Flume Analysis
Flume Analysis
Flume Analysis
Page 1
HYDRAULICS
6. Computation of Headlosses
HL = inlet + friction + outlet = 0.139 OK, HL < Ha
= (0.30Δhv1 + hf + Δhv2) + 10%
7. Check Q
using b = 0.30 Qr = 0.038
d= 0.15
s= 0.00679 Qs = A.V
n= 0.018 = 0.037 OK
Page 2
8. Transition Lengths
θ1 = 27.5 θ2 = 22.5
Y1 = 1.5d Y2 = 1.5d
Y1 = 1.5d Y2 = 1.5d
Li = 1.00 Lf = 16 Lo = 1.00
Y1 = 1.5d + ( ba - bf ) = 0.32
2
Y2 = 1.5d + ( bb - bf ) = 0.38
2
9. Elevations
TB EL = 93.23 TB EL = 93.04
WS EL = 92.83 WS EL = 92.68
Sf = 0.0067938
1 2 3 4
Page 4
FLOOR SLAB
Loading combinations:
1. ww + wc = 640 kg/lm
2. LL + wc = 340 kg/lm
use V = 96 kg/m-run
effective M = 11 kg-m.
Page 5
FLOOR SLAB
Page 6
SIDE BEAMS
no of pieces = 7 5
Еo.n = 21.54
d. Check for Shear:
va = V ,= 1.94 use: min 10mm U stirrups, sp. 20 cm oc
bd min U stirrups- 10mm
v' = va - vc, = (2.30) spaced- 30 com oc
try a 10 mm Ao = 1.571 or d/2 = 20
spacing, s = Ao.fs , = -
v'.b For the side beams:
use 10mm stirrups @ 0 cm tsb = 0.13 m.
d= 0.40 m.
d. Check for Bond: D= 0.50 m.
u actual = V ,= 1.36 ok < Ua main reinf: 7 pcs - 10 mm.
Еo.jd stirrups: 10mm U stirrups @ 20 cm oc
Page 7
FLUMESEAT, COLUMNS & FOOTINGS
5. Design of Columns:
a. No Sideway, Single Curvature
Long Column : 60 < h/r > 100
Short Column : h/r <= 60
Page 8
FLUMESEAT, COLUMNS & FOOTINGS
b. Loadings:
side beamsloads,(P=2V), = 4,032 kg.
flume seat, wfs = 74 kg.
Total Col Load, P = 4,106 kg.
try:
column size :
width(longitudinal), wl = 20 cm
width(transverse), wt = 35 cm
h= 3 m.
c. reinforcements:
try : 6 pcs 16 mm- RSB
Asfs = 15,321 kg
p/g = 1.72 ok
h/r = 50.00 short col < 60
Allowable Column Load, Pa = 8,725 kg. ok, Pa > P
d. ties: column:
use: 10 mm width(longitudinal), wl = 20 cm
spacing, s1 = 48 cm width(transverse), wt = 35 cm
spacing, s2 = 38 reinf: 6 pcs 16 mm- RSB
spacing, s3 = 30 ties: 10 mm @ 30 cm
6. Design of Footing:
a. Loadings:
Column Load, CL = 4,516
Footing Load, FL = 5,194
Allow. Bearing Pressure, qa = 10,760
A reqd = 0.48
transverse dir, c1 = 1.06 try: c1 = 1.50 m
longitudinal dir, c2 = 0.46 c2 = 0.90 m
A supplied, Asup = 1.35
check actual q, qact =
3,345 ok
b. Moments & footing thickness, "d", T
moment(at column face), M = 498 kg-m
d= 4.44 cm
add: 20 to 25 cm) : 29.44
use d = 10 cm.
Tf = 20 cm.
footing weight = 648 ok, actual < assumed
c. Reinforcements:
short dir.(longitudinal) long dir.(transverse)
M= 307 498
As = 2.80 4.54
try: 16 mm: no of pcs = 2 3
use: 16 mm: no of pcs = 4 3
Page 9
FLUMESEAT, COLUMNS & FOOTINGS
SUMMARY:
Floor Slab:
thickness = 10 cm. main reinf - 12mm @ 45 cm o.c.
temp bars - 10mm @ 30 cm o.c.
Side Beams:
tsb = 0.13 m. main reinf: 7 pcs - 10 mm.
d= 0.40 m. stirrups: 10mm U stirrups @ 20 cm oc
D= 0.50 m.
Flume Seat:
w= 0.25 m. main reinf: 1 pcs - 12 mm.
d= 0.22 m. stirrups: 10mm U stirrups@ 11 cm oc
D= 0.30 m.
Column:
width(longitudinal), wl = 20 cm reinf: 6 pcs 16 mm- RSB
width(transverse), wt = 35 cm ties: 10 mm @ 30 cm
Footing:
transverse dir, c1 = 1.50 m. with 3 pcs 16 mm
longitudinal dir, c2 = 0.90 m. with 4 pcs 16 mm
d= 10 cm
Tf = 20 cm
Page 10
LONGITUDINAL DIRECTION
TRAVERSE DIRECTION
Number
span, L = 8.00 m
flume b = 0.30
floorslab thickness = 0.10
side wall: height = 0.40 2
side wall: thickness = 0.13
depth of water = 0.15 PT = 0.35
flume seat(bracket), trnsvrse = 0.76
longitudinal = 0.25 transverse dir, c1 = 1.50
depth = 0.30
0.13 0.30 0.13
0.40
0.15
13.91
0.06 0.10
0.30
0.76
h= 3.00
heel toe
0.20
1.50