Initial Risk and Complexity Assessment
Initial Risk and Complexity Assessment
Instructions on using this spreadsheet: Read eachMajor Project Requirement and select whether your project fits the low,
medium, or high risk description by choosing the correct option in the rating drop down list. After rating your project on all of the
Major Project Requirements, review your project's risk score and recommended project category at the end of the spreadsheet. Project Manager:
Rating Criteria
Reference Materials
Major Project PC: Project Charter template
Low Risk Medium Risk High Risk Rating
Requirement PP: Project Plan (for Category D Projects) template
PE - Project Excecution template
Business process change minimal change or extends moderate change significant change high PC - Project Scope Statement (Includes/Excludes), PP - Quality
systems in use Management, PE - Communications Activity, PE - Quality Log
Budget < $100K $100K - $250K > $250K high PP - Budget Allocation, Risk Register template, Risk Log template,
Project Performance Report template, PE - Budget Activity
End-user/stakeholder very involved somewhat involved little or no involvement high PP - Roles and Responsibilities, PP - Project Reviews & Assessments, PE
involvement - Communications Activity
Project manager very experienced with moderate experience or no experience with this type of Project Charter template, Project Plan template, PP - Resource Training,
has other similar project project or is new to project high Project Status Report template, Project Performance Report template,
experience similar projects
experience management Project Execution template
Number of end-users 1 to 100 101 to 1000 > 1000 high PP - End-user Training and Security Plan, PP - Project System
Performance Approach
Project delivery date derived by proper project best guess estimate none, mandated and/or critical high PP - Work Activities, PP - Schedule Allocation, PP - Major Project
management practices Milestones, PP - Critical Dates, PE - Project Activity
Texas A&M Information Technology Project Management Office Page 1 of 3 July 6, 2010
Rating Criteria
Reference Materials
Major Project PC: Project Charter template
Requirement Low Risk Medium Risk High Risk Rating PP: Project Plan (for Category D Projects) template
PE - Project Excecution template
Project requirements clearly defined and some ambiguity vague, undefined, or high PC - Project Scope Statement (Includes/Excludes), Texas Project
reasonable unreasonable Delivery Framework System Development Life Cycle Extension
Team skillset in relation to good fit moderate fit poor fit high PP - Resource Training, Team Status Report template
the project
Change management well defined & approval not well defined and/or not defined high PP - Change Management Plan, Change Request template,
process process in place verbal approval PE - Change Log
SDLC (system established, followed, and not well defined or Texas Project Delivery Framework System Development Lifecycle
development life cycle) not defined and/or not followed high
effective partially followed Extension
approach
documented but
Assumptions documented, verified, unverified and/or undocumented, unverified, high PC - Assumptions
and/or conservative aggressive and/or aggressive
Physical facilities little or no modification some modifications major modifications needed, or high PC - Project Facilities and Resources
needed needed; some existent facilities non-existent
Texas A&M Information Technology Project Management Office Page 2 of 3 July 6, 2010
Rating Criteria
Reference Materials
Major Project PC: Project Charter template
Requirement Low Risk Medium Risk High Risk Rating PP: Project Plan (for Category D Projects) template
PE - Project Excecution template
Post implementation not applicable or secured budgeted not discussed high PC - Funding Authority
support funding
Project contingency fund not applicable or secured budgeted not discussed high PC - Funding Authority
Project team roles & well defined & followed not well defined or not defined and/or not followed high PP - Roles and Responsibilities, Team Status Report template, PE -
responsibilities partially followed Communications Activity
Quality assurance established, followed, and not well defined or high PP - Quality Management, PE - Quality Activity
approach effective partially followed not defined and/or not followed
Request for Proposal Not required Required but not extensive Required and extensive high Texas A&M University Department of Procurement Services
Rollout approach pilot or single work group partial full high PP - Project Transition
Team member identified partially identified unknown high PP - Roles & Responsibilities
identification
Technological solution proven and existing proven but new locally not proven and new locally high PP - Quality Management, PE - Quality Activity
Category D Project
Texas A&M Information Technology Project Management Office Page 3 of 3 July 6, 2010