STD 128 PDF
STD 128 PDF
OISD-STD-128
FOR RESTRICTED CIRULATION ONLY
INSPECTION
OF
UNFIRED PRESSURE VESSELS
OISD - STANDARD-128
First Edition, November 1988
Amended edition, August, 1999
Revised edition October, 2010
I
_______________________________________________________________________________________
OISD–STD-128
First Edition, November, 1988
Amended edition, August, 1999
Revised edition October, 2010
FOR RESTRICTED CIRULATION ONLY
INSPECTION
OF
UNFIRED PRESSURE VESSELS
Prepared by
FUNCTIONAL COMMITTEE ON
INSPECTION OF UNFIRED PRESSURE VESSELS
II
_______________________________________________________________________________________
NOTE
OISD publications are prepared for use in the Oil and gas
industry under Ministry of Petroleum and Natural Gas. These are the
property of Ministry of Petroleum and Natural Gas and shall not be
reproduced or copied and loaned or exhibited to others without written
consent from OISD.
III
_______________________________________________________________________________________
FOREWORD
The Co-ordinator,
Functional Committee on
“Inspection of Unfired Pressure Vessels,
Oil Industry Safety Directorate,
7th Floor, “New Delhi House”
27, Barakhamba Road,
New Delhi – 110 001
Website : www.oisd.gov.in
IV
_______________________________________________________________________________________
V
_______________________________________________________________________________________
VI
_______________________________________________________________________________________
CONTENT
S. N. SECTION PAGE
1.0 Introduction 01
2.0 Scope 01
3.0 Definition 01
4.0 Role of Inspection 02
5.0 Stages of Pressure Vessel Inspection 02
6.0 Frequency of Inspection 03
7.0 Inspection Checks 05
8.0 Inspection During Maintenance 16
9.0 Re-rating of pressure vessels 16
10.0 Documentation 17
11.0 References 18
ANNEXURES:
I A Typical Pre-commissioning Check List 19
II A Typical Checklist for In service Inspection 21
III Guidelines on Pressure Testing of Pressure Vessels 23
IV Corrosion Rate and Remaining Life Calculation 25
V Inspection Documentation Cards (Forms) 26
VI Inspection of Welding 31
VII Hydrogen Blisters-inspection, Evaluation and Repair of 34
VIII Inspection Tools 36
IX Likely Areas of Metal Deterioration 37
VII
OISD-128 1
__________________________________________________________________________________________
5.2.6 Special attention shall be given to iii) Out of service for more than 6
pressure vessels in humid area, areas months
near to cooling tower and in areas
where corrosive chemical vapours are The duration of hydrostatic
present to check for external corrosion pressure testing shall be in line
and thickness reduction due to with the applicable code and not
exposure to corrosive stream. less than 30 minutes after
stabilization.
5.2.7 Whenever there is plant upset, those
pressure vessels which experience b) Austenitic stainless steel pressure
excessive pressure / temperature shall vessel shall be hydrostatic
be externally inspected immediately. pressure tested using water with
chloride content less than 50
5.3 OUT OF SERVICE PPM.
(COMPREHENSIVE) INSPECTION
c) Stress due to hydrostatic pressure
5.2.8 The out of service inspection of testing shall not exceed 90% of
pressure vessel shall be carried out to the yield stress of the material of
assess the integrity of the equipment, construction of the pressure
condition of internals and to determine vessel.
the corrosion rate to estimate the
remaining life. The inspection strategy/ d) Hydrostatic pressure test shall not
program shall be designed based on be carried out at metal
the likely hood and consequences of temperatures near the ductile-to-
damages because of the prevailing brittle transition temperature of the
internal service/ environment material.
conditions. The appropriate NDT
techniques such as Liquid penetrant e) Wherever the foundation,
test (LPT), Magnetic particle test internals like column trays and
(MPT), Ultrasonic test (UT), supports of the pressure vessel
Radiography etc. shall be deployed for are not designed for hydrostatic
condition assessment. load, suitable NDT or pneumatic
test shall be considered with due
5.2.9 The thickness for all major components approvals.
(shells, heads, and cone sections) and
a representative sample of vessel The guidelines on pressure testing
nozzles shall be measured, remaining of pressure vessels are given in
life and next inspection interval shall be Annexure III.
calculated for the limiting component.
Adequate number of thickness 6.0 FREQUENCY OF INSPECTION
measurement locations (TMLs) shall
be defined to establish general and The pressure vessel inspection
localized corrosion rates in different frequency regime shall be arrived at
sections of the vessel. so as to provide adequate
information, necessary to declare
5.2.10 Hydrostatic Pressure Testing that all the sections/ components of
the pressure vessel, including the
a) Hydrostatic pressure testing shall mountings, are safe to operate until
be carried out for pressure the next scheduled inspection.
vessels as per statutory
requirements and also under the The following factors shall be
following conditions; considered while arriving at the
inspection frequency regime for
i) After any major alteration / re- pressure vessels:
rating / replacement/ exposure
to fire. a) The nature of the fluid handled
along with its pressure and
ii) After chemical cleaning temperature
involving metal loss
OISD-128 4
__________________________________________________________________________________________
6.2 OUT OF SERVICE INSPECTION The corrosion rate and remaining life
shall be calculated as detailed in
The frequency of out of service Annexure-IV
inspection shall be determined based
on history, corrosiveness of the fluid 6.3 SPECIFIC INSPECTIONS
handled and operating conditions. The
periods between these inspections i) Pressure vessels installed in new
shall not exceed one half of estimated process plants shall be inspected
remaining life of the vessel based on based on licensor
corrosion rate. However, the interval of recommendations or within first 2
out of service inspections shall not years of operation to assess the
exceed five years. internal conditions at select
locations.
OISD-128 5
__________________________________________________________________________________________
b) Bolts and nuts shall be checked d) Check for full length engagement
for evidence of crevice corrosion. of thread connections.
I) Fluidized Catalytic Cracking Unit iii) Dip leg along with flapper/ trickle
(FCCU) valve shall be inspected for
erosion/ perforations/ plugging.
a) Reactor/ Regenerators/
Strippers of FCCU iv) Other internals like deflector
plate lining, grid cone lining and
i) In catalytic Reactors and riser pipe shall be checked for
Regenerators, the supporting bars erosion.
for internal equipment such as
cyclones shall be closely v) Stripper shell and steam nozzle
examined for erosion, crack etc. shall be inspected for erosion.
The cyclone assemblies, air
distributor, disengaging device, vi) Condition of the lining in the feed
internal abrasion resistant lining riser pipe shall be checked.
etc. are susceptible to catalyst
erosion and shall be closely vii) Inspection of steam and catalyst
examined. feed injections piping and
nozzles shall be carried out.
ii) Welding of the air grid supporting
rings shall be checked for erosion viii) In the plenum chamber, shell
and cracking. Out of roundness shall be inspected for erosion
or bulging may be evaluated by and thickness measurements
measuring the diameter of the shall be taken.
vessel at the cross section of
maximum deformation and ix) In the anti-coking chamber,
comparing it with the original peripheral holes shall be
diameter. If the bulging is at checked for plugging.
intervals, the measurement can
be done by dropping a plumb line x) Cyclone supports should be
and taking the measurements at checked for erosion/cracking.
selected intervals. This shall also
reveal the contour of the shell. xi) Dissimilar weld joints exist in the
riser pipe these should be
b) REACTORS checked for cracks.
xiv) The slide valve internals shall be ix) Nozzles in the air distributor
examined for erosion and proper assembly shall be checked for
operation. internal erosion. Grid plate shall
be inspected for cracks or
perforations. Overflow well and
seal boxes shall be checked for
c) REGENERATOR erosion and perforations.
The regenerator vessels are x) Lining of the cone below the air
normally provided with internally grid shall be inspected for
erosion resistant insulating cast- possible refractory damage.
able refractory. Based on the in
service thermography survey, the xi) Auxiliary burner tips, air door and
identified areas of possible the pilot shall be inspected
refractory damage shall be visually.
internally inspected.
d) ORIFICE CHAMBER/ DOUBLE
The additional specific checks for DISC SLIDE VALVE (DDSV)
regenerator are as follows;
i) The orifice chamber shell shall be
i) The refractory lining shall be inspected for erosion and bulging
checked for erosion, spalling, at baffle locations.
cracking etc.
ii) The areas just after the Double
ii) Particular attention should be Disc Slide Valve (DDSV) shall be
given just near big manway and inspected critically.
in the areas of possible
turbulence. iii) The holes/ sleeves on the grid/
baffle plate shall also be
iii) Aeration connections, thermo- examined for increased diameter
wells and trickle valves shall be due to erosion.
inspected for possible erosion
and damage. iv) The DDSV internals shall be
examined for erosion and proper
iv) Cyclone assembly shall be operation.
inspected at locations like inlet
horns, volute, dust bowl, gas II) HYDROCRACKER/
risers etc for erosion. HYDROTREATER
v) Dip leg along with flapper/ trickle Reactor / pressure vessels including PSA
valve shall be inspected for (pressure swing absorber) vessels are
erosion/ perforations/ plugging. subjected to following degradation
mechanisms;
vi) Lining of the plenum chamber
and stack above the plenum a) Metallurgical Degradation
chamber shall be inspected. If
the plenum chamber is of SS i) High Temp. Hydrogen attack
material, the bimetal weld joint
ii) Temper Embrittlement
between chamber and shell shall
be examined from inside. iii) Sigma phase formation /
Sensitization of class 300 SS
vii) Steam rings shall be inspected
for oxidation/ erosion. iv) High temperature Stress Rupture
b) Corrosion Degradation
OISD-128 13
__________________________________________________________________________________________
Typical checks for reactor components Injection points including small bore
are as given below; piping and instrument tapings are to be
carefully examined using B-scan or
radiographic inspection techniques.
S.N. Component Inspection
Techniques III) MOUNDED STORAGE VESSEL
1 Tray & Catalyst Visual, Liquid a) All the weld joints of the vessel shall be
support cone penetrant examined through NDT techniques like
attachment welds Testing Wet Fluorescent Magnetic Particle
method, Dye Penetration Test
hardness survey, and ultrasonic flaw
2 Wire Mesh Visual detection to ensure the integrity of the
joints.
3 Thermo well Visual, Liquid b) The wall thickness of the vessel shall
penetrant be measured ultrasonically.
Testing
c) In case of any indication of defect or
metal loss, the mound cover of the
4 Gasket Ring Liquid vessel shall be removed to expose
Groove penetrant the outer surface for necessary
Testing examination from outside, if required.
IV) RUBBER LINED PRESSURE The safety valves and safety relief
VESSEL valves on the pressure vessels should
be periodically inspected and tested as
The rubber lining shall be inspected for per OISD-Std-132.
mechanical damage, holes, cracking,
blistering, bonding etc. Holes in the 8.0 SPECIFIC INSPECTIONS,
lining are evidenced by bulging. A REPAIRS AND CHECKS
holiday detector should be used to
thoroughly check the lining for leaks AFTER REPAIRS
and holiday. Care must be taken so
that the test voltage does not approach 8.1 WELD BUILD UP
a value that might puncture the lining.
The test voltages shall be selected In pressure vessels where metal loss
based on the thickness of the rubber observed is limited to a small localized
lining. Inspection of rubber lined area and the remaining thickness is
vessels shall be carried out in line with less than the minimum required
IS-4682-Part-I. thickness, repair by local weld filling
may be required to build up the
V) RIVETED VESSELS thickness. The area to be repaired
should be marked and should be
Riveted vessels shall be examined for cleaned thoroughly. The area is filled
tightness of rivets, soundness of with weld deposits, in a staggered
caulking and seal welds and other manner to avoid warping, with suitable
conditions. For the insulated riveted electrodes matching with the base part.
vessel, insulation should be removed After weld build up, the area should
from all joints for checking as per inspected for cracks and defects.
statutory requirements. Thickness shall be measured
ultrasonically to check whether
7.3 MINIMUM/ RETIRING THICKNESS requisite thickness has been obtained.
Preheating and post weld heat
The limiting or retiring thickness of any treatment whenever required should be
pressure vessel shall be determined as carried out as applicable.
per the applicable design code to
which it has been manufactured. 8.2 NOZZLE REPLACEMENT
Thinned and deteriorated nozzles shall times the thickness of base metal
be replaced. New nozzles fabricated thickness measured from weld. The
out of piping having thickness PWHT shall be monitored by suitable
equivalent to original nozzles are number of thermo-couples.
installed. Welding including preheating
and post weld heat treatment shall be 8.3 PARTIAL REPLACEMENT OF SHELL
carried out as per approved procedure. PLATES AND DOMES
The weld joints shall be checked
visually and also by dye penetrant test. Some portion of shell plates and
Defects, if any, shall be repaired. The domes of pressure vessels may get
leaks from the nozzle welds shall be thinned due to corrosion or erosion.
checked by pressurising with air at a The thickness of the affected area may
pressure 1.03 kg/cm2 through the tell- reach the retiring thickness. In such
tale hole provided in the reinforcing cases, partial replacement of shell
pad. The integrity of repaired weld shall plate or dome is carried out as weld
be checked either by pressurizing the repair of the big area is not practically
entire vessel or by pressurizing local possible. The affected portion is cut
area. In some cases where the area is and removed. The new plates
accessible from inside, a box may be matching with the metallurgy and
provided externally around the nozzle. thickness of the original plate is made
The box is pressurised with water to available.
the test pressure of the column/vessel
calculated by applicable code. The The edge preparation shall be done as
weld joints and HAZ are checked for per the code requirement by grinding.
possible leaks. If any defect is found in The prepared edges shall be checked
the weld joints, these are gouged, re- for cracks, flaws and defects by
welded and retested. magnifying glass and by using dye
penetrant kit. The welding procedure
Pre heat and controlled deposition is developed for welding the old and
welding is to be considered in lieu of new piece as per the relevant code.
post weld heat treatment where PWHT The welding may be performed either
is unadvisable or mechanically from inside or outside. The root run
unnecessary. Prior to use any shall be thoroughly inspected for
alternative method a metallurgical cracks and flaws. After completing the
review needs to be conducted to find welding from one side, the other side is
out whether proposed alternative is chipped and grounded. Before welding
suitable for application. The review again, the groove is checked for cracks
should consider reason for original and defects. Welding is then
PWHT, susceptibility to cracking, completed from the other side.
stresses in the location of welding, high Complete welding shall be visually
temperature Hydrogen attack, checked and radiographed as per the
susceptibility to creep damage etc. applicable code. Detailed inspection of
welding shall be done as outlined in
The controlled deposition welding shall Annexure VI.
be considered for material limited to P-
1, P-3 & P-4 steels only. A detailed Preheat and post weld heat treatment
weld procedure specification shall be shall be carried out as per the
developed and qualified for each requirement of relevant code. In order
application. to check whether post weld treatment
has been carried out properly,
The welding technique shall be hardness readings on the weldment
controlled deposition temper bead or and HAZ shall be taken after PWHT.
half bead technique. The hardness readings should be
minimum as the indentation marks
Local PWHT may be substituted for all required during hardness
materials provided application is measurement act as stress riser and
reviewed and a detailed procedure is this leads to stress concentration. If
developed. The required post weld post weld heat treatment is required it
heat temperature shall be maintained is recommended to carry out
for a distance of not less than two radiography before post weld heat
OISD-128 16
__________________________________________________________________________________________
11.0 REFERENCES
The following codes standards and publication have either been referred or used in the
preparation of this standard, and the same shall be read in conjunction with this standard.
i) API Guide for Inspection of Refinery Equipment - Chapter VI - Unfired Pressure Vessels.
ii) API Guide for Inspection of Refinery Equipment - Chapter V - Preparation of Equipment for
Safe Entry and Work.
iii) ASME - Pressure Vessel Code. Section VIII Divn. I & II.
vii) API-RP-572, Inspection of Pressure Vessels (Towers, Drums, Reactors, Heat Exchangers
and Condensers)
viii) IS-9964 Part-I, Preparation of Tank for Safe Entry and Work.
ix) IS-4682 part I, Code of practices for lining of vessels and equipment for chemical
processes-Rubber Lining.
Annexure-I page 1 of 2
The check list format shall contain the following minimum information.
a) Equipment No.
b) Serial No.
c) Date of Inspection
d) Equipment Type
e) Plant
f) Service
g) Design Code
h) Manufacturer
i) Main Dimensions
j) Material of Construction
k) Max. Allow. working pressure/Vacuum
l) Max. Allow. Working Temperature
m) PWHT Radiography (Spot/Full)
n) Hydrostatic Test Pressure
CHECKLIST
1.0 Check documentation like Material Test Certificate (MTC), Procedure Qualification
Record (PQR), welding procedure Specification (WPS), Welders Qualification Records
QAP etc.
2.0 Check records of stage inspections such as joint fit ups, pre/ post weld heat treatment,
Radiography & other NDT tests, hydro test etc.
3.0 Check and inspect all nozzle connections including drains and vents
4.0 Check and inspect all threaded connections for proper tightening
5.0 Check for adequate engagement of threads, back welding and gusseting
6.0 Check for any alteration/ deviation from the drawing during fabrication
10.0 Check and ensure installation of specified gaskets, especially at the untested joints.
Annexure-I page 2 of 2
15.0 Check for tension free jointing of piping connected to pressure vessel
17.0 Check insulation and fire proofing for proper installation/ sealing etc
18.0 Check records of coating on under grounded/ mounded vessels for bonding/ thickness/
holiday testing.
21.0 Ensure free movement of vessel (thermal expansion) with respect to adjoining
22.0 Ensure ladders and landing platforms are meeting the standard norms and practices.
OISD-128 21
_______________________________________________________________________________________
Annexure -II
i) Carry out Ultrasonic thickness gauging of the vessel operating at lower temperature.
Larger the vessel, more readings are required to be assured of its condition. Record of
previous internal inspections can be utilized to locate the areas subject to corrosion.
ii) Inspect the equipment for any local hot spots by thermography / visual inspection
particularly for internally refractory lined vessels, local corrosion, and gasket leaks.
iii) Check for condition of protective coating, insulation and fire proofing of structural
members for adequacy of protection.
iv) Check the condition of bottom dished end to skirt weld for any rain water corrosion.
v) Check for bulging, out of roundness, sagging and distortion. If abnormality observed, the
overall dimensions of the vessel shall be checked to determine the extent of the distortion
vi) Check the condition of platform, hand rails and ladders for safety.
vii) Check the protective devices like safety valves, rupture discs for any passing / rupture.
Thermo-graphy may be used to detect the passing of safety valves. Ensure that the block
valves upstream and downstream of safety valves (if provided) are kept opened and car-
sealed.
viii) Check and monitor the process parameters like pressure, temperature, throughput,
change in feed stock, pH control, sulphur, chloride content which will have a slow but long
term impact on health of columns and vessels.
ix) Check the effectiveness and performance of corrosion inhibitors, caustic, ammonia and
other chemicals injected for corrosion protection.
x) Ensure the functioning of pressure gauges, temperature indicators and level gauges.
All observations shall be recorded and filed in history file. In service inspection report shall be taken into
account for shutdown work list and planning.
OISD-128 22
_______________________________________________________________________________________
Annexure-III page 1 of 3
2) Purpose
Pressure testing of pressure vessel is carried-out for a variety of purposes in addition to that
highlighted above.
i) When a pressure test is to be conducted in which the test pressure will exceed the set
pressure of the pressure relieving device(s), the pressure relieving device(s) should be
removed. An alternative to removing the pressure relieving device(s) is to use test clamps
to hold down the valve disks.
ii) All gages shall be calibrated against a standard dead weight tester or a calibrated master
gage. Gages shall be recalibrated at any time that there is reason to believe that they are
in error.
iii) Dial indicating pressure gages used in testing shall be graduated over a range of about
double the intended maximum test pressure, but in no case shall the range be less than
1½ nor more than 4 times that pressure. Digital reading pressure gages having a wider
range of pressure may be used provided the readings give the same of greater degree of
accuracy as obtained with dial pressure gages.
iv) An indicating gage shall be connected directly to the vessel. If the indicating gage is not
readily visible to the operator controlling the pressure applied, an additional indicating gage
shall be provided where it will be visible to the operator throughout the duration of the test.
For large vessels, it is recommended that a recording gage be used in addition to indicating
gages
OISD-128 23
_______________________________________________________________________________________
Annexure-III page 2 of 3
5) Test pressure
Actual pressure used during a test depends on the objective of the test.
a) Strength Testing: In this case a stress level greater than that experienced in service is
induced (but lesser than that which would cause damage). Strength testing necessarily
demonstrates that the equipment can safely withstand the maximum service pressure
(at maximum operating temperature). The test pressure can be at the same level as
the original test pressure (new equipment), but normally it is slightly less to allow for
loss in thickness due to corrosion.
b) Leak Testing: It is carried-out where the objective is not to test the strength of the
equipment, but to detect the leakage (sometimes leakage rates). The pressure applied
is generally less than design pressure. Normally, it is carried-out to detect leak
tightness of gasket joints, tube to tube sheet joints etc.
a) Some of the considerations which should be borne in mind during a pressure test are
equipment foundations & supporting structure, ability of line supports and vessels
nozzles to carry the test weight, ensuring that connected ancillary equipment
(instrument, valves etc) are capable of withstanding the test pressure, including static
head in the specified test pressure etc.
d) At no stage shall the vessel be approached for close inspection until the pressure has
been positively reduced to a level lower than that previously attained. “Previously
attained” pressure indicates maximum operating pressure attained by the vessel during
its service life. The pressure(s) at which the vessel will be approached for close
inspection shall be specified in the test procedure. Such pressures need not exceed
design pressure. Under such situations, after the equipment has withstood the
pressure for required time it is recommended to reduce the pressure to the equipment
design pressure before it is approached for a thorough inspection. However, this
precaution is not applicable in the case of leak testing (for gasket joints) since the test
pressure in this case will be normally less than design pressure.
e) Under similar safety precaution (new) equipment tested for integrity may be reduced to
2/3rd the test pressure before carrying-out close inspection. The reduced pressure so
stated incidentally corresponds to the design pressure or slightly less than the design
pressure.
Annexure-III page 3 of 3
g) The specified test pressure includes the amount due to static head acting at any point
under consideration. Particular care should be taken when applying a hydraulic test to
a vertically mounted vessel, which may have been tested initially in the horizontal
plane.
h) A point worth mentioning in this context refers to the precautions to be taken in case of
vessel supports fireproofed both from inside as well as outside. The internal condition
of the supports needs to be ascertained prior to water filling, especially in case of
equipment that have seen over 10 years of service. LPG spheres and some high-
pressure vessels/columns (will be fire-proofed on both sides) are some equipment that
come under this category.
i) For compartmented vessels, especially those with bellows, due attention shall be paid
to allowable internal pressure differences.
k) No vessel undergoing pressure testing shall be subjected to any form of shock loading.
e.g: hammer testing.
The consequences of failure during a pneumatic test can be devastating and such testing
requires special precaution. Some of the precautions to be taken are as follows:
b) Except where it is necessary to meet design codes or statutory requirements, the test
pressure should be limited to 110% of design pressure for strength and to 100% of
design pressure for leak testing. Pressure should be applied in small increments. As a
practice of safety, equipment should not be subjected to pneumatic pressure beyond 1
kg/cm2g except for vessels/ piping systems that are specifically designed for pneumatic
pressure and where water entry into the system is not tolerated due to operational
reasons.
c) The pressure should be reduced to a pressure not exceeding design pressure before
any close examination is carried-out.
OISD-128 25
_______________________________________________________________________________________
Annexure-IV
The process/ procedure for Corrosion Rate calculation/ estimation shall be duly approved.
A. Remaining life of the pressure vessel shall be calculated as per the following procedure
B. For new pressure vessel and pressure vessels where service conditions are being changed,
the probable corrosion rate for determination of remaining life shall be determined using
following method;
i) Corrosion rate may be calculated from data collected on similar material and service
ii) If data on similar material or service is not available, then it can be estimated from
published data
iii) If corrosion rate can not be established from above, the thickness determination shall
be made immediately after 3 months of service by thickness measurement.
Subsequent measurements shall be made after appropriate intervals until corrosion
rate is established.
OISD-128 26
_______________________________________________________________________________________
Annexure-IV
INSPECTION DOCUMENTATION CARDS (FORMS)
FORM 1
VESSEL DATA CARD
INFORMATION WEIGHTS
DESIGN CODE_________________________ SHELL______________________________
MANUFACTURER_______________________ INTERNALS_________________________
MANUFACTURER’S INSULATION_________________________
ORDER NO.____________________________
DIAMETER___________________________ HEADS_____________________________
CONDITIONS
DESIGN TEMPOC_____________________ OPERATION TEMPO C_______________________
FORM 4
UNIT_________
UJ+
OISD-128 32
_______________________________________________________________________________________
ANNEXURE-VI page 1 of 3
INSPECTION OF WELDING
The duties of a welding inspector usually involve the performance of a number of operations,
including:
i) The faces and edges of material should be examined for laminations, blisters, scabs
and seams.
ii) Heavy scale, oxide films, grease, paint, oil and moisture should be removed.
iii) The pieces to be welded should be checked for size and shape. Warped, bent or
otherwise damaged material should be detected in the early stages of fabrication.
iv) Edge preparations, bevel angle, alignment of parts and fit up should be checked. The
groove surface should be smooth (equivalent to machined/filled/ground surface). The
root gap should be uniform.
v) Tacks to hold alignment of joint must be checked for soundness. Tacks which are to
be included in weld must be done by qualified welders in accordance with the welding
procedure and must be of the same quality as root pass.
Visual inspection is employed to check details of the work while welding is in progress. The
details to be considered are:
i) Welding process
ii) Cleaning.
iii) Preheat and interpass temperatures.
iv) Joint preparation.
v) Distortion control.
vi) Filler Metal.
vii) Interpass chipping, grinding or gouging.
The inspector should be thoroughly familiar with the items involved in the qualified welding
procedures. Compliance with all details of the procedure should be verified. The root pass is
most important from the point of view of weld soundness. The root pass may be checked by
OISD-128 33
_______________________________________________________________________________________
ANNEXURE-VI page 2 of 3
dye-penetrant testing. The inspection of root pass offers another opportunity to inspect for
plate laminations.
In the case of double-groove welds, slag form the root pass on the side of the plate may from
slag deposits on the other side. Such deposits should be chipped, ground or gouged out prior
to welding the opposite side. Where slag removal is incomplete, it will remain in the root of the
finished welds. Emphasis should be placed on the adequacy of the tack welds and clamps or
braces used to maintain the root opening to assure penetration and alignment.
Visual examination is the first stage in the inspection of a finished weld. The following quality
factors should be checked:
iv) Surface flaws, such as cracks, porosity, unfilled craters and crater cracks particularly
at the end of welds, undercutting, overlap, excessive weld reinforcement, excessive
grinding etc.
v) The areas where fit-up lugs were attached or where handling lugs, machining blocks
or other temporary attachments were welded on, must be checked carefully after the
attachment is removed. The area must be ground smooth and any pits or tears shall
be filled in with weld metal ground smooth Air hardening materials should be
preheated before any thermal cutting.
vi) Post-weld heat treatment time, temperature and heating/cooling rates. For groove
welds, the width of finished welds will fluctuate in accordance with the groove angle,
root face, root opening and permissible tolerances. The height of reinforcement
should be consistent with the specified requirements. Where not specified the
inspector may have to rely on his judgement, guided by what he considers a good
welding practice.
The finished weld should be thoroughly cleaned of oxides and slag for its final inspection.
After visual inspection the finished weld may be examined by one or more than one of the
following techniques.
i) DYE PENETRANT TESTING: Unless otherwise specified, the extent of this test will
be 100% for all root runs for alloy steel welds. Adequate precautions as specified in
applicable code should be taken while interrupting the welding cycle.
b) alloy steel - 100% of the welds. The weld joint for radiography will be marked
by the inspector.
OISD-128 34
_______________________________________________________________________________________
ANNEXURE-VI page 3 of 3
Radiographic examination of weld joints of two dissimilar materials shall be considered as per
the higher metallurgy stipulations.
Hardness testing by portable hardness testers may be considered as NDT method. Hydraulic
testing may be done to check for leaks through welds, cracks etc.
6. DESTRUCTIVE TESTS
i) Mechanical tests like tensile, bend, impact, hardness, drift, flattening tests etc.
The method and extent of examinations will be governed by applicable code requirements.
7. REPAIR OF WELDS
ii) Weld discontinuities which are beyond acceptable limits shall be removed from the
joint completely by the process of chipping and grinding.
iii) Where random radiography is specified, the first weld of each welder shall be
completely radiographed. In case of pipe size 150 mm dia. and below, the first two
welds shall be completely radiographed.
iv) For each weld found unacceptable due to a welders fault two additional checks
should be carried out on welds performed by the same welder.
OISD-128 35
_______________________________________________________________________________________
Annexure-VII page 1 of 2
1. INSPECTION
A. Visually inspect exterior and interior of vessel to determine location of all hydrogen blisters.
C. Conduct magnetic particle inspection at the edge and crown of any blister 2 inches and greater
in diameter to locate cracks which originate at, or have progressed near to the surface.
D. In order to detect plate cracks (fissures), conduct magnetic particle inspection of the plate for a
distance of 6 inches beyond the limits of blisters 2 inches and greater in diameter appearing on
the inside of the vessel. See Figure 1.
2. EVALUATION
A. If the blisters are clustered and originate at varying depths, replace the plate.
B. If plate fissures are detected under Paragraph II. F, replace the affected plate.
C. Hydrogen blisters visible in the cylindrical section of the shell, the crown of flanged and dished
or elliptical heads or in hemispherical heads and those that are away from seams of localised
loading such as support pads should be considered acceptable.
D. Hydrogen blisters visible in and very near highly stressed areas such as head knuckles,
openings, seam and seam junctures, and support pads should be considered unacceptable in
pressure vessels.
E. If the diameter of any blisters listed in paragraph III.C exceeds the thickness of the plate, and
the vessel is operated below the metal transition temperature, the material should be replaced.
USE ASME Code, Section VIII Division 2, impact Test Exemption Curves for Carbon Steels.' as
a measure of transition temperature.
OISD-128 36
_______________________________________________________________________________________
Annexure-VII page 2 of 2
3. REPAIRS
A. Cracked blisters on the outside surface of vessels in hydrofluoric acid service and cracked
blisters on either inside or outside surfaces of vessels in other services shall be repaired as
follows:
1. Drill 1/8" diameter holes at ends of each crown crack or edge crack to a depth equal to
blister depth as determined by thickness measurement.
B. Relieve hydrogen pressure in uncracked blisters 2 inches and larger in diameter by drilling a
1/16 inch diameter hole in the centre of the crown as follows:
1. If blisters 2 inches and larger in diameter on the inside surface have crown or edge cracks,
gouge out complete blister, fill with weld metal and grind smooth with plate surface.
1. Hydrogen may diffuse through the vessel wall and become trapped inside tubular legs that
are welded to the vessel. This can form an explosive mixture with air in the legs.
2. Prior to any welding or cutting on or near the legs of a blistered vessel, the legs should be
purged of any explosive gases as follows:
a) Drill 1/4" diameter holes at top and bottom of legs, with a non-sparking drill.
b) Flush with inert gas or with air from the bottom hole.
Annexure-VIII
INSPECTION TOOLS
Annexure-IX page 1 of 3
The fractionating column bottom and internals are subjected to high temperature corrosion due
to presence of sulphur whereas column top is prone to low temperature acidic corrosion
because of salts and H2S present in the crude. The crude containing naphthenic acid also
causes the corrosion of the column shell, and the same is pronounced in the sections where
temperature ranges from 200oC to 400oC. Severity of naphthenic acid attack is higher where
the turbulent conditions exist. The impingement plate particularly in the columns where the
feed nozzle is radial is subjected to severe erosion. Noticeable corrosion or erosion is also
generally observed where the steam impinges the shell. The dislodging of the trays
(particularly valve trays) is common due to steam surge.
Galvanic corrosion is also observed at the location where cladded shells and uncladded shells
join together. Where the lining is bulged, the parent metal is subjected to corrosion. Liquid
level corrosion is noticeable in the top tray downcomer collectors particularly at the reflux
collector trays.
Pronounced corrosion is generally noticed at the interface level of water and hydrocarbons.
Mostly the corrosion is noticed in the bottom portion of the accumulators, which are not
internally protected.
Dehydrators & LP/HP separators of crude stabilising units are likely to get corroded in the
bottom portion from 5 to 7 O’ clock position due to presence of salt & water.
The sections where the turbulent conditions exist like impingement plate/flash zone are
subjected to corrosion erosion due to naphthenic acid and sulphur in the crude. Columns,
shells are also liable to corrode opposite to impingement plate due to rebound of fluid.
Weldments and Heat Affected Zone are also susceptible to corrosion.
E. REACTORS IN REFORMERS
Generally the reactors are of low alloy steels like 2-1/4Cr-1 Mo or cladded with stainless steel.
Due to this superior metallurgy metal wastage is generally not observed. However, the
following locations give indication of deterioration/cracking.
F. REACTORS IN FCCU
OISD-128 39
_______________________________________________________________________________________
The shell, riser O.D. and portion of the cyclone dip leg O.D. are severely attacked in the riser
extension type of installation. Where the grids are still used, erosion is found fairly uniform over
most of the grid when high velocities are employed through cyclones. Some erosion occurs to
Annexure-IX page 2 of 3
the wall of the plenum chambers and to the top head where small plenums are in use. For
those reactors with only two cyclones, high swirl of catalyst through the nozzles cause severe
erosion.
The refractory lining generally stands up quite well in reactor cyclones. Normal repairs require
some resurfacing of small areas or replacement of small localised sections. There are two
kinds of valves at the bottom of dipleg. The one mostly in use is the flapper type with counter
weight. The other is the trickle valve type, with the flapper plate hanging over the opening
suspended by rings. The flapper type of valves are subjected to erosion.
G. REGENERATOR IN FCCU
In the plate type of distribution grid, erosion to the grid plates is a common phenomenon. Due
to considerable vibration and heat differentials cracking of the grid plate can also take place.
In pipe type of grid design where seals are still in use, these seals may leak. Migration of
catalyst past the seal could destroy a pipe grid in a very short time.
The branches (pipe coming off each lateral) experience metal loss, mainly to the top
circumference. Occasionally the steam coming out of jet blowing directly into another branch,
lateral or end plate creates erosion. Warpage of pipe grids can take place due to overheating
during start-up and during operation. Many 5% Cr. grids experience weld cracking.
The failure of refractory lining on the shell is another common problem. During operation, it
may cause hot spots on the shell. Erosion of cyclone dip legs, failure of cyclone welds along
with weld of cyclone supports may also take place.
Erosion of the double disc sliding valve gates, erosion at the core near the inlet and at
holes/sleeves in the grid plate are common problems. Bulging or cracking on the shell
adjacent to the grid-plate also may take place. The erosion problems in orifice chamber are
caused by the catalyst carryover from the Regenerator.
I. CHOKE CHAMBERS
Cracking of skirt and shell weld joints is quite common particularly in the coke chambers where
the skirt is not of slotted type. In the coke chambers generally feed, stripping steam and water
quench nozzles are installed at the bottom. Due to thermal cyclic shocks lower portion of the
coke chamber gets bulged. At the advanced stages of bulging, circumferential welds which act
as stiffeners get cracked in the axial direction. However, the effect is pronounced just opposite
the feed entry nozzle at an elevation of about 1 meter. The chambers where the feed enters
from the top, bulging is confined in the top portion. The conical portion of the coke chamber
where the feed enters is also prone to cracking at the knuckle portion. Bottom flange to shell
weld joint, weld joints of feed, water quench and steam nozzles are also likely to crack under
thermal cyclic conditions.
The corrosion and scaling is generally confined to the bottom between 5 to 7 O’ clock positions
probably due to the presence of corrodents like H2S and water. LPG storage vessels are also
prone to stress corrosion cracking. The circumferential weld joints below the equatorial plates
in the LPG Horton spheres are more prone on such cracking.
OISD-128 40
_______________________________________________________________________________________
Annexure-IX page 3 of 3
Vessels in low temperature service e.g. in KTU of refineries and propane circuit of LPG
recovery units of Gas Processing Plants are prone to external corrosion due to faulty insulation,
which causes condensation of the vessels. The severity of corrosion increases in case of
corrosive atmosphere as in KTU.
In these vessels internal corrosion due to moist So2 where condensation can take place, also
occurs. Internals and shell are affected due to this.
Generally the storage vessels are fabricated from Carbon steel and Nickel steels. For the
operating conditions prevailing at refineries, material of construction used for Ammonia storage
vessels in the refineries are carbon steels. The weld joints of C.S. vessels are prone to stress
corrosion cracking particularly in the vessels, which have not been stress relieved initially or
after fabrication repairs.
The weld joints and heat affected zone of the columns and vessels in DEA and MEA service
which have not been stress relieved are also prone to cracking due to presence of H2S or H2S
and H2.
Further details about corrosion in pressure vessels are available in corrosion Manual-OISD
Publication No. 136.