (which would now be
55 days).
Don’t forget to take into account the factors that could affect the project
schedule (e.g., weather, material shortages, sub-contractor delays).
If you have a fixed-date possession, you have to build your schedule around
it.
• Once you are ready to finalize the schedule, you will prepare a workable
and flexible schedule that you can then share with your project team.
• Once you are at this stage, don’t think that your work is all done!
Scheduling is an iterative process that must take into account many
different factors that could affect the project schedule, such as the
weather, material shortages, sub-contractor delays and more.
An iterative process is a process for calculating a desired result by
means of a repeated cycle of operations. An iterative process should be
convergent, i.e., it should come closer to the desired result as the number
of iterations increases.
• If your schedule was properly prepared, these factors should result in
slight adjustments only, not drastic changes.
Fixed-date possession
The first schedule you develop will serve as the baseline for this project.
Keep this baseline copy and update it with any changes that occur. Make
special note of any critical scheduling tasks or stages.
• Examples:
• Flooding causes delay in shipment of materials.
• Sub-contractor declares bankruptcy.
• Employee fails a drug test.
• Rain lasting for weeks.
• Hit water table or underground spring when digging for the
footing or septic tank.
Your cost control plan should include strategies to check for discrepancies, plan
for contingencies and meet budgetary timelines. You should use your cost
control plan as a control tool throughout your project. Do not simply update it
after suppliers and subcontractors are paid!
• Controlling costs
• Discrepancies check
• Contingency fund
• Timeline
Key points
• Your project plan should contain the budget and a plan for controlling costs.
• The preliminary cost estimates developed during the initiation phase now
have to become detailed cost estimates and amalgamated into one master
budget document to provide a total cost baseline.
• Compare this number with the preliminary cost estimate. If there are huge
discrepancies, communicate with appropriate stakeholders.
• Cost control plan should be used as a control tool throughout your project. Do
not simply update it after suppliers and subcontractors are paid! Guide 27
Multifamily projects:
- Quantity surveyors
Key points
• Remember that you are dealing with mortgage draws so that you can make
payroll, pay sub-trades, etc. You have to meet timeline targets to get things
done so that cash continues to flow.
If you work on multifamily projects you may need to work with quantity
surveyors. Quantity surveyors are experts at assessing the value of a project
that is not fully completed.
These professionals are used by the bank for mortgage draws; they assign a
value for the stage of the project’s development (value of work in place).
They report to the banks on a monthly basis and the contractor is paid out
accordingly.
estimating 28
4.5 Cost Control Tools
Variance and earned-value analyses are two cost control tools that can help you
keep your budget on track. Here are some more details:
You have to put a plan in place to make sure that the project meets the
standards set out in the plans and specifications, show home and workmanship
material guide. Here are two strategies to plan for quality control:
• There is a common misconception in the industry that the warranty works the
same as insurance: if things go wrong you’re covered. The fact is warranty
providers can recover repair costs from builders if deemed appropriate. You
• Find out the documents required by your warranty provider. Ask what the
processes and expectations are for filling out documents.
• Make sure you are aware of what dispute-resolution processes are available
through your warranty provider.
• Two ways to ensure quality: training and inspections. You should plan for
both.
Guide 31
4.7 Communication Plan
You should create a communication plan that contains the following information:
Who needs the information?
What information is needed?
Who is responsible for sending information?
How should information be sent?
Consider creating a communication matrix to help you keep track of all the
people involved with your project (see Figure 9: Sample Communication Matrix).
• Make sure that you have tailgate meetings with everyone on site (and make
sure there is a major focus on health and safety).
- Pre-construction meetings are not mandatory but most builders that have
implemented their use cannot imagine not using them. These meetings
are sometimes referred to as tailgate meetings.
- A pre-construction meeting is used to clearly define the scope of work to
be completed and the people responsible for each portion.
- Some projects are done with only one meeting at the start of the project
while others have meetings at the beginning of each stage, each week, or
even each day where necessary. (ie. On volunteer based projects like
Habitat for Humanity)
- Depending on the frequency of the on-site meetings they may include
some or all of the following information:
o Introduction and circulation of required contact information
o Distribution of up to date plans
o Distribution of up to date specifications
o Distribution of approved change orders
o Timelines or updates to timelines
o Introduction of trades that will need to work in concert with one
another
o Distribution of information on safety issues, insurance issues and
MSD sheets as required
- At times it may be necessary to have more than one meeting in order to
separate topics to specific trades, etc.
- Before setting up an onsite meeting consider the following:
o What information do I need to get across NOW
o Who do I need to be at this meeting
o Do I have contact information for each of these workers
o What is the best way to get the message across
o Do I have answers to the questions that will arise due to the
information being circulated
- Those that you identify to be at the meeting may not be able to make it so
To develop a risk management plan, you have to analyze risks and plan
responses.
Analyze Risk
Assign probability: Once you have a list of the risks that could happen, it’s
important to determine how likely they are to occur. Determine if it’s low,
medium or high. Drill this down to an approximate percentage (0-100%).
Estimate impact: Determine the effect that the event would have on the
project. Consider time and money. Add a cost and/or time estimate for each
risk.
Quantify effects: Multiply the probability percentage by the cost or time
impact to come up with the quantified effect.
Prioritize: Rank your list of risks giving those with the highest probability and
impact priority.
Plan Responses
Once you have analyzed the risks and planned responses, you should develop a
plan to make sure that you recognize risks when they occur and to recognize
new ones as they come up. Risks have a specific lifespan and should be
monitored at the point when they are likely to occur. Working with your list of
prioritized risks, the project schedule and the WBS, identify at what stage risk
events are likely to occur and identify strategies to monitor the risks. Write these
into your schedule to keep you on track.
estimating 36
4.10 Human Resources Plan
Key points
• While developing the schedule, you determined the resources required for
each task. If you have a role in staffing, this can guide your staffing
requirements.
• If there is specific training that your team requires, lay out how and when
this training will occur. Remember that training can improve quality.
• Keep in mind the health and safety and other labour-related legislation in
your area. Depending on where you are, you may be required to develop a
health and safety plan. Next we will discuss the health and safety plan in
more detail.
• Tailgate meetings are a great time to discuss health and safety hazards.
Make sure to work it in to every meeting. This will be discussed more in the
Guide 37
Health and Safety Plan
If you find yourself in the role of prime contractor on the work site, remember that
you are responsible to ensure that contractors, employers and employees at the
work site comply with the Occupational Health and Safety Act and regulations.
The Act requires the prime contractor to put in place an action plan to make sure
those working on the job site are in compliance and to set up mechanisms for
monitoring health and safety. An effective health and safety plan is one way of
meeting this requirement.
The health and safety plan includes documents that describe health and safety
policies and procedures. It may include the following information:
Some site managers use software to keep track of purchase orders and some
use physical PO books (Note: there are over 150 POs required for the
construction of a basic home). Choose what system works best for you.
When the invoice doesn’t match the PO within a specified variance amount, the
invoice is returned to the supplier for them to investigate.
Key points
• Purchase order systems are mechanisms that you put in place to control
costs and inventory.
• Can reduce cost overruns: P.O.s are issued based upon the supplier’s
quotes to the builder. The builder may also get additional pricing and quotes
if required. These are then added to the job budget.
• When the invoice doesn’t match the PO within a specified variance amount,
the invoice is returned to the supplier for them to investigate.
At times extra work on site is required due to various reasons. To account for
these, you can use a “variance PO”.
The variance PO allows more flexibility because it enables you to order the
material necessary to complete the job on time, without the need to re-issue
new POs from the office.
Guide 39
4.11.2 Inventory Control
An important part of your job is to protect raw materials and completed work.
This includes doing all you can to prevent vandalism and theft. Theft of
materials is among the top causes of losses for builders.
• Recently, the price of copper hit a five-year high. As a result, builders and
property managers noticed an increase in thieves stealing copper wiring from
buildings and selling it to scrap metal recyclers. This type of theft creates a
double-hit, as the builder is then responsible for replacing the wiring and for
repairing the damage caused when it was ripped out of the walls.
• Theft from construction sites is not just about the materials stolen. Thieves can
cause damage to the building during the theft, as well as project delays from lost
materials. For example:
• Thieves recently made off with copper piping cut from heat pumps on
the top floor of a new condo. As a result, the building was flooded,
causing damage in excess of $165,000 and delaying the project seven
months.
• These thefts cause damage far beyond the actual materials that have been
stolen. Repeated claims can result in increased insurance costs, and even in
denied claims. Companies can also incur higher deductibles and removal of
certain costs from claims (as some policies do not cover stolen tools).
Key points
• Inventory Control: Protect raw materials and completed work including the
prevention of vandalism and theft
• Materials can go missing from time to time because of human error, but
they can often disappear because of theft.
5.1 Objectives
Your job during this phase is to be a detective; looking for the various effects one
issue can have on each component of the project (integration management).
There is a lot to manage, and that’s why it’s important to keep organized.
Remember the idea of integration management: you have to consider how a
project will be impacted by many angles.
Your job during this phase is to be a detective, looking for the various effects one
issue can have on each component of the project (integration management).
Let’s look at a few general examples to test your investigative skills.
estimating 42
Execution consists of:
Executing the scope management plan means ensuring that the work that was
agreed upon is being completed. This differs from Quality Control: "Scope
verification is primarily concerned with the acceptance of work results while
quality control is primarily concerned with the correctness of work results."
(PMBOK)
To execute the scope management plan, conduct your inspections and review
the work as it is being completed.
For example, if there has been a delay and the customer is upset, don’t promise
them something to make up for it without careful consideration of all project
components.
5.4 Scenarios
The supplier can get the windows repaired on site, but it will take approximately
a week for the work to be done.
Guide 45
A job you’re working on has allowed for a sweat equity arrangement with the
client.
• Sweat equity is when customers are given credit for work they do in their
home. It provides the customer with the benefit of having to come up with less
money to purchase the home or with a smaller down payment. It also makes it
possible for them to add items to their home which they might not have
otherwise been able to afford.
• The downside to sweat equity is that quality is affected by having untrained
people do part of the work. Customers working in their homes affect the
construction schedule because they are often only available to do the work on off
hours, and they take longer than the trades. If they are not available on the
exact date and time the trade would be able to do the work, the home will not
only take longer to finish, it will affect the flow of planning, not only for their
house but for others as well.
• Construction insurance does not cover work done by the client.
• It is difficult to recover any damage to previous trades work. For example, if a
customer who is installing his own hardwood damages the drywall, the drywall
company will charge the builder for those repairs. Clients rarely take
responsibility for damage and they don’t want to pay for it. This kind of scenario
can have a negative affect your relationship with the client.
You finish a feature and the client expresses disappointment because it’s not
what he expected.
estimating 46
What do you do?
Your railing supplier is upset because the cabinet supplier keeps going up and
down the stairs, causing disruptions, delays and safety issues.
• First and foremost, you have to communicate, both with the supplier and the
client. Having a discussion with the client may being unexpected solutions
(perhaps the client will be happy with the countertops)
• If you are nearing possession and a three-week delay is out of the question,
you may consider installing the countertops as is, and replacing them down
the line
• Scope management: ensure that the work that was agreed upon is being
completed to the expected standard.
• Time management: When delays occur, consider the impact that will have on
the rest of the project.
• Cost control: You can help manage the costs of a construction project by
making sure that change orders are accurate.
• Quality control: Consider how changes in materials can affect the quality of
work.
• Communication management: Tailgate meetings will help keep the lines of
communication with the trades open. Make sure there is a strong focus on
health and safety during these meetings.
• Risk management: Make sure to update your risk management plan as new
risks arise. You won’t always know what risks exist until you are in the middle
of construction.
• Human resource management: It can be difficult to deal with different
personalities on a job site. Keep notes about issues that come up. You may
be able to learn from them and avoid HR issues in the future.
estimating 50
• Procurement management: Procurement management ties in with
communication in a major way. Make sure there is clarity when you are
communicating with the person in charge of procurement so you don’t end up
with the wrong people/materials/equipment down the line.
Integrated change control is a vast topic, but basically it means that you have
planned a way to manage the changes that occur during a project. It means that
you evaluate suggested changes using tools to evaluate whether the change
should be approved or rejected.
You need to know what’s going on with your project as early as possible so you
can address the problem and take corrective action. All the planning you have
done should ensure that you are prepared to meet the demands of most
situations.
You should visit each site every day. While you’re there, you should do the
following:
• Make sure everyone understands the work they are doing and the expected
amount of time it should take.
• Tell them to let you know as soon as possible if they think they will be late.
• Spend enough time at each site to get a good idea of what is happening.
• Check to see all trades and supplier commitments are being kept.
• Take photos as they can save you in the event of a dispute! You can also
estimating 52
The best way to make sure that your records are organized and easy to consult
is through the use of a daily log. The log is a historic record of the daily events
that take place on the job site. Not only can this information protect you legally,
it can also help you to continuously improve by offering insight into why
particularly good or bad results were obtained.
Here’s a recap of the information that should be included in your daily log:
If you ever need to use your daily log as evidence in a legal case, you can
improve its credibility by keeping it in the form of a bound book. The best format
is a blank-page notebook on which the site manager enters the date at the head
of each entry rather than having the pages predated. There should be no space
left between the end of the entry for one day and the beginning of the entry for
the next day, and all the pages of the book should be entered consecutively.
Keep track of what inspections need to take place and add them to your
schedule.
A construction site is always changing and is full of hazards. You are required
by law to maintain a safe workplace (Occupational Health and Safety Act,
Regulation and Code). The Canada Labour Code states that employees have
the right to refuse work that they deem to be unsafe. For more information on
health and safety legislation, visit the Infrastructure Health & Safety Association’s
website [http://www.ihsa.ca/resources/health_safety_manual.aspx] and
download a copy of individual Construction Health and Safety Manual chapters.
Guide 53
Promote a culture of health and safety
Develop Safe Work Practices for any hazardous work, such as:
The following Hazard Recognition Form can be used while conducting a hazard
assessment.
estimating 54
Hazard Recognition Form
Status Legend:
1 2 3 4 N/A
Access 1 2 3 4 N/A
13. PPE (gloves, mask, goggles, ear protection, hard hat) 1 2 3 4 N/A
Hazards Identified:
Signature: Date:
estimating 56
Print Name
Trade/Staff On-site:
Signature
There are numerous inspections required throughout the project process. Below
is a list of normal inspections and when you should request them.
NOTE: Not all inspections are required in all areas. As the project manager
it is your responsibility to confirm which inspections are required and
when. Remember that each municipality may be different.
Building Inspections
applied)
HVAC
Fire separations at completion of wall, floor and shaft separations and fire
Insulation and vapour barrier at completion of insulation & vapour barrier and before
installing drywall
Often call a pre-drywall inspection
Outside storm & sanitary sewers at completion, before back filling and
Inside storm & sanitary sewers at completion, could be partial, ready for
Rough-in, water supply, drains, waste & at completion and ready for testing
vents
required fixtures
*In most cases the plumber will call for these inspections but it is important that you do not proceed until
these inspections have been completed and passed.
estimating 60
Electrical Inspections
meter, the main disconnect means (for (may be done at the same time as
Rough in Inspection (all electrical wiring at completion, could be partial, ready for
drywall
occupancy)
Guide 61
HVAC Inspections
installation of insulation
*Construction may be done in phases. Such projects may require additional inspections.
*There may also be Bank Inspections required by the financial lending institute
as various stages of construction.
- Preventing work-related illness and injury is the most important job at any
workplace
- Know the current requirements in the area you are working as they vary.
For example, in Toronto, you may be required to have the site enclosed
with protective fencing.
- Insist that your workers wear and use proper safety equipment, such as
- OH&S also requires you to ensure that everyone on the work site adheres
to the safe limits of approach for live electrical lines.
- Safe At Work Ontario is the Ministry of Labour’s strategy for enforcing the
Occupational Health and Safety Act. This program makes many
resources available to help in your own implementation of the regulations
on site.
- Employees and sub trades have the right to know of potential dangers
that can affect their work and health.
- When you are covered by the WSIB, it means that if you are injured in a
work-related accident or develop a work-related illness, WSIB will support
you through your recovery, and help you get safely back to work.
Construction variances are a major drain on profits for a home building company.
Be sure to review variances and compare actual results against the baselines.
Learn to identify scope creep early on, before it becomes a major problem.
The ability to specifically define risk increases as your project moves forward.
Risks are more definitive during the Execution Phase than they are in the Project
Planning Phase, as knowledge of the project and any associated issues has
increased. Realistic contingency plans with specific actions can be put into place
as a control measure.
Risk management, which looks at risks to the project and potential impacts, is
implemented throughout the project. You’ll remember that risk management
includes four steps:
Guide 65
1. Risk Identification
Also remember that risk management involves all members of the project
team. As part of your risk management strategy, you should hold regular
meetings with your team. These meetings include:
• If you have to pick something up from a supplier make sure you have
clear directions, proper documentation of product detail and appropriate
measures to protect it from damages in transit.
• You have to keep track of delivery schedules and adjust them if
necessary.
• You may be required to collect shipping orders, sign off on deliveries and
confirm that the orders are correct
• On a condo project you would have a trailer for inventory of your standard
items by sub-trade suppliers, and then you make sure you have adequate
supply in the trailer as the project progresses
• Example of ordering special order items and finishing: Client special
ordered appliances – you have to ensure on-time delivery, secure storage
and consider the impact: are there special rough in requirements? Do you
have the right electrical, gas supplies, and cabinetry sizes?
• Hardwood has to be on site and protected: protect it from rain, hazardous
materials, etc.
• You have to ensure safe access for delivery and storage of material.
• Procurement procedures should be clearly defined in the Independent
Contractor Agreement used for each of the sub-trades.
estimating 66
7. Closing Phase
7 .1 Objectives
There are many things to consider when closing a project. This section will
discuss the following topics:
Substantial completion/performance.
Pre-occupancy detailing.
Pre-occupancy list.
Customer PDI (Pre-delivery Inspection)
Warranty
If you have a sound schedule in place and you have been updating it throughout
your project, you should anticipate the completion of your project well in advance
and be able to take appropriate measures, such as beginning the final cleanup
operations.
7 .2 Substantial Completion/Performance
In Ontario, the PM or Builder manager must inform the municipality that the new
home is substantially completed (e.g., the building can be used for its intended
use). This may include such inspections as “Occupancy” or a “Final Inspection.”
Once the PM manager receives the Certificate of Substantial Performance, it
must be placed in the home, in clear view. The Certificate notifies all sub-
contractors that the terms of the Builder’s Lien Act are now in effect: It is
important to note that the OBC requires “occupancy permits” to be issued by the
Guide 67
municipality. These are important regarding homes being “sold” and “fixed
closing dates.”
Sub-contractors now have 45 days to file a lien if they have not been paid all
monies.
Pre-occupancy detailing is the first step in the closing process, and it must be
done before the Pre-Delivery Inspection (PDI) and orientation. This step is
usually completed by a senior employee who needs to be very critical of even
Guide 69
the smallest of discrepancies. Being extremely critical at this point will help cut
down on customer complaints and enhance your company’s reputation for
quality. Use the show home as a benchmark for quality. Look for anything that
a customer may not accept and request that you come back to fix it. The cost of
getting trades to return in a completed house to fix these items can quickly spiral
out of control. This step is well worth the time and effort to avoid the costs of
doing things over again and re-establishing customer satisfaction! You could
spend an unlimited amount of time and resources trying to meet the customer’s
expectations.
After completing the pre-occupancy detailing and fixing anything that needs to be
fixed, you should provide the customer with all items required by their contract.
The pre-occupancy list should be prepared at least one week before the Pre-
Delivery Inspection (PDI)These items can include (but may not be limited to):
Be sure to highlight any items on the list that require attention prior to
possession.
The Pre-Delivery Inspection (PDI) is your opportunity to point out the positive
aspects of the customer’s new home. Here are points you should cover:
Show them what items need maintenance, how to perform that maintenance and
how to operate the different systems in their new home.
Here are some general tips to help you through the walkthrough:
Be there at least 30 minutes in advance: you know the client will be there
early; they’re likely excited about getting the keys to their new home!
Make the home comfortable and inviting:
o Place a carpet at the front door to leave shoes. This will prevent the floor
from being damaged and scratched during the walkthrough.
o Turn on the heat or the air conditioning.
o Turn on all the lights, fireplace or any other fixtures and ensure they
operate correctly when you show the client how to operate them.
o Have all required supplies with you, such as a lighter to light pilot lights.
o Ensure the exterior is presentable; remember: you only have one chance
to make a good first impression! Sweep the walkway, clean the garage,
and remove any debris left over from the construction.
During the walkthrough, involve the client! Ask them to light pilot lights, remove
screens and re-install them, remove and replace furnace filters. This will keep
them active and give them pride of ownership. It will also focus their attention on
the task at hand and may stop them from picking at details they don’t like.
1. Start outside.
2. Go to the basement.
3. Go to the second floor.
4. Go on the main floor.
The expert who offers this advice has found that if you start inside, the client is
usually hyper-focused on every detail and focuses on the negative. Starting
outside gives the site manager the chance to direct the client’s attention to the
positive aspects of the house.
Guide 71
7.6 Warranty
Once you have completed the walkthrough with the customer and you are in the
process of signing all the documentation in the kitchen, take the time to explain
the details of the warranty. Review the following key points:
- What the warranty provisions are and who provides the Warranty? (the
builder) Tarion is the backstop.
- Required maintenance and how to contact the service department.
- Explain who they can call in case of an emergency.
- Provide the client with the Homeowner Information Package (HIP)
You should also describe what is covered—and not covered—by a third party
warranty provider:
o One and two year warranties for certain defects in work and materials;
o A seven year warranty for major structural defects; and
o Coverage for condominium common elements (the common or shared
area of condominium buildings.)
Ensure that you’re aware of the Tarion Warranty requirements for Ontario.
Provision of information to the client on how your warranty service meets and/or
exceeds the mandated coverage will help in your relationship with your client.