BLDG Est Guide
BLDG Est Guide
BLDG Est Guide
LOCATION:
OWNER:
ARCHITECT:
I SITE PREPARATION
a. Building Layout 0.32 20,580.00
b. Excavation 1.09 70,732.50
II SITE DRAINAGE 0.94 61,115.00
III REINFORC ED CONCRETE
a. Forms and Scaffoldings 6.60 427,776.67
b. Concrete Works 7.38 478,462.21
c. Reinforcing Steel Bars 24.66 1,598,460.50
IX CARPENTRY WORKS
2.95 191,010.00
X PLUMBING WORKS
a. Fixtures and sanitary lines 1.52 98,790.00
b. Tiles and Trims 1.41 91,275.00
XI ELECTRICAL WORKS 4.83 313,100.00
XII PAINTING WORKS 4.78 310,000.00
XIII MISCELLANEOUS ITEMS 0.76 49,130.00
REMARKS: TOTAL PERCENTAGE 100.00
b. excavation
U. COST AMOUNT
II. SITE DRAINAGE
a. down spout
b. drainage
22 sets catch basin 450.00 9,900.00
93 lnmt storm drain 8" diameter concrete pipes 350.00 32,550.00
c. septic tank
3.50 wd x 5.00L x 3.50depth
( see CHB works)
360 pcs 2" x 3" x 14" horizontal 2,520.00 bdft 28.00 70,560.00
240 pcs 2" x 3" x 14" vertical 1,680.00 bdft 28.00 47,040.00
180 pcs 2" x 3" x 14" diagonal brace 1,260.00 bdft 28.00 35,280.00
240 pcs 2" x 3" x 14" suspended slab 1,680.00 bdft 28.00 47,040.00
80 pcs 2" x 3" x 14" base for beams 560.00 bdft 28.00 15,680.00
60 pcs 2" x 3" x 14" forms for columns 420.00 bdft 28.00 11,760.00
250 pcs 2" x 2" x 14" forms 1,166.67 bdft 28.00 32,666.67
20 kegs assorted common wire nail 1,200.00 24,000.00
250 pcs 1/2" thk plywood 575.00 143,750.00
b. conrete works
Breakdown of cement
U. COST AMOUNT
2,238.79 bags portland cement 168.00 376,117.35
127.93 cbmt screened sand 200.00 25,586.21
191.90 cbmt 3/4" crushed stone 400.00 76,758.64
sub total 478,462.21
U. COST AMOUNT
c. Reinforcing steel bars
FOUNDATION WORKS
315 pcs 20mm x7.50 mtrs matting for columns 591.00 186,165.00
360 pcs 20mm x 9.00 mtrs C-1 710.00 255,600.00
48 pcs 20mm x 9.00 mtrs C-1 second floor 710.00 34,080.00
1,800 pcs 10mm x 6.00 mtrs ties of column 98.00 176,400.00
168 pcs 16mm x 7.50 mtrs tie beams 379.00 63,672.00
260 pcs 10mm x 6.00 mtrs tie beam stirrups 98.00 25,480.00
GROUND FLOOR SLAB
456 pcs 10mm x 6.00 mtrs slab on fill 98.00 44,688.00
SECOND FLOOR FRAMIMG
16 pcs 20mm x 10.50 mtrs line G: B2 main bars 829.00 13,264.00
4 pcs 16mm x 10.50 mtrs B2 stiffiner 531.00 2,124.00
36 pcs 20mm x 10.50 mtrs line F B1 main bars 829.00 29,844.00
8 pcs 20mm x 7.50 mtrs B2 main bars 592.00 4,736.00
6 pcs 16mm x 10.50 mtrs B1, B2 stiffiner 637.00 3,822.00
54 pcs 20mm x 10.50 mtrs line D B1 main bars 829.00 44,766.00
6 pcs 16mm x 9.00 mtrs B1 stiffiner 531.00 3,186.00
8 pcs 20mm x 7.50 mtrs line B B2 main bars 592.00 4,736.00
2 pcs 16mm x 7.50 mtrs B2 stiffiner 378.00 756.00
16 pcs 20mm x 9.00 mtrs line A B2 main bars 710.00 11,360.00
4 pcs 16mm x 9.00 mtrs B2 stiffiner 531.00 2,124.00
16 pcs 20mm x 9.00 mtrs line 1 B2 710.00 11,360.00
4 pcs 16mm x 9.00 mtrs B2 stiffiner 531.00 2,124.00
30 pcs 20mm x 9.00 mtrs line 2,4,6,8,10 - SB 1 710.00 21,300.00
14 pcs 16mm x 9.00 mtrs stiffiner 531.00 7,434.00
8 pcs 20mm x 9.00 mtrs line 3,9 SB 1 710.00 5,680.00
6 pcs 16mm x 9.00 mtrs stiffiner 531.00 3,186.00
48 pcs 20mm x 7.50 mtrs line 5,7 B2 591.00 28,368.00
16 pcs 16mm x 7.50 mtrs stiffiner 379.00 6,064.00
12 pcs 20mm x 7.50 mtrs SB 2 591.00 7,092.00
4 pcs 16mm x 7.50 mtrs stiffiner 379.00 1,516.00
600 pcs 10mm x 6.00 mtrs beam stirrups 98.00 58,800.00
1440 pcs 12mm x 7.50 mtrs suspended slab 214.00 308,160.00
ROOF SLAB
32 pcs 20mm x 7.50 mtrs line 5,7,D B1 591.00 18,912.00
10 pcs 16mm x 7.50 mtrs stiffiner 379.00 3,790.00
16 pcs 20mm x 9.00 mtrs line B,F 710.00 11,360.00
6 pcs 16mm x 9.00 mtrs stiffiner 531.00 3,186.00
40 pcs 20mm x 7.50 mtrs SB, CB 591.00 23,640.00
240 pcs 10mm x 6.00 mtrs roof beam stirrups 98.00 23,520.00
432 pcs 12mm x 7.50 mtrs roof suspended slab 213.00 92,016.00
U. COST AMOUNT
7,371.00 pcs 6" concrete hallow blocks 8.50 62,653.50
20,995.00 pcs 4" concrete hallow blocks 7.50 157,462.50
1,289.36 bgs portland cement 168.00 216,613.09
1,200.10 pcs 10mm x 6.00 mtrs def. Bars 98.00 117,609.80
147.36 cbmt screened sand 200.00 29,471.17
30.00 kls #16 tie wire 45.00 1,350.11
U. COST AMOUNT
V. PLASTERING WORKS
1,454.67 bags portland cement 168.00 244,384.00
124.69 cbmt washed sand 200.00 24,937.14
U. COST AMOUNT
VI. TILE WORKS
336 sqmt floor tiles at ground floor 550.00 184,800.00
336 sqmt floor tiles at second floor 450.00 151,200.00
40 sqmt stairs and landing 550.00 22,000.00
75 sqmt bricks 350.00 26,250.00
238 sqmt floor tiles - Phase 2 550.00 130,900.00
U. COST AMOUNT
VIII. FENESTRATIONS
a. Door panels (see schedule of doors)
2 sets 2.00 x 2.80 analok door D-1 19,600.00 39,200.00
4 sets 1.20 x 2.40 flush door D-2 12,500.00 50,000.00
9 sets .80 x 2.10 flush door D-3 3,500.00 31,500.00
9 sets .70 x 2.10 flush door D-4 2,500.00 22,500.00
6 sets .70 x 2.10 flush door -Phase 2 D-4 2,500.00 15,000.00
b. Door Jambs
540 lnft 2" x 6" tanguile door jambs 75.00 40,500.00
c. Accessories
27 prs 3-1/2" x 3-1/2" loose pin hinges 90.00 2,430.00
9 sets cylinder lockset 650.00 5,850.00
U. COST AMOUNT
VII. THERMAL PROTECTION
PHASE - 2
285 sqmt Rigid steel roof framing 1,750.00 498,750.00
U. COST AMOUNT
IX. CARPENTRY WORK
a.celing woks
356 pcs 2" x 3" x 14" ceiling joist 2,492.00 bdft 28.00 69,776.00
456 pcs 2" x 2" x 14" nailers 2,128.00 bdft 28.00 59,584.00
165 pcs 1/4" thk marine plywood 330.00 54,450.00
6 kegs assorted common wire nail 1,200.00 7,200.00
b. cabinets
b. Fixtures
d. Service Connections
1 set meter base and meter 25,000.00 25,000.00
ls service connection
AMOUNT
XII. PAINTING WORKS
a. Concrete Surface 145,000.00
AMOUNT
XIII. MISCELLANEOUS ITEMS
12 ltrs clordaine anti anay 480.00 5,760.00
20 lnmt stair railings 1,750.00 35,000.00
279 pcks sahara water proofing 30.00 8,370.00
COST BREAKDOWN
REMARKS