Checklist For Supervision of Reinforced Soil Wall PDF
Checklist For Supervision of Reinforced Soil Wall PDF
Checklist For Supervision of Reinforced Soil Wall PDF
LCH
Compiled by : _____________________________________
KYW
Checked by : _____________________________________
TYC
Approved by :_____________________________________
ACKNOWLEDGED
CHECKED BY
BY
No. CHECKLIST ITEMS GUE & PARTNERS
CONTRACTOR SDN BHD (G&P)
1.0 SURVEY/SETTING UP SIGNATURE YES NO
The initial survey and setting out of the wall alignment
1.1 survey shall be carried out by a licensed surveyor with
the presence of Engineer’s representative.
The initial survey drawings showing the levels and
1.2 alignment of wall shall be endorsed by licensed surveyor
before submitted for Engineer’s approval.
The wall alignment shall be pegged at every 10m
1.3
intervals at site.
Wherever there are curves or cornering of the wall, the
1.4 wall alignment shall be pegged at every 2m intervals or
closer at site.
EXCAVATION/ REMOVAL OF UNSUITABLE SIGNATURE
2.0 YES NO
MATERIAL
Carry out Mackintosh Probe (MP) at the foundation of the
2.1
wall at every 5m intervals or as directed by the Engineer.
Submit Mackintosh Probe results to the Engineer no
2.2
longer than 24 hours after the MP tests.
Engineer to issue instruction on depth of excavation and
2.3
removal of unsuitable material based on MP results.
Carry out soil replacement with approved material after
2.4
removal of unsuitable material.
Cover base of wall foundation with plastic sheets to avoid
softening if soil replacement is not carried out
immediately after excavation. If the contractor fails to
2.5
provide the plastic sheet at site, the soft material should
be stripped out prior to the placement of suitable material
or quarry dust.
3.0 WALL ERECTION SIGNATURE YES NO
3.1 Brace externally the initial row of panels.
Connect steel reinforcements to panels, backfill and
3.2
compact before next row of panels are erected.
Insert joint fillers into all the joints between the panels
3.3
with the help of a wooden edge.
Place cushion pads at the slots on the top edge of each
3.4
panel before the installation of subsequent rows of panel.
Check alignment and verticality of wall during erection
3.5
using a plumb bob.
Check the reinforcement size and anchor block size (if
3.6
applicable) at site before backfilling works.
4.0 BACKFILL AND COMPACTION SIGNATURE YES NO
Level backfill before placing of and bolting of
4.1
reinforcement strips.
Maximum loose thickness of every fill layer shall not
exceed 375mm before compaction. Trial run should be
4.2
carried out at site to determine the number of passes to
achieve the required degree of compaction.
Keep trucks and heavy vehicles 1.5m away from the
4.3
back of the wall panel.
Use hand-operated compacting machine (plate
4.4 compactor etc.) with weight < 1 ton within 1.5m from the
wall face for compaction.
Section: CH-028
G&P GEOTECHNICS SDN BHD
Revision: 0
Date: 29-05-2006
CHECKLIST FOR SUPERVISION OF REINFORCED SOIL WALL Page 3 of 4