100% found this document useful (1 vote)
334 views11 pages

Flume Analysis

Download as xls, pdf, or txt
Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1/ 11

HYDRAULICS

Project BISLIAN (MALAKI)


POLILIO, QUEZON
Structure : Elevated Flume
& Location sta. 0 + 79.98 to 0 + 95.98 MC
L = 16 m.
span, L = 8.00 m.
no. of spans = 2.00 use : 2.00 spans @ 8.00 m.
2 Flume L = 16 m
new outlet stationing is : 0 + 96
Hydraulic Design Analysis
1. Canal Elements:
Elements Above Below
Q 0.0375 0.0375
V 0.612 0.434
A 0.0695 0.0855
b 0.40 0.40
d 0.18 0.22
D 0.575 0.575
Dc - -
R 0.099 0.1094
t 0.40 -
S 0.00184 0.000812
ss:1 - :1 - :1
n 0.015 0.015
Elevations
TB 93.23 93.04
WS 92.83 92.68
CB 92.65 92.46
NG

2. Velocity & Velocity Heads:


head avai, Ha = 0.15 m.
Flume Vel., Vf = 1.50 mps (assumed)
hva = 0.0191
hvb = 0.0096
hvf = 0.1148
0.30Δhv1 = 0.0287
0.50Δhv2 = 0.0526

3. Flume Invert Slope


Inv. F(2-3) = Y - (0.30Δhv1 + 0.50Δhv2) = 0.1087
Sf = 0.00679

4. Aprrox. Water depth "d", flume "b" & flume velocity


with Sf = 0.00679
n= 0.018 V= 2.8847 d2/3
b = 2d V= 0.0188 /d2
A = 2d2 d= 0.151
P = 4d b= 0.30 A= 0.045
R = 0.50d use : d = 0.15 Vf = 0.833
R2/3 = 0.630 d2/3 b= 0.30 hvf = 0.035

Page 1
HYDRAULICS

5. Check for Critical Condition


-To test if flume is flat enough to insure that design flow will be stable.
use: n = 0.014
d= 0.15
b= 0.30
q= Q = 0.125 cum/sec/m.
b
dc = q2 1/3
= 0.117 m
g
Vc = Q = 1.070
Ac
Rc = 0.066
Sc = 0.00897 OK, Sc > Sf

6. Computation of Headlosses
HL = inlet + friction + outlet = 0.139 OK, HL < Ha
= (0.30Δhv1 + hf + Δhv2) + 10%

7. Check Q
using b = 0.30 Qr = 0.038
d= 0.15
s= 0.00679 Qs = A.V
n= 0.018 = 0.037 OK

Page 2
8. Transition Lengths

θ1 = 27.5 θ2 = 22.5
Y1 = 1.5d Y2 = 1.5d

0.30 ba = 0.40 bf = 0.30 0.30 bb = 0.40

Y1 = 1.5d Y2 = 1.5d

water surface lines

Li = 1.00 Lf = 16 Lo = 1.00

Y1 = 1.5d + ( ba - bf ) = 0.32
2
Y2 = 1.5d + ( bb - bf ) = 0.38
2

Li = Y1 = 0.61 say 1.00 m


tan θ1
L0 = Y2 = 0.92 say 1.00 m
tan θ2

9. Elevations

Li = 1.00 Lf = 16.00 LO = 1.00

TB EL = 93.23 TB EL = 93.04

WS EL = 92.83 WS EL = 92.68

CB EL = 92.65 df = 0.15 CB EL = 92.46

Sf = 0.0067938

1 2 3 4

elev 2 = hf + elev3 elev 3 = ws el4 - ho - df


= 92.63 = 92.52
10. SUMMARY:
Adopt a flume section:
b= 0.30 m
d= 0.15 m
D= 0.40 m
Sf = 0.00679
FLOOR SLAB

Project BISLIAN (MALAKI)


POLILIO, QUEZON
Structure : Elevated Flume
& Location sta. 0 + 79.98 to 0 + 95.98 MC

Structural Design Analysis


1. Design Parameters
a. Allowable Stresses:
fc' = 211 kg/sqcm psi = 0.07045 k/scm
fc = 95 kg/sqcm psf = 4.890 k/scm
fs = 1,270 kg/sqcm
R= 16.84 kg/sqcm
k= 0.411
n= 9.30
j= 0.863
vc = 4.24 kg/sqcm
vp = 20 kg/sqcm
Es = 2,040,000 kg/sqcm
Ec = 219,340 kg/sqcm
ua (top bars) = 27 kg/sqcm for 12mm bars
20 kg/sqcm for 16mm bars
(other than = 38 kg/sqcm for 12mm bars
top bars) 28 kg/sqcm for 16mm bars

b. Unit Weights of Materials


water, ww = 1,000 kcm
natural dry earth, wne = 1,800 kcm
natural saturated earth, wse = 2,000 kcm
well compacted moist earth, wce = 2,200 kcm
submerged earth, wsub = 1,200 kcm
plain concrete, wc = 2,300 kcm
reinf concrete, wrc = 2,400 kcm
steel, ws = 7,850 kcm
angle of repose of nat dry soil, Φ = 30 O

c = (1-sin Φ)/(1+sin Φ) = 0.67


allow. soil bearing pressure, qa = 10,760 ksm
Allowable Live Loads (LL)
b<= 0.60 m. = 100 ksm
0.60 < b < 1.00 m. = 180 ksm
1.00 < b < 1.50 m. = 280 ksm
b > 1.50 m. = 400 ksm

2. Flume Design Data:


- section flowing full
- side beams to carry loads
base, b = 0.30 m. taken from the hydraulic design
depth of water, d = 0.15 m. taken from the hydraulic design
depth, D = 0.40 m. taken from the hydraulic design
floor slab thickness, tfs = 0.10 m. assumed value
side beam thickness, tb = 0.13 m. assumed value
column height, H = 3.00 m. to be provided

Page 4
FLOOR SLAB

flume/span length, L = 8.00 m. taken from the hydraulic design


number of spans = 2.00 m. taken from the hydraulic design
total flume length = 16.00 m. taken from the hydraulic design

3. Design of Floor slab:


a. Loading, Shear & Moment:
Loadings: (one-meter strip)
wt. of water, ww = 400 kg/lm use 'D'
wt. of concrete, wc = 240 kg/lm slab only
live load, LL = 100 kg/lm from allowable loads
total load, wt = 740 kg/lm

Loading combinations:
1. ww + wc = 640 kg/lm
2. LL + wc = 340 kg/lm

effective loading = 640 kg/lm

b. Shear & Moment:


i- due to water's horizontal thrust/meter
horizontal load, Ph = 80 kg/m-run
horizontal moment, Mh = 11 kg-m.

ii- due to normal loading


V= wt.L / 2, = 96 kg/m-run
M = wt.L / 12, =
2
5 kg-m.

use V = 96 kg/m-run
effective M = 11 kg-m.

iii- compute for the 'd' reqd :


due to moment:
d= M 1/2
,= 0.80 cm
Rb
due to shear:
d= V ,= 0.23 with t fs = 10 cm.
va.b effective 'd' = tfs - 2.5
the greater value of 'd' reqd = 0.80 = 7.50 cm.
d' (from the assumed t fs) = 7.50
use 'd' = 7.50 cm

iii- compute for steel reinf:


@ midspan @ support
As = M ,= 0.13 sqcm 0.13
fsjd
using 12mm Φ bars, As = 1.13 sqcm 1.13
spacing req'd = 872 cm 872
use spacing = 45 cm o.c. 45
temp bars= 0.002bt, = 2.00 sqcm 2.00

Page 5
FLOOR SLAB

using 10mm = 0.785 0.785


spacing req'd = 39 39
use spacing = 30 30

For the floor slab:


thickness = 10 cm.
reinf.:
main - 12mm bars @ 45 cm o.c.
temp bars - 10mm bars @ 30 cm o.c.

Page 6
SIDE BEAMS

Project BISLIAN (MALAKI)


POLILIO, QUEZON
Structure : Elevated Flume
& Location sta. 0 + 80 to 0 + 95.98 MC

Structural Design Analysis


4. Design of Side Beams:
a. Loading, Shear & Moment:
Loadings: (form the floor slab)
loading from floorslab = 192 kg/lm side beams:
side beams, wsb = 312 D= 0.50 m
504 t sb = 0.13
load per beam, w = 252 kg/m

b. Shear & Moment:


V = wL / 2, = 1,008 kg. flume/span length, L = 8.00 m
M = wt.L / 8, =
2
2,016 kg-m.

d' required: d' supplied:


due to moment:
d= M 1/2, = 30 cm ds = 40 cm
Rb
due to shear:
d = V , = 18 cm
vc.b
adopt 'd' reqd = 30 cm OK, < ds adopt d = 40 cm

c. Compute for steel reinf:


@ midspan @L/4
As = M ,= 4.60 3.45
fsjd
using 10 mm, As = 0.79

no of pieces = 7 5
Еo.n = 21.54
d. Check for Shear:
va = V ,= 1.94 use: min 10mm U stirrups, sp. 20 cm oc
bd min U stirrups- 10mm
v' = va - vc, = (2.30) spaced- 30 com oc
try a 10 mm Ao = 1.571 or d/2 = 20
spacing, s = Ao.fs , = -
v'.b For the side beams:
use 10mm stirrups @ 0 cm tsb = 0.13 m.
d= 0.40 m.
d. Check for Bond: D= 0.50 m.
u actual = V ,= 1.36 ok < Ua main reinf: 7 pcs - 10 mm.
Еo.jd stirrups: 10mm U stirrups @ 20 cm oc

Page 7
FLUMESEAT, COLUMNS & FOOTINGS

Project BISLIAN (MALAKI)


POLILIO, QUEZON
Structure : Elevated Flume
& Location sta. 0 + 80 to 0 + 95.98 MC

Structural Design Analysis


5. Design of Flume Seat:
a. Loadings:
side beamsloads, V, = 1,008 kg. acting at 0.04 m., from column face
flume seat, wfs = 37 kg. Assume flume seat size:
load/length = 1,045 kg. width, w = 0.25 m.
depth, D = 0.30
total load = 2,090 kg. length, L = 0.21
Assume column size:
b. Shear & Moment: longitudinal direction, c = 0.20
V= 1,045 kg. transverse direction, w = 0.35
M= 44 kg-m. length, L = 8.00

d' required: d' supplied:


due to moment:
d= M 1/2, = 3 cm ok, dreqd < ds ds = 22 cm
Rb
due to shear:
d= V ,= 10 cm ok, dreqd < ds
vc.b
adopt 'd' reqd = 9.9 cm OK, < ds adopt d = 22 cm

c. Compute for steel reinf:


As = M , = 0.19 sqcm
fsjd
using 12 mm, As = 1.13 Еo.n = 4.39 cm.
no of pieces = 1

d. Check for Shear:


va = V , = 1.93 use: min 10mm U stirrups, sp. 11 cm oc
bd

v' = va - vc, = (2.31)


try a 10 mm Ao = 1.571 min U stirrups- 10mm
spacing, s = Ao.fs , =(34) spaced- 30 com oc
v'.b or d/2 = 11
use 10mm stirrups @ -34.4855 cm (whichever is lesser)

d. Check for Bond:


u actual = V ,= 1.180 ok < Ua
Еo.jd

5. Design of Columns:
a. No Sideway, Single Curvature
Long Column : 60 < h/r > 100
Short Column : h/r <= 60

Page 8
FLUMESEAT, COLUMNS & FOOTINGS

Allowable Column Load, Pa = 0.85('0.25f'cAg + Asfs) - short column = 13,023


Allowable Column Load, Pa = Pa(short)(1.07 - 0.008h/r) - long column = 8,725
p/g = As/Ag (1-4%)

b. Loadings:
side beamsloads,(P=2V), = 4,032 kg.
flume seat, wfs = 74 kg.
Total Col Load, P = 4,106 kg.
try:
column size :
width(longitudinal), wl = 20 cm
width(transverse), wt = 35 cm
h= 3 m.
c. reinforcements:
try : 6 pcs 16 mm- RSB
Asfs = 15,321 kg
p/g = 1.72 ok
h/r = 50.00 short col < 60
Allowable Column Load, Pa = 8,725 kg. ok, Pa > P

d. ties: column:
use: 10 mm width(longitudinal), wl = 20 cm
spacing, s1 = 48 cm width(transverse), wt = 35 cm
spacing, s2 = 38 reinf: 6 pcs 16 mm- RSB
spacing, s3 = 30 ties: 10 mm @ 30 cm

6. Design of Footing:
a. Loadings:
Column Load, CL = 4,516
Footing Load, FL = 5,194
Allow. Bearing Pressure, qa = 10,760
A reqd = 0.48
transverse dir, c1 = 1.06 try: c1 = 1.50 m
longitudinal dir, c2 = 0.46 c2 = 0.90 m
A supplied, Asup = 1.35
check actual q, qact =
3,345 ok
b. Moments & footing thickness, "d", T
moment(at column face), M = 498 kg-m
d= 4.44 cm
add: 20 to 25 cm) : 29.44
use d = 10 cm.
Tf = 20 cm.
footing weight = 648 ok, actual < assumed
c. Reinforcements:
short dir.(longitudinal) long dir.(transverse)
M= 307 498
As = 2.80 4.54
try: 16 mm: no of pcs = 2 3
use: 16 mm: no of pcs = 4 3

d. Check for Shear:

Page 9
FLUMESEAT, COLUMNS & FOOTINGS

Shear Bond Punching Shear


-('d' dist fr col face) -( @ col face) -(col dim + 'd')
x= 0.48 m. 0.58 m. 0.45 m.
y= 0.25 m. 0.35 m. 0.30 m.
V= 1,430 kg 1,731 kg 4,065 kg
v actual = 1.59 kscm 12.25 kscm 5.42 kscm
OK OK OK

SUMMARY:
Floor Slab:
thickness = 10 cm. main reinf - 12mm @ 45 cm o.c.
temp bars - 10mm @ 30 cm o.c.
Side Beams:
tsb = 0.13 m. main reinf: 7 pcs - 10 mm.
d= 0.40 m. stirrups: 10mm U stirrups @ 20 cm oc
D= 0.50 m.
Flume Seat:
w= 0.25 m. main reinf: 1 pcs - 12 mm.
d= 0.22 m. stirrups: 10mm U stirrups@ 11 cm oc
D= 0.30 m.
Column:
width(longitudinal), wl = 20 cm reinf: 6 pcs 16 mm- RSB
width(transverse), wt = 35 cm ties: 10 mm @ 30 cm
Footing:
transverse dir, c1 = 1.50 m. with 3 pcs 16 mm
longitudinal dir, c2 = 0.90 m. with 4 pcs 16 mm
d= 10 cm
Tf = 20 cm

Page 10
LONGITUDINAL DIRECTION

TRAVERSE DIRECTION

Number

Pier Width: Longitudinal, PL = 0.20 1.00


Transverse, PT = 0.35 1.00
Pier Height = 3.00 1.00

Footing Width Longitudinal = 0.90 1.00


Transverse = 1.50 1.00 0.25 PL = 0.20 0.90 (longitudinal dir, c2)
ftg. Thickness = 0.20 1.00

Backfill Ht.= 1.50 1.00

span, L = 8.00 m
flume b = 0.30
floorslab thickness = 0.10
side wall: height = 0.40 2
side wall: thickness = 0.13
depth of water = 0.15 PT = 0.35
flume seat(bracket), trnsvrse = 0.76
longitudinal = 0.25 transverse dir, c1 = 1.50
depth = 0.30
0.13 0.30 0.13

0.40
0.15

13.91
0.06 0.10

0.30

0.76

h= 3.00

heel toe
0.20

1.50

Foundation Reaction @ toe


= 13.91 Tons/Sq. M.
Foundation Reaction @ heel
= 0.06 tsm

Revised detailed design

You might also like