27.checklist For Glazing & ACP Cladding

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4
At a glance
Powered by AI
The document outlines a quality control checklist for glazing and ACP cladding projects, ensuring various construction and material aspects are properly installed and meet specifications.

The checklist ensures that the framework, materials, installation process, and finished work for glazing and windows meet specifications and quality standards. It covers aspects like proper drawings, scaffolding, bolts, panels, seals, and sign-offs.

Steps involved in glazed panel installation include using PVC shims, inserting gaskets, maintaining gaps, applying sealants, and installing glass clips and screws to securely bond the panels in the framework.

KMV PROJECTS LTD

CHECKLIST FOR QUALITY CONTROL


ACTIVITY : GLAZING AND ACP CLADDING

Project :
Location :

NOTE : Please mark as y for yes or n for no in the appropriate box or enter readings as per requirements
SL . NO. To be checked YES NO
1 Name,date and number of the drawing
Frame work
2 Latest approved Drawings at site [ ] [ ]
All the required material are as approved
3 by the Client . [ ] [ ]
Area ready with necessary plastered and
4 painted works . [ ] [ ]
5 Scaffolding and safety measures . [ ] [ ]
The MS brackets to anchor the mullions
6 are properly surface treated . [ ] [ ]
Anchor bolts are of specified type and
7 properly grouted . [ ] [ ]

PVC shims are used in between the


mullions and brackets to avoid direct
8 contact with dissimilar materials . [ ] [ ]
9 MS bolts are tightened properly [ ] [ ]

In case of vertacal glazing , the mullions


are true to plumb or in correct angle in
case of incl;ined glazing and all the
10 transoms are to level . [ ] [ ]

Gaskets are properly inserted in the


mullions and transoms prior to installing
11 the glazing panels .
The gap between the masonry and
window/structural glazing is lessthan or
12 equal to 10 mm .
Glazed Panel Installation
glass and glass processing is as per
13 approval and free from distortion. [ ] [ ]
Glass /ACP properly bonded with
structural silicone sealant and the bite is
14 as per design requirement [ ] [ ]

Bonded panel installation in the frame


work with glass clips and SS screws
maintaining a uniform gap of 12 to 15 mm
15 between the glazed panels . [ ] [ ]

Application of silicone sealant in the gap


between the glazed panels is uniform and
16 suitable backer rod is also used . [ ] [ ]

17 Glass is cleaned with mild soap solution [ ] [ ]


18 Flashing affect is as required [ ] [ ]

The gap between the masonry and


window/structural glazing unit is filled
with weather proof sealant with suitable
19 backer rod . [ ] [ ]
Aluminium Composite Panel cladding .
Main frame is properly anchored as per
20 design requirements . [ ] [ ]
21 Grids are correct [ ] [ ]
ACP protection sheet is not disturbed / or
22 damaged . [ ] [ ]
23 ACP is plane enough . [ ] [ ]
Gap between the adjucent panels is 10 to
24 12 mm . [ ] [ ]
Gap between the adjucent panels is filled
with weather proof sealant with suitable
25 backer rod . [ ] [ ]
Protection sheet is removed after proper
26 installation as specified . [ ] [ ]

Contractor's Site Engineer's signature