Tac 2016 Paper 120
Tac 2016 Paper 120
Tac 2016 Paper 120
Jeffrey Oke
Mine Design Engineering, Kingston, Ontario, Canada
ABSTRACT
Umbrella arch systems are defined as a pre-support method that is installed during the first pass of excavation from
within the tunnel, above and around the crown of the tunnel face, that reinforces through the interaction between the
support and the ground. There exist no universal design specifications for umbrella arch systems, however,
recommendations have been made regarding the design components of the eleven sub-categories. Three of such sub-
categories consist of spile elements. This paper will present a guideline for the preliminary design of two of these three
spile elements, when installed to mitigate structure or to manage convergence/strain. These guidelines were developed
from the collection of published empirical data, analytical solutions, empirical verification, laboratory results, as well as
observed limitations/restrictions of installation equipment.
1 INTRODUCTION
An umbrella arch is defined as a pre-support method that
is installed during the first pass of excavation from within Oke et al. (2014a) provided an empirical selection
the tunnel, above and around the crown of the tunnel chart (Figure 1) as well as a range of design properties
face, that reinforces through the interaction between the (Table 1) for each element (spile, forepole, and grout) and
support and the ground (Oke et al. 2014a). Steel the eleven sub-categories of the umbrella arch systems.
elements that are used for the umbrella arch are Oke et al. (2014b) provided some design
described as spiles when they are shorter in length, L, recommendations for umbrella arch systems that employ
than the height of the excavation, He, and described as forepole elements in squeezing ground conditions.
forepoles when they are longer. There currently exist no However, there are still no concrete design guidelines in
universal design specifications for umbrella arch support existence for spile elements. Guidelines for the
systems (Carrieri et al., 1991; Hoek, 1999; Volkmann, preliminary design of spiles will be presented within this
2003; Kim et al., 2005; Volkmann et al., 2006; Volkmann paper.
and Schubert, 2006, 2007, 2010; FHA, 2009; Hun, 2011;
Peila, 2013; Oke et al. 2016). These support systems can Table 1. Suggested range of design parameters for spile
easily be overdesigned, or worse under designed, elements of an umbrella arch system (Modified after Oke,
because of the lack of design standard. An insufficient 2014a). Note: SpCUA: Spile Confined Umbrella Arch
design is easy to identify as it leads to failure, but an SpGUA: Spile Grouted Umbrella Arch.
overdesign is much more different to identify. Such
overdesign of spile elements (L < He) was illustrated in Umbrella Arch with Spiles
Oke et al. (2014a) at the Niagara Tunnel, Canada. The SpCUA SpGUA
over design was minor, as it called for grout to confine the
Length, L 3L -H (3L )
elements in their locations (SpGUA), however, due to the u e u
high stress environment, the ground material squeezed Angle (°) 5-20 (15)
and confined the spiles in location which removed the Overlap (m) L/3-2L/3 (L/3)
requirement for grout. Once this confinement was
Initial center-to-center (cm) <50 (30) <30 (30)
observed, the design was modified the exclude grout
(SpCUA). Similarly, the forepole elements (L > He) at the Diameter (mm) 25-101.6 (50)
Driskos Tunnel, Greece, were slightly over designed, as Grout Pressure (MPa) NA 0.20-1 (1)
shown in Oke et al. 2014b. A study done by Langford et Notes: XX-XX: Range of data (XX): Typical value
al. (2016) echoes this overdesign at the Driskos Tunnel, Lu: Unsupported Span NA: Not applicable
as it was shown that the optimum support systems He: Height of excavation L: Length of support
(without considering the influence of umbrella arch in the
analysis) was typically a design category lower (less 2 BACKGROUND
support installed) than the design category employed.
Figure 1. A condensed version of the UA Selection Chart (UASC) for Convergence Management Ground Conditions and
Structural Control Only. Terminology: Spile Grouted UA (SpGUA); Spile Confined UA (SpCUA); Forepole Confined UA
(FpCUA); and Forepole Grouted UA (FpGUA). (Modified after Oke et al. 2014a).
The umbrella arch system originated over a century ago, 1857 (Szechy, 1966)) steel became the preferred material
when the primary support material was timber and the of support (i.e. introduction of rock bolts). However, the
support installation equipment was powered by humans. first instance of steel-based forepoling/spiling (in pipe
Upon encountering problematic ground conditions form) was not until the mid-1970s in Italy, as cited in
concerning face stability, mining excavation support Carrieri et al. (1991). Oke (2016) illustrates that there has
practices suggested the employment of forepoles been increasing demand for umbrella arch systems with
(wooden boards), as shown in Figure 2, in order to steel and grout elements since their introduction in the
advance through to the next section (Stauffer 1906, 1970’s. An illustration of the modern configuration of spile
Richardson and Mayo 1941, Proctor and White 1946, elements with the remaining typical support elements is
Lewis 1954, and Szechy 1966). Such a support method found within Figure 3.
protected the workers, who were excavating the project
by hand, from the possibility of falling ground material due 3 PRELIMINARY DESIGN OF SPILES
to the newly exposed crown of the excavation. With the The following preliminary design for spile elements was
advancement of technology (such as hydraulic drilling in based on conservative estimations, the response of which
should always be verified in the field or through advanced
calculations (e.g. three-dimensional numerical analysis). It
is important to note that water has not been taken into
consideration for the design. If water is encountered, the
spiles would need to be designed to mitigate the water
flow through ground improvement (a different section of
the UASC, missing from Figure 1).
2
ு
1
ିଶఒ ௧ ఝ ௧ ఝ
2
ோ
[1]
ு
௦ ∙
ିఒ ௧ ఝ ௧ ఝ
ோ
Where:
3
γ: specific weight of ground [N/m ]
c: cohesion [Pa]
Rm: mean radius of the silo, which should be calculated
assuming the silo as an ellipse with the small diameter
equal to 1.5 times the unsupported span (1.5Lu), and the
large diameter being the width Dt (or excavation width) of
0.5
the tunnel: Rm = 0.5(Dt∙1.5Lu) as shown in Figure 3.
λ: horizontal pressure coefficient, which can be assumed
as λ = 1-sin ϕ
ϕ: friction angle [Deg]
H: overburden [m]
2
qs: Stress on ground surface [N/m ] (if applicable)
Figure 4. Spile capacity based on varying height of failure, cohesion, and spile spacing for a constant excavation
width, unsupported span, and friction angle.
Figure 5. Spacing and angle of installation assessment based on length between umbrella arches.
drilling (0.5% Mager and Mocivnik, 2000, to 2% John and length between umbrella arches without considering the
Mantle, 2002) will cause the spacing between the spiles required overlap, as explained in the following section.
to increase with length. As illustrated in Figure 5, the
center-to-center spacing can increase to 40cm from an 3.3 Overlap
initial 30cm after 8m of length for a 10m diameter crown The required overlap for an umbrella arch with spile
and a deviation of drilling of 1%. elements depends on the mitigation method they are
However, if the overlap of the umbrella arch spiles is employed for. Within the scope of the design
greater than 1/2 of the length it is possible to increase the recommendation presented in this paper, Spiles are
spacing, as long as the next array of spiles is offset installed to mitigate two different stabilities (Figure 1): i. to
resulting with a spile being installed between two existing increase the stability of the unsupported ground between
spiles and that the relative spacing is maintained. the support and the excavation face, and/or ii. to increase
Additionally, Figure 5 illustrates the required angle of the stability of the tunnel face. If spiles are installed solely
installation based on length and the required support to support the unsupported span, an embedment length,
clearance. Clearly, the smaller the length of the support based on empirical data are typically 1m. However,
element, the higher the required angle of installation. John additional analysis (e.g. wedge stability) needs to be
and Mattle (2002) state that the drilling equipment completed in order to quantify this length.
typically requires 40cm of clearance. If it is both the face and unsupported span that
It is important to note that the angle of installation require increased stability, the overlap can be based on
design (Figure 5) is based on a “niche” or “saw-tooth” the Rankine failure block (based on the material angle of
profile that requires enlargement of the excavation profile friction, Φ, only) as shown by the red dashed line within
as the ground breaks back to the spile elements. In some Figure 6. Figure 6 illustrates the required overlap based
cases, the ground is stable, and the requirement for on different heights of excavation. The grey zone reflects
enlarging the profile is not required. If no enlargement is the range of applicable overlap based on the empirical
needed, then the free end of the spile elements may need design recommendations within Table 1 while remaining
to be trimmed/cut/decoupled if they cannot be installed true to the definition of a spile as having a length of the
flush enough to the excavation crown. element less than the height of excavation.
However, it remains difficult to select the exact The overlap design chart (Figure 6) does not
Figure 6. Required overlap on umbrella arch based on friction angle and height of excavation.
consider any other additional pre-support, such as core- 12. Coverage angle based on the recommendation
reinforcement, nor does it consider the influence of water. within Figure 1.
Engineering judgement will be required when determining 13. Optimization of design parameters (during
the overlap of the umbrella arch composed of spiles when operation):
additional pre-support is employed. a. The center-to-center spacing can be increased if
stability of the ground between spiles is stable.
4 DESIGN METHODOLOGY This increase in spacing can be verified during
The design methodology for spiles are illustrated in Figure operation, or through numerical analysis, as
7 and are as follows: described in Oke et al. 2014b;
1. Define the unsupported span based on: b. The required overlap can be reduced if the face
a. Lattice Girder/Steel Rib spacing; and/or can be shown to be stable, but should not be
b. Rock bolt spacing. less than 1m; and
2. Based on the mode of failure, predict the height of c. If the length of the spile has increased to be
failure if spiles are not installed; greater than the height of the excavation, then
a. If failure depth is unknown, assume the greatest the element should be treated as a forepole. It
of the excavation width or height. can be more economical to employ the longer
3. Solve analytical solution of John and Mattle (2002) elements due to less set up time (Volkmann
(or other simple analytical solution) with a 50% 2016).
reduction of Terzaghi silo theory load as illustrated in
Figure 4: Unsupported Span, Lu Estimate Height of failure
a. For drill and blast operations, assume cohesion • Lattice Girder/Steel Rib spacing • If failure depth is unknown, assume the
• Rock bolt spacing greatest of the excavation width or height
of 0 due to blast damage;
b. For mechanical excavation (i.e. road header),
use the cohesion of the ground material; and Analytical solution of John and Mattle (2002) – Figure 4
c. If close to surface, estimate surface load. • 50% reduction of Terzaghi silo theory load
• Cohesion
4. Select an appropriate spile size that meets the • 0: for drill and blast operations
moment capacity. • Ground material: mechanical excavation (i.e. road header)
5. Estimate the length of the spile element based on • If close to surface, estimate surface load