Document No.: TDC-1455-FT-02, Rev.: 0
Date: 30-09-2014
Job No.: 1455

TECHNICAL DELIVERY CONDITION FOR SEALESS PIPE FITINGS SA 234 Gr. WPB

1. Quantity : As per purchase requisition

2. Dimensions : As per purchase requisition

3. Name of material : Pipe fittings of wrought carbon steel

4. Specification designation : SA 234 WPB in accordance with ASME SEC.II, Part A,


Edition 2010

5. Grade : WPB

6. Manufacture : Hot finish, Normalized

7. Size : As per purchase requisition


(NPS, schedule Number)

8. Type of construction : Seamless

9. End use of material : Sour Service application

10. Optional requirement : Nil.

11. Special requirements :


 Shall have a maximum carbon content of 0.23.
 The Carbon Equivalent (CE) based on the Ladle Analysis shall not exceed 0.43, calculated by
the following formula: Carbon Equivalent = C+ Mn/6 + (Cr+Mo+V)/5 + (Ni+Cu)/15
 Sulphur content in the material shall be ≤ 0.01% and Nickel content in the material shall be
<1%.
 All materials shall be supplied in the normalized condition. Normalizing shall be carried out as
a separate heat treatment
 All materials shall be in accordance with the materials property and heat treatment
requirements of ISO 15156 or NACE MR0175
 Materials shall have hardness at any point (including HAZ & Parent metal) not exceeding
HRC 22.
 Wrought steel butt welding fittings shall comply with the requirements of MESC 76/201.
 All Material supplied shall be new, clean and free from mill scale, rust, pit and defects.
 Unless noted otherwise in the purchase description, pipe fittings shall be in accordance with
the following: ASME B 16.9 and SPE 76/200.
 All non-destructive examination shall be performed after heat-treatment.

Page 1 of 2
Oil & Gas Construction Factory L.L.C
Document No.: TDC-1455-FT-02, Rev.: 0
Date: 30-09-2014
Job No.: 1455

TECHNICAL DELIVERY CONDITION FOR SEALESS PIPE FITINGS SA 234 Gr. WPB

12. Certification : According to SA-234Para-12; Original or Verified true


copy of Mill test certificate is required in accordance with
EN10204-3.1: E2004.

As a minimum, the MTC’s should contain the following:

 Description, Size and Quantity


 Standard & Grade
 Heat/ Melt/ Manufacturing No.
 Heat Treatment Details
 Chemical Analysis
 Mechanical Tests Result
 Hydrostatic Test Result
 Hardness Test Result
 Results of Supplementary Test(s)
 NDE Results
 Nace Compliance Statement
 Dimensional Check Report

Prepared by Approved by

(Design Engineer) (Engineering Manager)

Page 2 of 2

You might also like