EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Control of Document
The procedure is identified and traceable to the project's updated list of Sch. "Q",
A1
quality documents. Para. 1.1
B Control of Issuance and Receiving of Welding Consumables
All personnel involved in the handling, storage, issuance and use
B1 of welding consumables are identified with their respective Best Practice
responsibilities.
The procedure has provided details on how welding consumables are
controlled by the following but not limited to:
a. Storage requirements -prior to issuance
B2 Best Practice
b. Material controller- for issuance
c. Requestor/User -- receiving of consumables
d. Return of un-used consumables
Provide a Flow chart to show the mechanism for control of welding
B3 Best Practice
consumables.
The procedure shall contain the relevant forms to use in documenting and
B4 monitoring the control of welding consumables. Best Practice
(NOTE: Suggested forms are SATR-W-2009 & SATR-W-2010 )
NOTES:
Items indicated as "Best Practice" are recommendations. Contractor, SAPMT & PID should decide and agree to adopt or provide an equivalent that
will then be incorporated in the project quality plan. On acceptance by all parties, they become mandatory for implementation.
REFERENCE DOCUMENTS:
1. SAES-W-011, Welding Requirements for On-Plot Piping, (30 October, 2002)