Project Name: Description: Concrete: SLAB 1
Project Name: Description: Concrete: SLAB 1
Project Name: Description: Concrete: SLAB 1
DESCRIPTION:
Concrete: SLAB 1
Data:
Length 8 m
Width 5 m
Thickness 0.1 m
Total Volume 4 cu.m
Specifications
Class B
Cement in Bag 40 kg
Cement in Bag 7.5
Sand 0.5
Gravel 1
No. of Bags 30 bags
Vol. of Sand 2 cu. m
Vol. of gravel 4 cu. m
Bar Reinforcement:
Bar Diameter 12 mm
Area of Slab 40 sq. m
Bar Spacing 300 mm
Commercial Bar Length 6 m
28pcs-12mm dia. @ 5m width 28
18pcs-12mm dia. @ 8m length 18
140
144
Total 284
Number of Rebars 48 pcs
Tie Wire
Length of tie wire (0.3,0.4) 0.3 m
Weight of tie wire 0.174 kgs
Total Weight of Tie Wire 6.96 kgs
Concrete: SLAB 1
Data:
Length 8 m
Width 5 m
Thickness 0.1 m
Total Volume 4 cu.m
Specifications
Class C
Cement in Bag 40 kg
Cement in Bag 6
Sand 0.5
Gravel 1
No. of Bags 24 bags
Vol. of Sand 2 cu. m
Vol. of gravel 4 cu. m
Bar Reinforcement:
Bar Diameter 12 mm
Area of Slab 40 sq. m
Bar Spacing 300 mm
Commercial Bar Length 6 m
28pcs-12mm dia. @ 5m width 28
18pcs-12mm dia. @ 8m length 18
140
144
Total 284
Number of Rebars 48 pcs
Tie Wire
Length of tie wire (0.3,0.4) 0.3 m
Weight of tie wire 0.174 kgs
Total Weight of Tie Wire 6.96 kgs
Concrete: SLAB 2
Data:
Length 2.8 m
Width 1.7 m
Thickness 0.1 m
Total Volume 0.476 cu.m
Specifications
Class B
Cement in Bag 40 kg
Cement in Bag 7.5
Sand 0.5
Gravel 1
No. of Bags 4 bags
Vol. of Sand 1 cu. m
Vol. of gravel 1 cu. m
Bar Reinforcement:
Bar Diameter 12 mm
Area of Slab 4.76 sq. m
Bar Spacing 300 mm
Commercial Bar Length 6 m
11pcs-12mm dia. @ 1.7m width 11
7pcs-12mm dia. @2.8m length 7
18.7
19.6
Total 38.3
Number of Rebars 7 pcs
Tie Wire
Length of tie wire (0.3,0.4) 0.3 m
Weight of tie wire 0.174 kgs
Total Weight of Tie Wire 0.82824 kgs
Concrete: SLAB 2
Data:
Length 2.8 m
Width 1.7 m
Thickness 0.1 m
Total Volume 0.476 cu.m
Specifications
Class C
Cement in Bag 40 kg
Cement in Bag 6
Sand 0.5
Gravel 1
No. of Bags 3 bags
Vol. of Sand 1 cu. m
Vol. of gravel 1 cu. m
Bar Reinforcement:
Bar Diameter 12 mm
Area of Slab 4.76 sq. m
Bar Spacing 300 mm
Commercial Bar Length 6 m
11pcs-12mm dia. @ 1.7m width 11
7pcs-12mm dia. @2.8m length 7
18.7
19.6
Total 38.3
Number of Rebars 7 pcs
Tie Wire
Length of tie wire (0.3,0.4) 0.3 m
Weight of tie wire 0.174 kgs
Total Weight of Tie Wire 0.82824 kgs
Concrete: SLAB 3
Data:
Length 5 m
Width 4.2 m
Thickness 0.1 m
Total Volume 2.1 cu.m
Specifications
Class B
Cement in Bag 40 kg
Cement in Bag 7.5
Sand 0.5
Gravel 1
No. of Bags 16 bags
Vol. of Sand 2 cu. m
Vol. of gravel 3 cu. m
Bar Reinforcement:
Bar Diameter 12 mm
Area of Slab 21 sq. m
Bar Spacing 300 mm
Commercial Bar Length 6 m
18pcs-12mm dia. @ 4.2 width 18 pcs
15pcs-12mm dia. @ 5m length 15 pcs
75.6
75
Total 150.6
Number of Rebars 26 pcs
Tie Wire
Length of tie wire (0.3,0.4) 0.3 m
Weight of tie wire 0.174 kgs
Total Weight of Tie Wire 3.654 kgs
Concrete: SLAB 3
Data:
Length 5 m
Width 4.2 m
Thickness 0.1 m
Total Volume 2.1 cu.m
Specifications
Class C
Cement in Bag 40 kg
Cement in Bag 6
Sand 0.5
Gravel 1
No. of Bags 13 bags
Vol. of Sand 2 cu. m
Vol. of gravel 3 cu. m
Bar Reinforcement:
Bar Diameter 12 mm
Area of Slab 21 sq. m
Bar Spacing 300 mm
Commercial Bar Length 6 m
18pcs-12mm dia. @ 4.2 width 18
15pcs-12mm dia. @ 5m length 15
75.6
75
Total 150.6
Number of Rebars 26 pcs
Tie Wire
Length of tie wire (0.3,0.4) 0.3 m
Weight of tie wire 0.174 kgs
Total Weight of Tie Wire 3.654 kgs
Concrete: SLAB 4
Data:
Length 6 m
Width 5 m
Thickness 0.1 m
Total Volume 3 cu.m
Specifications
Class B
Cement in Bag 40 kg
Cement in Bag 7.5
Sand 0.5
Gravel 1
No. of Bags 23 bags
Vol. of Sand 2 cu. m
Vol. of gravel 3 cu. m
Bar Reinforcement:
Bar Diameter 12 mm
Area of Slab 30 sq. m
Bar Spacing 300 mm
Commercial Bar Length 6 m
21pcs-12mm dia. @ 5m width 21
18pcs-12mm dia. @ 6m length 18
105
108
Total 213
Number of Rebars 36 pcs
Tie Wire
Length of tie wire (0.3,0.4) 0.3 m
Weight of tie wire 0.174 kgs
Total Weight of Tie Wire 5.22 kgs
Concrete: SLAB 4
Data:
Length 6 m
Width 5 m
Thickness 0.1 m
Total Volume 3 cu.m
Specifications
Class C
Cement in Bag 40 kg
Cement in Bag 6
Sand 0.5
Gravel 1
No. of Bags 18 bags
Vol. of Sand 2 cu. m
Vol. of gravel 3 cu. m
Bar Reinforcement:
Bar Diameter 12 mm
Area of Slab 30 sq. m
Bar Spacing 300 mm
Commercial Bar Length 6 m
21pcs-12mm dia. @ 5m width 21
18pcs-12mm dia. @ 6m length 18
105
108
Total 213
Number of Rebars 36 pcs
Tie Wire
Length of tie wire (0.3,0.4) 0.3 m
Weight of tie wire 0.174 kgs
Total Weight of Tie Wire 5.22 kgs
CLASS B
Cost Estimates: SLAB 1
Name & Specification Unit Quantity Unit Cost Amount
MATERIALS
12mm Rebars pcs. 48 190 ₱9,120.00
Portland Cement bags 30 250 ₱7,500.00
Sand cu.m. 2 700 ₱1,400.00
Gravel cu.m. 4 700 ₱2,800.00
Wire kg 7 65 ₱455.00
Total Cost ₱21,275.00