3UUP REP Weekly Report 11 - 18july 2019

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

WEEKLY REPORT 11TH – 18TH JULY 2019

Urban Upgrading Programme for the Towns


of Kigoma, Lindi and Sumbawanga

The United Republic of Tanzania


Ministry of Water (MOW)

Financed by
Kreditanstalt für
European Union
Wiederaufbau

Consultants

GKW Consult GmbH Don Consult Ltd Lahmeyer Tanzania


Augustaanlage 67 Po Box 4218 Po Box 32334
68165 Mannheim Dar es Salaam Dar es Salaam
Germany Tanzania Tanzania
United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programme / Construction Phase


Weekly Report – 11th to 18th July 2019

© GKW Consult GmbH, 2019

The information contained in this document is solely for the use of the Client identified on the cover sheet for the
purpose for which it has been prepared.

GKW Consult undertakes no duty to or accepts any responsibility to any third party who may rely upon this docu-
ment.

All rights reserved. No section or element of this document may be removed from this document, reproduced,
electronically stored or transmitted in any form without written permission of GKW Consult.

Prepared for:
Ministry of Water
Maji Ubungo
Dar es Salaam, Tanzania

Prepared by:
GKW Consult GmbH
Augustaanlage 67
68165 Mannheim, Germany

Inspection status: Freigegeben

Revision History:

Revision Date Author Checked by Approved by Description


00 12.07.2019 M. Mwamukinga T. Kirsch T. Kirsch Final
A. Makaidi
A. Rweyemamu
M. Kriek
D. Sabai

3UUP_REP_Weekly Report_11 -18July 2019 Page ii


United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programme / Construction Phase


Weekly Report – 11th to 18th July 2019

Table of Contents

1 Kigoma WSS – Immediate Works ............................................................................... 4


3 Lindi WSS – Immediate Works.................................................................................... 6

Annexe 1 – Photo Documentation ....................................................................................................... 9


Annexe 2 – Progress Overview ........................................................................................................... 10

3UUP_REP_Weekly Report_11 -18July 2019 Page iii


United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programmer / Construction Phase


Weekly Report – 11th to 18th July 2019

1 Kigoma WSS – Immediate Works

Item Description

Contractor No.1 Lorsch (T) Ltd

Type of Works Electromechanical

79,488.44 EUR (excl. provisional


Total Amount of Works
sum*)

*provisional sum of 100,000.00 EUR is covering Kigoma and Lindi

Contract Data Commencement date 1st February 2019

Access to Site 2ndApril 2019

Payment of Advance Payment 20th March 2019

Completion Date (including 23rd August 2019


extension of time)

Defects Liability Period 6 months

N° / Type of Incident • None

Overall Progress to date • 100% Excluding Variation Order No.4

Payment Request this week • None

Contractor No.2 JLA Investment Company (T) Ltd

Type of Works Civil

17,215.05 EUR (excl. provisional


Total Amount of Works
sum*)

*provisional sum of 50,000.00 EUR is covering Kigoma and Lindi


Contract Data
Commencement date 4th February 2019

Access to Site 21st March 2019

Payment of Advance Payment 19th March 2019

Completion Date (including 14th August 2019


extension of time)

3UUP_REP_Weekly Report_11 -18July 2019 Page 4


United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programmer / Construction Phase


Weekly Report – 11th to 18th July 2019

Item Description

Defects Liability Period 6 months

N° / Type of Incident • None

Overall Progress to date • 100%

Payment Request this week • None

Consultant
• Construction supervision of VO 04
• Assistance in plant operation;

Contractor (Lorsch and JLA)


Major work done this week • Electrical cabling for the ultrasonic level sensor – VO 04
(Lorsch);
• Excavation for the discharge pipeline from the submersible
pump to the 4,000 litres HDPE water tank– VO 04 (Lorsch);
• Delivery of procured materials for implementation of VO 04 –
Chlorination Kigoma (Lorsch);

Problems encountered
Problems encountered and • None
proposed solutions Proposed Solutions
• None

• Lorsch Managing Director is currently on site and the speed


Status of previous problems
of works has improved significantly

Variation proposals / VAO • None

Consultant
• Construction supervision of VO 04 (Lorsch):
Contractor (Lorsch and JLA)
• Installation of discharge pipework from the submersible
Major activities planned for
pump to the 4,000 litres HDPE water tank – VO 04 (Lorsch)
next week
• Electrical works for the ultrasonic level sensor and the chlo-
rination unit – VO 04 (Lorsch)
• Installation of the star/delta starter for the submersible
pump – VO 04 (Lorsch)

3UUP_REP_Weekly Report_11 -18July 2019 Page 5


United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programmer / Construction Phase


Weekly Report – 11th to 18th July 2019

Item Description

Abnormal weather conditions • None

2 Lindi WSS – Immediate Works

Item Description

Contractor No.1 Lorsch (T) Ltd

Type of Works Electromechanical

40,136.48 EUR (excl. provisional


Total Amount of Works
sum*)

*provisional sum of 100,000.00 EUR is covering Indi and Kigoma

Contract Data Commencement date 1st February 2019

Access to Site 16th May 2019

Payment of Advance Payment 20th March 2019

Completion Date (including 23rd August 2019


extension of time)

Defects Liability Period 6 months

N° / Type of Incident • None

Overall Progress to date • 98% Excluding Variation Order No.5

Payment Request this week • None

Contractor No.2 JLA Investment Company (T) Ltd

Type of Works Civil

7,193.00 EUR (excl. provisional


Total Amount of Works
sum*)
Contract Data
*provisional sum of 50,000.00 EUR is covering Lindi and Kigoma

Commencement date 4thFebruary 2019

Access to Site 16th May 2019

3UUP_REP_Weekly Report_11 -18July 2019 Page 6


United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programmer / Construction Phase


Weekly Report – 11th to 18th July 2019

Item Description

Payment of Advance Payment 19th March 2019

Completion Date (including 14th August 2019


extension of time)

Defects Liability Period 6 months

N° / Type of Incident • None

Overall Progress to date • 100% Excluding the Variation Order No.2

Payment Request this week • None

Consultant
• Assistance in operation of the WTP and new distribution
network;
• Supervised the implementation of VO No.2 and No.5;
• Continued with water analyses for BH11 and 13;

Major work done this week


Contractors - Lorsch
• Material follow up for VO5 execution.
Contractor - JLA
• Continued with reinstatement of the pipes in the distribution
network as per variation order No.2;
• Follow up on the ordered material/items under VO No.2.

Problems encountered
Problems encountered and • Outstanding site handover from OIA to MoW.
proposed solutions Proposed Solutions
• Waiting for court ruling at Mtwara High court.

Status of previous problems • Ruling of court case at Mtwara High court is still pending.

Variation proposals / VAO • None.

Consultant
• Continue assisting LUWASA in the aspect of operation of the
Major activities planned for WTP and new distribution network;
next week
• Construction supervision of immediate works and any other
emergency works;

3UUP_REP_Weekly Report_11 -18July 2019 Page 7


United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programmer / Construction Phase


Weekly Report – 11th to 18th July 2019

Item Description
• Supervise the implementation of VO No.2 and No.5;

Contractor (Lorsch)
• Follow up on the ordered items under variation order No.5.

Contractor (JLA)
• Continue with the reinstatement of the pipes in the distribu-
tion network as per variation order No.2;
• Start the repair of the PAC and air blower roofs at WTP
• Follow up on the ordered material/items under VO No.2.

Abnormal weather conditions • None.

3UUP_REP_Weekly Report_11 -18July 2019 Page 8


United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programme / Construction Phase


Weekly Report – 12th to 18th July 2019 / Annex 2

Annexe 1 – Photo Documentation

VO 04 Chlorination Kigoma – Delivered pipes and VO 04 Chlorination Kigoma – Electrical cabling for
fittings for the discharge pipe from the pump to the ultrasonic level sensor
the HDPE water tank

Progress on the reinstatement of distribution network between N-16 and N-36 (Part of VO2) – Lindi WSS

3UUP_REP_Weekly Report_11 -18July 2019 Page 9


United Republic of Tanzania
Ministry of Water (MoW)

3 Towns Urban Upgrading Programme / Construction Phase


Weekly Report – 12th to 18th July 2019 / Annex 2

Annexe 2 – Progress Overview

IMMEDIATE WORKS KIGOMA (ELECTROMECHANICAL: LORSCH (T) LTD):


Works finished (DLP ongoing since 7th May 2019) – refer to Weekly Report 2nd to 8th May 2019.

IMMEDIATE WORKS KIGOMA (CIVIL: JLA INVESTMENT COMPANY (T) LTD):


Works finished (DLP ongoing since 7th May 2019) – refer to Weekly Report 2nd to 8th May 2019.

IMMEDIATE WORKS LINDI (ELECTROMECHANICAL: LORSCH (T) LTD):


Access to site on 16th May 2019.

IMMEDIATE WORKS LINDI (CIVIL: JLA INVESTMENT COMPANY (T) LTD):


Access to site on 16thMay 2019

3UUP_REP_Weekly Report_11 -18July 2019 Page 10


United Republic of TanzaniaMinistry of Water (MoW) ANNEXE 2
3 Towns Urban Upgrading Programmer / Construction Phase

PROGRESS OVERVIEW - IMMEDIATE WORKS KIGOMA (CIVIL: JLA INVESTMENT COMPANY (T) LTD)
From 20
TIME
ITEM START FINISH Mar to
ACTIVITY FRAME
NO. DATE DATE reporting
[DAYS] date
6 Mobilization 2 20-03-19 21-03-19
Actual work done 100%
7 Handing over of site 1 21-03-19 21-03-19
Actual work done 100%
8 Procurement of Materials (cement, sand, re-bars and form) 7 22-03-19 28-03-19

9 Sourcing of construction materials 7 22-03-19 28-03-19


Actual work done 100%
10 Submission of RFA to the Engineer for approval of selected materials 3 25-03-19 27-03-19
Actual work done 100%
11 Procurement & delivery of materials to the site 3 25-03-19 27-03-19
Actual work done 100%
12 Construction of Works 318 20-03-19 07-11-19

13 Removal of fixed reinforcement bars 3 22-03-19 24-03-19


Actual work done 100%
14 Cleaning - Removal of collapsed soil fromthe excavated ground 5 22-03-19 26-03-19
Actual work done 100%
15 Re-excavation to formation level 4 23-03-19 26-03-19
Actual work done 100%
16 Casting of blinding concrete 1 27-03-19 27-03-19
Actual work done 100%
17 Fixing of reinforcement bars for base slaband stem 4 29-03-19 01-04-19
Actual work done 100%
18 Fixing of forms and support for base slab(also formwork for kicker of the stem) 6 30-03-19 04-04-19
Actual work done 100%
19 Casting of base slab 1 05-04-19 05-04-19
Actual work done 100%
20 Fixing of forms & supports for the stem 10 07-04-19 17-04-19
Actual work done 100%
21 Casting of concrete for stem 1 18-04-19 18-04-19
Actual work done 100%
22 Backfilling and compaction 7 29-04-19 02-05-19
Actual work done 100%
23 Site cleanup 2 01-05-19 02-05-19
Actual work done 100%
24 Provision for any other emergency works 71 20-03-19 29-05-19

24.1 VO 01: Removal of existing pontoon and HDPE pipes DN 500 3 12-04-19 14-04-19
Actual work done 100%
25 Provisional Handover 1 07-05-19 07-05-19
Actual work done 100%
26 Defects Liability Period 180 07-05-19 07-11-19
Actual work done 40%

3UUP_REP_Weekly Report_11 -18July 2019.docx


United Republic of TanzaniaMinistry of Water (MoW) ANNEXE 2
3 Towns Urban Upgrading Programmer / Construction Phase

REVISED PROGRESS OVERVIEW - IMMEDIATE WORKS KIGOMA (CIVIL: JLA INVESTMENT COMPANY (T) LTD)

REVISED
TIME REVISED REVISED
ITEM START FINISH TIME NOT IMPLEMENTED AS PER WORK-PLAN
ACTIVITY FRAME START FINISH
NO. DATE DATE FRAME DUE TO
[DAYS] DATE DATE
[DAYS]

6 Mobilization 2 20-03-19 21-03-19 2 20-03-19 21-03-19

7 Handing over of site 1 21-03-19 21-03-19 1 21-03-19 21-03-19

8 Procurement of Materials (cement, sand, re-bars and form) 7 22-03-19 28-03-19 7 22-03-19 28-03-19

9 Sourcing of construction materials 7 22-03-19 28-03-19 7 22-03-19 28-03-19

Submission of RFA to the Engineer for


10 3 25-03-19 27-03-19 3 25-03-19 27-03-19
approval of selected materials

11 Procurement & delivery of materials to the site 3 25-03-19 27-03-19 5 25-03-19 29-03-19

12 Construction of Works 258 20-03-19 02-12-19 318 20-03-19 07-11-19

13 Removal of fixed reinforcement bars 2 22-03-19 23-03-19 3 22-03-19 24-03-19

14 Cleaning - Removal of collapsed soil fromthe excavated ground 5 22-03-19 26-03-19 5 22-03-19 26-03-19

15 Re-excavation to formation level 4 23-03-19 26-03-19 4 23-03-19 26-03-19

16 Casting of blinding concrete 1 27-03-19 27-03-19 1 27-03-19 27-03-19

17 Fixing of reinforcement bars for base slaband stem 4 29-03-19 01-04-19 4 29-03-19 01-04-19

Fixing of forms and support for base slab


18 4 02-04-19 05-04-19 6 30-03-19 04-04-19
(also formwork for kicker of the stem)

19 Casting of base slab 2 09-04-19 09-04-19 1 05-04-19 05-04-19

20 Fixing of forms & supports for the stem 5 11-04-19 15-04-19 10 07-04-19 17-04-19

21 Casting of concrete for stem 2 17-04-19 18-04-19 1 18-04-19 18-04-19

22 Backfilling and compaction 4 27-04-19 30-04-19 7 29-04-19 02-05-19

23 Site cleanup 2 29-04-19 30-04-19 2 01-05-19 02-05-19

Provision for any other emergency works: VO 1- removal of


24 71 20-03-19 29-05-19 3 12-04-19 14-04-19
pontoon and HDPE pipes from Lake

25 Provisional Handover 1 07-05-19 07-05-19 1 07-05-19 07-05-19

26 Defects Liability Period 180 07-05-19 07-11-19 180 07-05-19 07-11-19

27 Final Handover 7 04-11-19 06-11-19 7 05-11-19 07-11-19

3UUP_REP_Weekly Report_11 -18July 2019.docx


United Republic of TanzaniaMinistry of Water (MoW) ANNEXE 2
3 Towns Urban Upgrading Programmer / Construction Phase

PROGRESS OVERVIEW - IMMEDIATE WORKS LINDI (CIVIL: JLA INVESTMENT COMPANY (T) LTD)

TIME
ITEM START FINISH From 20
ACTIVITY FRAME 4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul
NO. DATE DATE Mar to 3 Jul
[DAYS]
6 Mobilization 7 23-05-19 30-05-19
6.1 Mobilization of staff and equipment 7 23-05-19 30-05-19
Actual work done 100%
7 Procurement and delivery of Materials for the works (Pipes and Fittings) 77 22-03-19 06-06-19
Actual work done 100%
8 Physical Works 8 06-06-19 14-06-19
9 Replacement of Defective pipe section 14 23-04-19 07-05-19
Actual work done 100%
10 Reinstatement of the top soil and site cleaning 4 10-06-19 14-06-19
Actual work done 100%
11 Provision for emergency works 48 26-06-19 14-08-19
VO 02: Repair of various water supply components at Lindi
Actual work done 45% 45%
12 Provisional Handing over of works 7 07-08-19 14-08-19
Actual work done 0%
13 Defects Liability Period 180 14-08-19 14-02-20
Actual work done 0%
14 Final Handover 7 07-02-20 14-02-20
Actual work done 0%

3UUP_REP_Weekly Report_11 -18July 2019.docx


United Republic of TanzaniaMinistry of Water (MoW) ANNEXE 2
3 Towns Urban Upgrading Programmer / Construction Phase

DELAY OVERVIEW - IMMEDIATE WORKS LINDI (CIVIL: JLA INVESTMENT COMPANY (T) LTD)
REVISED
TIME REVISED REVISED
ITEM START FINISH TIME NOT IMPLEMENTED AS PER WORK-PLAN
ACTIVITY FRAME START FINISH
NO. DATE DATE FRAME DUE TO
[DAYS] DATE DATE
[DAYS]

6 Mobilization 7 21-03-19 30-03-19 7 23-05-19 30-05-19

6.1 Mobilization of staff and equipment 7 21-03-19 30-03-19 7 23-05-19 30-05-19

Procurement and delivery of Materials for the works (Pipes and


7 30 22-03-19 22-04-19 77 22-03-19 06-06-19
Fittings)

8 Physical Works 21 23-04-19 14-05-19 8 06-06-19 14-06-19

9 Replacement of Defective pipe section 14 23-04-19 07-05-19 6 06-06-19 12-06-19

10 Reinstatement of the top soil and site cleaning 7 08-05-19 14-05-19 4 10-06-19 14-06-19

Provision for emergency works: VO 02: Repair of various water


11 90 21-03-19 23-07-19 48 26-06-19 14-08-19
supply components at Lindi

12 Provisional Handing over of works 7 15-05-19 21-05-19 7 07-08-19 14-08-19

13 Defects Liability Period 180 23-07-19 23-01-20 180 14-08-19 14-02-20

14 Final Handover 7 17-01-20 23-01-19 7 07-02-20 14-02-20

3UUP_REP_Weekly Report_11 -18July 2019.docx


United Republic of TanzaniaMinistry of Water (MoW)3 Towns Urban Upgrading Programmer / Construction Phase ANNEXE 2

PROGRESS OVERVIEW - IMMEDIATE WORKS KIGOMA (ELECTROMECHANICAL: LORSCH (T) LTD)

TIME
ITEM FINISH From 23 Jan to 3
ACTIVITY FRAME START DATE Jul 2019
4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul
NO. DATE
[DAYS]

0 Advance payment logistics 56 23-01-19 20-03-19


Actual work done 100%
1 Procurement of materials and mobilization of staff and equipment 28 21-03-19 17-04-19

1.1 Procurement of pumps 28 21-03-19 17-04-19


Actual work done 100%
1.2 Procurement of fittings and MCCB 7 21-03-19 27-03-19
Actual work done 100%
2 Materials mobilisation 26 28-03-19 22-04-19

2.1 Delivery of pipe fittings and MCCBs 7 28-03-19 03-04-19


Actual work done 100%
2.2 Delivery of 2x pumps 12 11-04-19 22-04-19
Actual work done 100%
3 Installation and commissioning works 68 11-04-19 17-06-19

3.1 Installation and commissioning of 1x MCCB 7 11-04-19 17-04-19


Actual work done 100%
3.2 Installation of pump and pump fittings 2 04-04-19 05-04-19
Actual work done 100%
3.3 Testing, commissioning and acceptance of pump 1 13 23-04-19 03-05-19
Actual work done 100%
3.4 Installation of pump 2 (supply only) 1 03-05-19 03-05-19
Actual work done 100%

3.5 Testing, commissioning and acceptance of pump 2 (only acceptance required) 1 03-05-19 03-05-19
Actual work done 100%
3.6 Equipment installation handover 92 03-05-19 16-08-19
Actual work done 80%
4 Other emergency works 90 15-04-19 16-07-19

4.1 VO 01: Pipe Support for Vamia Manifold 2 17-04-19 18-04-19


Actual work done 100%
4.2 VO 03: Pipes and fittings - Kigoma intake pipe 10 26-04-19 05-05-19
Actual work done 100%
4.3 VO 04: Chlorination Kigoma 64 10-06-19 16-08-19
Actual work done 55% 50%
5 Attend defects during DLP 180 07-05-19 16-02-20
Actual work done 40%
6 Final handover 7 09-02-20 16-02-20

3UUP_REP_Weekly Report_11 -18July 2019.docx


United Republic of TanzaniaMinistry of Water (MoW)3 Towns Urban Upgrading Programmer / Construction Phase ANNEXE 2

REVISED PROGRESS OVERVIEW - IMMEDIATE WORKS KIGOMA (ELECTROMECHANICAL: LORSCH (T) LTD)

REVISED
TIME REVISED
ITEM FINISH TIME REVISED NOT IMPLEMENTED AS PER WORK-PLAN
ACTIVITY FRAME START DATE FINISH
NO. DATE FRAME START DATE DUE TO
[DAYS] DATE
[DAYS]

0 Advance payment logistics 56 23-01-19 20-03-19 --- --- ---

1 Procurement of materials and mobilization of staff and equipment 28 21-03-19 17-04-19 28 21-03-19 17-04-19

1.1 Procurement of pumps 28 21-03-19 17-04-19 28 21-03-19 17-04-19

1.2 Procurement of fittings and MCCB 7 21-03-19 27-03-19 7 21-03-19 27-03-19

2 Materials mobilisation 26 28-03-19 22-04-19 26 28-03-19 22-04-19

2.1 Delivery of pipe fittings and MCCBs 7 28-03-19 03-04-19 7 28-03-19 03-04-19

2.2 Delivery of 2x pumps 12 11-04-19 22-04-19 8 11-04-19 19-04-19

3 Installation and commissioning works 68 11-04-19 17-06-19 9 17-06-19 25-06-19

3.1 Installation and commissioning of 1x MCCB 7 11-04-19 17-04-19 68 11-04-19 17-06-19

3.2 Installation of pump and pump fittings 7 23-04-19 29-04-19 2 04-04-19 05-04-19

3.3 Testing, commissioning and acceptance of pump 1 7 30-04-19 06-05-19 13 23-04-19 03-05-19

3.4 Installation of pump 2 7 21-05-19 27-05-19 1 03-05-19 03-05-19 Supply only

3.5 Testing, commissioning and acceptance of pump 2 7 28-05-19 03-06-19 1 03-05-19 03-05-19 Supply only

3.6 Equipment installation handover: Pump 1 7 11-06-19 17-06-19 92 03-05-19 16-08-19

4 Other Emergency Works 90 18-04-19 16-07-19 94 03-05-19 23-08-19

4.1 VO 01: Pipe Support for Vamia Manifold 4 15-04-19 18-04-19 2 17-04-19 18-04-19

4.2 VO 03: Pipes and fittings - Kigoma intake pipe 10 26-04-19 05-05-19 10 26-04-19 05-05-19

4.3 VO 04: Chlorination Kigoma 18 10-06-19 28-06-19 64 10-06-19 16-08-19

5 Attend defects during DLP 180 02-08-19 02-02-20 180 07-05-19 16-02-20

6 Final handover 7 27-01-20 02-02-20 7 09-02-20 16-02-20

3UUP_REP_Weekly Report_11 -18July 2019.docx


United Republic of TanzaniaMinistry of Water (MoW)3 Towns Urban Upgrading Programmer / Construction Phase ANNEXE 2

PROGRESS OVERVIEW - IMMEDIATE WORKS LINDI (ELECTROMECHANICAL: LORSCH (T) LTD)

TIME From 23 Jan


ITEM FINISH
ACTIVITY FRAME START DATE 2019 to 26 27-Jun 28-Jun 29-Jun 30-Jun 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul
NO. DATE June
[DAYS]
0 Advance payment logistics 56 23-01-19 20-03-19
Actual work done 100%
1 Procurement of materials and mobilization of staff and equipment 78 21-03-19 06-06-19
1.1 Procurement of Soft starter for HLP 78 21-03-19 06-06-19
Actual work done 100%
1.2 Procurement of Variable Frequency Drives 71 21-03-19 30-05-19
Actual work done 100%
2 Materials mobilisation 6 01-06-19 06-06-19
2.1 Delivery of Soft Starter 3 03-06-19 06-06-19
Actual work done 100%
2.2 Delivery of 3x Variable Frequency Drives 6 01-06-19 06-06-19
Actual work done 100%
3 Installation and commissioning works 33 07-06-19 08-07-19
3.1 Installation and commissioning of 1x soft starter on the HLP 7 07-06-19 14-06-19
Actual work done 98% 98%
3.2 Installation of Variable frequency Drive at BH13 7 17-06-19 23-06-19
Actual work done 100%
3.3 Testing, commissioning and acceptance of VFD at BH13 7 17-06-19 23-06-19
Actual work done 98% 98%
3.4 Installation of Variable frequency Drive at BH03 7 24-06-19 30-06-19
Actual work done 100%
3.5 Testing, commissioning and acceptance of VFD at BH 03 7 24-06-19 30-06-19
Actual work done 98% 98%
3.6 Installation of Variable frequency Drive at BH12 7 31/06/2019 07-07-19
Actual work done 100%
3.7 Testing, commissioning and acceptance of VFD at BH 12 13 23-06-19 06-07-19
Actual work done 98% 98%
3.8 Provisional handover 7 21-08-19 23-08-19
Actual work done 0%
3.9 Other emergency works 126 06-04-19 23-08-19

3.9.1 VO 2 Genset demobilisation and dewatering pumps supply 7 09-05-19 16-05-19

Actual work done 100%


Supply and installation of various electrical items in
3.9.2 VO 5 56 28-06-19 23-08-19
the well field and Ng'apa WTP
Actual work done 50% 50%
4 Attend defects during DLP 180 09-02-20 16-02-20
Actual work done 0%
5 Final handover 7 17-02-20 23-02-20

3UUP_REP_Weekly Report_11 -18July 2019.docx


United Republic of TanzaniaMinistry of Water (MoW)3 Towns Urban Upgrading Programmer / Construction Phase ANNEXE 2

DELAY OVERVIEW - IMMEDIATE WORKS LINDI (ELECTROMECHANICAL: LORSCH (T) LTD)


REVISED
TIME REVISED REVISED
ITEM START FINISH TIME NOT IMPLEMENTED AS PER WORK-PLAN
ACTIVITY FRAME START FINISH
NO. DATE DATE FRAME DUE TO
[DAYS] DATE DATE
[DAYS]

0 Advance payment logistics 56 23-01-19 20-03-19 --- --- ---

Procurement of materials and mobilization of staff and


1 28 21-03-19 17-04-19 78 21-03-19 06-06-19
equipment

1.1 Procurement of Soft starter for HLP 28 21-03-19 17-04-19 78 21-03-19 06-06-19

1.2 Procurement of Variable Frequency Drives 28 21-03-19 17-03-19 71 21-03-19 30-05-19

2 Materials mobilisation 7 17-04-19 23-04-19 6 01-06-19 06-06-19

2.1 Delivery of Soft Starter 7 17-04-19 23-04-19 3 03-06-19 06-06-19

2.2 Delivery of 3x Variable Frequency Drives 7 17-04-19 23-04-19 6 01-06-19 06-06-19

3 Installation and commissioning works 40 14-04-19 23-05-19 33 07-06-19 08-07-19

Installation and commissioning of 1x soft starter on the


3.1 7 17-04-19 23-04-19 7 07-06-19 14-06-19
HLP

3.2 Installation of Variable frequency Drive at BH13 7 23-04-19 29-04-19 7 17-06-19 23-06-19

3.3 Testing, commissioning and acceptance of VFD at BH13 7 30-04-19 06-05-19 7 17-06-19 23-06-19

3.4 Installation of Variable frequency Drive at BH03 7 30-04-19 06-05-19 7 24-06-19 30-06-19

3.5 Testing, commissioning and acceptance of VFD at BH 03 7 28-05-19 03-06-19 7 24-06-19 30-06-19

3.6 Installation of Variable frequency Drive at BH12 7 07-05-19 14-05-19 7 31/06/2019 07-07-19

3.7 Testing, commissioning and acceptance of VFD at BH 12 7 15-05-19 23-05-19 13 23-06-19 06-07-19

3.8 Provisional handover 7 24-05-19 30-05-19 7 21-08-19 23-08-19

3.9 Other emergency works 106 06-04-19 23-07-19 126 06-04-19 23-08-19

Genset demobilisation and dewatering pumps


3.9.1 VO 2 7 23-05-19 30-05-19 7 09-05-19 16-05-19
supply
Supply and installation of various electrical
3.9.2 VO 5 56 28-06-19 23-08-19 56 28-06-19 23-08-19
items in the well field and Ng'apa WTP

4 Attend defects during DLP 180 23-07-19 23-01-20 180 23-08-19 23-02-20

5 Final handover 7 17-01-20 23-01-20 7 17-02-20 23-02-20

3UUP_REP_Weekly Report_11 -18July 2019.docx