Floor Beam Fb/3 & Fb/4, Fb/3, Fb/3
Floor Beam Fb/3 & Fb/4, Fb/3, Fb/3
Floor Beam Fb/3 & Fb/4, Fb/3, Fb/3
G H I J K
I/L=3556 I/L=3556 I/L=5714
K=3.1 K=3.1 K=5.0 4.5 4.5
4.5 4.5 2.8
Loading GH/KL
Beam AB(FB/3) assume 250x400
Load for slab(S1)= 18.619 KN/m
Load for slab(S2)= 18.627 KN/m
Self-weight =.25x.4x25x1.5 = 3.750 KN/m
Total = 40.996 KN/m
Beam HI/JK(FB/4) DE, assume 250x400
Load for slab(S1)= 14.973 KN/m
Load for slab(S2)= 18.627 KN/m
Self-weight = 3.750 KN/m
Total = 37.35 KN/m
Beam IJ(FB/14) assume 400X250
Load for staer side = 6.056 KN/m
Self wt=.4x.25x25x1.5= 3.750 KN/m
Total = 9.806 KN/m
Weight of wall=3.01x.1x19x1.5= 8.579 KN/m
Total = 18.385 Kn/m
Point load due to beam FB/13 at center =57
F. E.M=(57X2.8)/8 = 20.00 KN/m
Relation stiffness K D.F
c/c=1146 1 AB=(3.1/5.1)=0.61
beam=3556 3.1 BA=(5.1/8.2)=0.38
(400x250)/4500 BC= 3.8
Beam=5714 5.0 CB=(3.1/10.1)=0.31
(400x250)/2800 CD=(5.0/10.1)=0.50
DC(5.0/10.1)=0.50
Member span F.E.M Fa dead +line load +ve mach span shear
A B C D
155
400 250
4-12 at bottom
For –Ve rectangular at B & E =82 Kn m
At the end the beam will be designed as rectangular beam.
Xu max/d= 0.48
Xumax =0.48x367=176.16 mm
Mulim=0.36xfckxbx Xumax(d-0.42 Xumax)
=0.36x20x250x176.16(367-0.42x176.16)
=0.317x293=92.881 Kn m >82 Kn m
As MuD is less then Mulim is under reinforced.
So 82x106=0.87fy Ast d(1-(Ast fy/bd fck)
=0.87x415x367Ash (1-(Ashx415/250x367x20)
=132505Ast-29.97Ast
2.736x106=4421Ast-Ast2
Or Ast=(4421-2921/2=743.5mm2
Shear reinforced
Shear Fe Vu=1/2x4.25x41=87.125kn
Tve=87.125x1000/250x367=0.95n/mm
Over all slab of support =100x4x113.1/250x367=0.494mm
Tve>Tc shear reinforced required
Vu s=Vu-Tbd =87125-.48x250x367=87125-44040=43055h
=0.87xfyxAstxd/Vus=0.87x415x2x50.3x367/43085
Stirap should be lenth of
1. 0.75x367=275.25
2. 300
So use 8@275 c/c
Beam FB/4 BC & DF
1700
155
400 250
Calculate moment
At mid span = +31.24 len/m
At support top B & F =-75.90 len/m
DO C & D =-50.70 len/m
Of required =
=258mm<then 369 it is ok
At mid span
MUD =31.24 len/m Mulim=0.36XfckXbfxDf(d-0.42xDf)
=0.36x20x1700x155(369-0.42x155)=1..8972x106x303.9
=576.56kn/m
Width is much
Soil is a under reinforced section
MUD =0.87XfyXAstxd(1-(415Ast /gxdxFck)
Or 31.24x106=30210-4.41
7.084=133227Ast – Ast2
Ast=30210-29737=237mm2
Shear reinforced
Shear Fece Vu = 3/2x37.35x4.25=73.4kn
Tve = 79.4x100/250x369=0.861n/m2
Over all centre reinforced at support =100x3x113.1/250x369=0.368
TC =0.36=(0.12/0.25)X0.48=0.42N/M2
Vus = VU- Tcbd=79400-.42x250x369
=40655 N
So specification of 8 stirrup
=0.87x415XAstxd/Vus=.87X415X2X50.3X369/40655
=330
1450
100
400 250
Beam FB13(CD)
Assume size =250x350
D=350-28-6=319m
Bf =lo/b=6=155=bw=2800x.7/6+6x155+250
=327=930+280 = 1450
Effective span = 2.8m
Calculate momont
+Ve moment = 16.24 depth
-Ve moment at C&D=43.76-Vu
So 43.76x106 =0.87fy.AST.D(1-(Ast.fy/bd.fck)
=.87x415x319Ast(1-(Astx415/200x319x20)
=115175 Ast-37.46Ast2
Or 1.186x 106=3075-Ast2
Or Ast=(3075-2188/2)=443.5mm2
Shear reinforced
S.F Vu= 55.74 kn
Tve=55740/200x319=0.874n/mm2
% of compression reinforced at support=100x2x50.3/200x369=0.158
Tc = 0.28+0.08/0.25x0.008=0.283n/m2
Vus=Vu-Tcbd=55740-0.283x200x319=37685h
=307m
0.75x319=239
978
425 728
250
BEAM FB/2
Calculated moment
+ve moment at mid span =36.37kn
-ve DO at B =83 kn
-ve DO c =16.27 kn
Bf=lo/12+bw+3df
=0.7x4500/12+250+155=978 m
Eft. Depth d=425-25-16/2=392
Eft span =4.5m
Total moment ,Tu = wx0.728x0.728/2x(4.5-0.25)x1/2
=8.43kn/m
Vu = 4.25x30.749/2=63.34kn
Ve = requirement shear =Vu =1.6T/6=63.34+1.6X8.43/6=65.59KN
Tve = 65.59/250x392=0.669n/m2
Long reinforced
equivalent B.H, val=Mu + Me
when Ve =Tu (1+(.425/.250)=10.02kn/m
Vel=36.37+10.02=46.39 kn/m
Mulim=0.36fckxXumax/d(1-0.42 Xumax/d)bd2
Xumax/d=0.48
=0.36x20x0.48(1-0.42x0.48)250x3922
=106.25kn/m.which is mel=46.39 kn/m
So the section is under reinforced
So 46.39x106=0.87xfyxAst d(1-(fy Ast/bd fck)
=141532Ast – 29.97 Ast2
Or 1.55x106=4722Ast-Ast2
Or Ast=4722-4012/2=355m2