Pre Commissioning
Pre Commissioning
Pre Commissioning
3. Steam system
8. Cleaning of pipelines ( Hydraulic flushing , pigging, air blowing, steam blowing, oil flushing, acid
cleaning, alkaline boiling and manual cleaning )
17.Service test
1. Team selection
2. Proper written procedures before any pre commissioning
3. Proper emphasis on personnel safety.
Plant construction:
Operator training
1.Start up procedures
2.Commissioning procedures
5. Reactor overview
Punch list is an integral part of mechanical completion and is a critical step to verifying the status of
system completion.
The category of punch list determines if a system is ready to move into the next phase of
commissioning.
Category A
Punch list items that must be repaired or completed prior to the issuance of mechanical completion
Category B
Punch list items that must be repaired or completed after mechanical completion but before pre
commissioning
Category C
Punch list items that must be repaired or completed prior to commissioning for safe start up and
continuing operations.
The turn over procedure and schedule will define how the systems are turned over from construction to
commissioning; what work has to be completed and by whom, before the system can be turned over.
SYSTEM DEFINITIONS
Basis of Design
Process Flow Diagrams (PFDs), Utility Flow Diagrams (UFDs) and Heat &
Material Balances
Process & Operational Control Description
Process Equipment List
Process Datasheets for Main Equipment (per Equipment List)
Piping & Instrumentation Diagrams (P&ID’s)
Line list
Tie-in Schedule
Cause & Effects Diagrams
Process Data Sheets for instrumentation
Process Alarm & Trip Schedule
Effluent and Emission Summary
Catalyst and Chemicals Summary
Process Simulation Report (including Process Simulations files)
Process Design Calculations
Flare and Relief System Study/Sizing Calculations
Distribution P&ID for the flare headers
HAZOP Report
Performance Guarantees Statement
Performance Test Procedure
Pre-commissioning and Commissioning Manual
Operating & Maintenance Manual
Architectural Design
Electrical Design
Area plans
Hazardous area classification drawings
Area key plans for Lighting, tray and grounding layouts
Layout drawings
Grounding layouts
Plant cable tray and cable routing layouts
Plant and buildings lighting layouts
Substation layouts
Switchgear building equipment layout
U/G duct bank layout etc.
One line diagrams showing interlocks, inter tripping, system capacity, Voltage
levels, currents, impedances, generation power levels etc.
Key one line diagram
138/4.16 kV one line diagram
4,16 kV (MV) one line diagrams
480V one line diagrams
120 VAC UPS one line diagrams
125 VDC UPS one line diagrams
Emergency power one line diagrams etc.
Schematics
4 kV motor schematics
460 V motor schematics
MOV control schematics
Lighting control schematics
Heat tracing isometrics etc.
Equipment drawings including vendor prints
These drawings shall be supplied for all the major tagged equipment such as
Transformers, Switchgears, MCCs, UPS, Chargers, Generators, Power
supplies, PTs, CTs, Control panels, packaged equipments etc.
Front and interior layout showing all the components
Wiring drawings and terminal connections
Installation details including manuals
Component maintenance and instruction manuals
Electronic equipment manuals and settings
Fuse ratings and characteristic curves
Equipment and component datasheets
Weights and measurements
Schematics
Equipment specifications
Motor datasheets
Circuit breaker settings
3 Line diagrams
Battery details including amp-hour ratings
Relay settings and relay discrimination curves
Data sheets and environment limitations
HVAC requirements
Manufacturing data books
Spare parts lists etc.
Inter connection diagrams
Inter connection drawings between panels
Details
Hazardous area classification details
Installation details for Lighting, grounding, heat tracing etc.
Duct bank details
Lists and Schedules
Cable routing schedules
MCC schedules
Lighting and Distribution panel schedules
Heat tracing panel schedules
Load lists
Electric equipment list
Bulk material lists and catalogue numbers
Cable tray penetration details in to buildings
Calculations
Tray sizing calculations
Heat tracing calculations
Equipment sizing calculations
Lighting level calculations
Emergency power load requirements
Studies and reports
System studies showing fault levels, short circuit current, Minimum/
Maximum
Load flow analysis, motor starting effects and system stability, voltage
levels
Transformer tap settings
Motor protection settings
Relay setting schedules including setting curves