3UUP REP Weekly Report 11 - 18july 2019
3UUP REP Weekly Report 11 - 18july 2019
3UUP REP Weekly Report 11 - 18july 2019
Financed by
Kreditanstalt für
European Union
Wiederaufbau
Consultants
The information contained in this document is solely for the use of the Client identified on the cover sheet for the
purpose for which it has been prepared.
GKW Consult undertakes no duty to or accepts any responsibility to any third party who may rely upon this docu-
ment.
All rights reserved. No section or element of this document may be removed from this document, reproduced,
electronically stored or transmitted in any form without written permission of GKW Consult.
Prepared for:
Ministry of Water
Maji Ubungo
Dar es Salaam, Tanzania
Prepared by:
GKW Consult GmbH
Augustaanlage 67
68165 Mannheim, Germany
Revision History:
Table of Contents
Item Description
Item Description
Consultant
• Construction supervision of VO 04
• Assistance in plant operation;
Problems encountered
Problems encountered and • None
proposed solutions Proposed Solutions
• None
Consultant
• Construction supervision of VO 04 (Lorsch):
Contractor (Lorsch and JLA)
• Installation of discharge pipework from the submersible
Major activities planned for
pump to the 4,000 litres HDPE water tank – VO 04 (Lorsch)
next week
• Electrical works for the ultrasonic level sensor and the chlo-
rination unit – VO 04 (Lorsch)
• Installation of the star/delta starter for the submersible
pump – VO 04 (Lorsch)
Item Description
Item Description
Item Description
Consultant
• Assistance in operation of the WTP and new distribution
network;
• Supervised the implementation of VO No.2 and No.5;
• Continued with water analyses for BH11 and 13;
Problems encountered
Problems encountered and • Outstanding site handover from OIA to MoW.
proposed solutions Proposed Solutions
• Waiting for court ruling at Mtwara High court.
Status of previous problems • Ruling of court case at Mtwara High court is still pending.
Consultant
• Continue assisting LUWASA in the aspect of operation of the
Major activities planned for WTP and new distribution network;
next week
• Construction supervision of immediate works and any other
emergency works;
Item Description
• Supervise the implementation of VO No.2 and No.5;
Contractor (Lorsch)
• Follow up on the ordered items under variation order No.5.
Contractor (JLA)
• Continue with the reinstatement of the pipes in the distribu-
tion network as per variation order No.2;
• Start the repair of the PAC and air blower roofs at WTP
• Follow up on the ordered material/items under VO No.2.
VO 04 Chlorination Kigoma – Delivered pipes and VO 04 Chlorination Kigoma – Electrical cabling for
fittings for the discharge pipe from the pump to the ultrasonic level sensor
the HDPE water tank
Progress on the reinstatement of distribution network between N-16 and N-36 (Part of VO2) – Lindi WSS
PROGRESS OVERVIEW - IMMEDIATE WORKS KIGOMA (CIVIL: JLA INVESTMENT COMPANY (T) LTD)
From 20
TIME
ITEM START FINISH Mar to
ACTIVITY FRAME
NO. DATE DATE reporting
[DAYS] date
6 Mobilization 2 20-03-19 21-03-19
Actual work done 100%
7 Handing over of site 1 21-03-19 21-03-19
Actual work done 100%
8 Procurement of Materials (cement, sand, re-bars and form) 7 22-03-19 28-03-19
24.1 VO 01: Removal of existing pontoon and HDPE pipes DN 500 3 12-04-19 14-04-19
Actual work done 100%
25 Provisional Handover 1 07-05-19 07-05-19
Actual work done 100%
26 Defects Liability Period 180 07-05-19 07-11-19
Actual work done 40%
REVISED PROGRESS OVERVIEW - IMMEDIATE WORKS KIGOMA (CIVIL: JLA INVESTMENT COMPANY (T) LTD)
REVISED
TIME REVISED REVISED
ITEM START FINISH TIME NOT IMPLEMENTED AS PER WORK-PLAN
ACTIVITY FRAME START FINISH
NO. DATE DATE FRAME DUE TO
[DAYS] DATE DATE
[DAYS]
8 Procurement of Materials (cement, sand, re-bars and form) 7 22-03-19 28-03-19 7 22-03-19 28-03-19
11 Procurement & delivery of materials to the site 3 25-03-19 27-03-19 5 25-03-19 29-03-19
14 Cleaning - Removal of collapsed soil fromthe excavated ground 5 22-03-19 26-03-19 5 22-03-19 26-03-19
17 Fixing of reinforcement bars for base slaband stem 4 29-03-19 01-04-19 4 29-03-19 01-04-19
20 Fixing of forms & supports for the stem 5 11-04-19 15-04-19 10 07-04-19 17-04-19
PROGRESS OVERVIEW - IMMEDIATE WORKS LINDI (CIVIL: JLA INVESTMENT COMPANY (T) LTD)
TIME
ITEM START FINISH From 20
ACTIVITY FRAME 4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul
NO. DATE DATE Mar to 3 Jul
[DAYS]
6 Mobilization 7 23-05-19 30-05-19
6.1 Mobilization of staff and equipment 7 23-05-19 30-05-19
Actual work done 100%
7 Procurement and delivery of Materials for the works (Pipes and Fittings) 77 22-03-19 06-06-19
Actual work done 100%
8 Physical Works 8 06-06-19 14-06-19
9 Replacement of Defective pipe section 14 23-04-19 07-05-19
Actual work done 100%
10 Reinstatement of the top soil and site cleaning 4 10-06-19 14-06-19
Actual work done 100%
11 Provision for emergency works 48 26-06-19 14-08-19
VO 02: Repair of various water supply components at Lindi
Actual work done 45% 45%
12 Provisional Handing over of works 7 07-08-19 14-08-19
Actual work done 0%
13 Defects Liability Period 180 14-08-19 14-02-20
Actual work done 0%
14 Final Handover 7 07-02-20 14-02-20
Actual work done 0%
DELAY OVERVIEW - IMMEDIATE WORKS LINDI (CIVIL: JLA INVESTMENT COMPANY (T) LTD)
REVISED
TIME REVISED REVISED
ITEM START FINISH TIME NOT IMPLEMENTED AS PER WORK-PLAN
ACTIVITY FRAME START FINISH
NO. DATE DATE FRAME DUE TO
[DAYS] DATE DATE
[DAYS]
10 Reinstatement of the top soil and site cleaning 7 08-05-19 14-05-19 4 10-06-19 14-06-19
TIME
ITEM FINISH From 23 Jan to 3
ACTIVITY FRAME START DATE Jul 2019
4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul
NO. DATE
[DAYS]
3.5 Testing, commissioning and acceptance of pump 2 (only acceptance required) 1 03-05-19 03-05-19
Actual work done 100%
3.6 Equipment installation handover 92 03-05-19 16-08-19
Actual work done 80%
4 Other emergency works 90 15-04-19 16-07-19
REVISED PROGRESS OVERVIEW - IMMEDIATE WORKS KIGOMA (ELECTROMECHANICAL: LORSCH (T) LTD)
REVISED
TIME REVISED
ITEM FINISH TIME REVISED NOT IMPLEMENTED AS PER WORK-PLAN
ACTIVITY FRAME START DATE FINISH
NO. DATE FRAME START DATE DUE TO
[DAYS] DATE
[DAYS]
1 Procurement of materials and mobilization of staff and equipment 28 21-03-19 17-04-19 28 21-03-19 17-04-19
2.1 Delivery of pipe fittings and MCCBs 7 28-03-19 03-04-19 7 28-03-19 03-04-19
3.2 Installation of pump and pump fittings 7 23-04-19 29-04-19 2 04-04-19 05-04-19
3.3 Testing, commissioning and acceptance of pump 1 7 30-04-19 06-05-19 13 23-04-19 03-05-19
3.5 Testing, commissioning and acceptance of pump 2 7 28-05-19 03-06-19 1 03-05-19 03-05-19 Supply only
4.1 VO 01: Pipe Support for Vamia Manifold 4 15-04-19 18-04-19 2 17-04-19 18-04-19
4.2 VO 03: Pipes and fittings - Kigoma intake pipe 10 26-04-19 05-05-19 10 26-04-19 05-05-19
5 Attend defects during DLP 180 02-08-19 02-02-20 180 07-05-19 16-02-20
1.1 Procurement of Soft starter for HLP 28 21-03-19 17-04-19 78 21-03-19 06-06-19
3.2 Installation of Variable frequency Drive at BH13 7 23-04-19 29-04-19 7 17-06-19 23-06-19
3.3 Testing, commissioning and acceptance of VFD at BH13 7 30-04-19 06-05-19 7 17-06-19 23-06-19
3.4 Installation of Variable frequency Drive at BH03 7 30-04-19 06-05-19 7 24-06-19 30-06-19
3.5 Testing, commissioning and acceptance of VFD at BH 03 7 28-05-19 03-06-19 7 24-06-19 30-06-19
3.6 Installation of Variable frequency Drive at BH12 7 07-05-19 14-05-19 7 31/06/2019 07-07-19
3.7 Testing, commissioning and acceptance of VFD at BH 12 7 15-05-19 23-05-19 13 23-06-19 06-07-19
3.9 Other emergency works 106 06-04-19 23-07-19 126 06-04-19 23-08-19
4 Attend defects during DLP 180 23-07-19 23-01-20 180 23-08-19 23-02-20