CSR Chapter 1,2,3
CSR Chapter 1,2,3
Common Schedule of Rates (CSR) being published by Punjab, PWD from time to time is a very
comprehensive document and useful in execution of development works in Punjab. Apart from Punjab
PWD this CSR is being used by number of Boards, Corporations, Public Sector Undertakings, Private
Sector Builders and Architects etc.
The CSR was first published in the year 1962 followed by revision in the year 1987. During the last 23
years, CSR has not been revised. 25 Nos. Addenda and Corrigenda on CSR-1987 have been issued from
time to time. The prices of Labour and Material have increased many fold and to update the rates, the
ceiling premium are being fixed from time to time by Zonal Committee of Superintending Engineers of
various departments.
It is utmost needed to revise the CSR due to introduction of new items in the market and evolution of
new material, machinery and modern construction techniques so as to make it really useful document.
I wish to place on record the technical input and effective co-ordination on the part of various
technical committees and the efforts put in by staff of CSR cell to finalize the CSR-2010
I am also thankful to all the Chief Engineers and Superintending Engineers for giving their valuable
advice and Executive Engineers and other staff members who gave their valuable suggestions and full co-
operation in the finalization of CSR-2010
I am sure that this CSR will be quite helpful to all the concerned in construction industry and
development works.
This CSR has been issued with the approval of the Direction Committee of Chief Engineers, in the
meeting held on 11.07.2011.
CSR - 2010
1 The Common Schedule of Rates 1962 was converted into metric system during 1965-66 as Interim
Common Schedule of Rates. Then it was revised in 1987. Then in 2010 reprint of CSR-1987 was
issued with the approval of the Committee of Direction of Chief Engineers by incorporating the A&C
slips No 1 to 21 and 25 (A&C slip No 22 to 24 relate to specifications).
2 Now the revision of CSR has become utmost necessary due to phenomenal increase in the rates of
material and labour and addition of new items in the market and evolution of new material machinery
and modern construction techniques over the past two decades.
3 As desired by hon'ble Chief Minister Punjab the revision work of CSR is undertaken on the
persuasions of Lt. Gen. (Retd.) B.S.Dhaliwal, Technical Adviser to Hon'ble Chief Minister Punjab. To
complete this task, Chief Engineer, PWD B&R, Chief Engineer Electrical (B&R), Chief Engineer
Water Supply and Sanitation and Chief Engineer Irrigation (Canal) were designated as Nodal Officers
vide Memo No. A.T.P.B/05/CSR dated 19th March 2010. The Chapters relating to Irrigation, Water
Supply and Sanitation and Electrical have been revised by the concerned departments and for
revising the remaining Chapters of B&R, 8 Nos. sub committees of convenors was constituted for
revising the different chapters. These revised chapters have been compiled and now the CSR - 2010
comprises the following chapters:-
(i) Chapter No. 1 to 27 and 31 to 32 Buildings and Culverts, Bridge, Road Works,
Irrigation Works such as Outlets, Lining and River
and Canal Protection works etc.
4 This Common Schedule of Rates is applicable to the works to be executed by the various Branches
of the State PWD Punjab.
6 The rates given in this Schedule are for normal construction and maintenance works. For large scale
projects, specialized and emergent works like closure works, flood works etc. separate rates may be
determined by, the Chief Engineer of the Department concerned.
7 This Schedule will not be applicable to the agreements and work orders already in vogue and these
will continue to be operated on the basis of the previous Schedule till their completion.
8 The areas in the state have been sub-divided into the following two zones :-
PLAINS
Area of all districts of Punjab excluding sub-mountainous region but including Chandigarh and
Municipal areas/notified areas of towns of the Sub-mountainous region and road land width of
Ambala-Chandigarh-Hoshiarpur-Pathankot-Madhopur-Jammu road.
SUB-MOUNTAINOUS REGION
Sub-mountainous area includes the North Eastern side of Ambala-Chandigarh-Ropar-Garhshanker-
Hoshiarpur-Dasuya-Mukerian-Pathankot-Madhopur-Jammu road.
(i)
The works at New Delhi and Delhi shall be carried out on the basis of C.P.W.D. Schedule of Rates
and specifications.
9 The schedule of Rates, 2010 is based on detailed analysis of rates for each item of work.
10 The rates given in this Schedule are based on the latest edition of the Punjab P.W.D. specifications
including subsequent Addenda and Corrigenda issued from time to time for all chapters except
Chapter No.21, 22 "Bridges," Chapter No.24 "Road work" for which the specifications of Road and
Bridge work evolved by the roads wings of the Ministry of Road Transport & Highways Published by
the Indian Roads Congress New Delhi, are to be adopted. The rates in respects of "Electrical
Installations" Chapter 33 are based on revised specifications, 1985.
11 Unless otherwise specified, the labour rates for various items of construction include handling of
materials within 100 metres. The through rates include all rehandling of materials at site of work and
no payment is due to the contractor on this account.
12 The through rates, given in the Schedule, include the carriage of materials as follows :-
(a) For such materials as timber, and electrical goods, etc., which have to be arranged by the
contractor, the entire carriage is included in the rate, irrespective of the lead. For such materials
as bricks, brick ballast, bajri, sand, stone, bitumen and cinder, extra lead involved beyond 5 km,
is payable as per carriage rates.
(c) For bricks the through rates include the carriage within a radius of 5km. of site of work, if the
source of bricks is within that limit. In case the source is beyond the radius of 5 km. of the site of
work, the through rates include carriage upto first 5 km. measured from source of bricks
irrespective of the fact whether this initial distance consists of katcha and pucca or partly katcha
and pucca. The lead beyond this initial distance of 5 km. will be payable at the rates provided in
the Schedule of Rates for the corresponding subsequent kilometres. For this purpose the
source of bricks shall be the nearest possible working kiln or dump from where the bricks can be
obtained and the resources shall be certified as such by the Sub Divisional Engineer in writing
before releasing the payment.
13 The through rates include all octroi charges, toll tax, VAT, Labour Welfare Cess, turnover tax and
other local taxes etc., paid by the contractor in bringing the material to the site of work.
14 The through rates include the wastage and breakage of various materials during construction.
15 Unless otherwise specified, the labour rates include the cost of water, tools and plants, labour and
materials for scaffolding and cost of good earth for mud mortar and mud plaster wherever required.
16 In case of works below ground level like basement of buildings and public health works such as
sewers, disposal works etc, the rates upto a depth of 4 metres below ground level, shall be the same
as for work in superstructure above first storey. For depths greater than 4 metres, additional rates for
subsequent storeys shall be added. For works which are not deeper than 1.5 metres from ground
level, ordinary rates for works in foundation and plinth shall apply.
17 Where the description of any item is too long, only essential portion may be written in estimates,
tenders contract and measurement books, although it will be deemed to cover the entire item as
described fully in the Common Schedule of Rates.
18 Wherever the column for "Rates" is neither headed by "Plains" nor by "Sub-mountainous Region" the
same may be considered to apply to both the regions.
19 Abbreviations of units, wherever occurring, in the Punjab, P.W.D. Common Schedule of Rates 2010,
are as mentioned here in after:-
(ii)
A. LENGTH
Millimetre .. mm
Centimetre .. cm
Decimetre .. dm
Metre .. m
Decametre .. dam
Hectometre .. hm
Kilometre .. km/Km
B. AREA
Squaremetre .. sq m/sqm
area .. a
hectare .. ha
C. VOLUME
D. CAPACITY
Milli litre .. ml
Litre .. ltr
Kilo litre .. kl
E. WEIGHT
Milligram .. mg
gram .. g
kilogram .. kg/Kg
quintal .. qtl/Qtl
F. DENSITY
H. COUNTING
Number/Numbers .. no/nos
Note :- The abbreviations mentioned herein before are for signify both singular as well as plural number.
MISCELLANEOUS
Ampere .. Amp.
Diametre .. dia.
(i) All items of Punjab P.W.D. Common .. (a) Dimensions shall be measured to the
Schedule of Rates 2010 except as nearest 0.01 metre. However, rounding off the
mentioned below : figures shall not be applicable to conversion
of basic dimensions of material and as
restricted in the P.W.D. Specifications
(Punjab) in force from time to time.
(b) Area shall be worked out to the nearest
0.01 sq m.
(c) Cubic contents shall be worked out to
the nearest 0.01 cu m.
(ii) Loading, un-loading, stacking and carriage. .. Length, breadth and height of stack shall be
measured correct to a cm. Suitable deduction
shall be made to account for voids in loose
stacking according to factor, mentioned in
relevant chapters of specifications or
Schedule.
(iv) Supply and filling cinder on roof including .. Length and breadth shall be measured
light ramming. correct to a cm and average depth to 5mm.
(v) Items of skirting and dados, including that .. Correct to 3 mm where the height of skirting
on risers and treads of stairs of plaster, does not exceed 30 cm and where the height
precast terrazzo tiles, Agra red stone and of skirting exceeds 30 cm, it shall be
of terrazzo, etc. measured correct to a cm.
(vi) Items of skirting and dados, including that .. Correct to 1 mm where the height of skirting
on risers and treads of stairs of white does not exceed 30 cm, and where the height
Makrana Marble, Chittor Black Marble and of skirting exceeds 30 cm it shall be
of Kotah Stone, measured correct to a cm.
(viii) Wood work wrought, planed and fixed for .. In cubic metres nearest to four places of
trusses, chowkats etc. decimal. Length of each piece shall be
measured nearest to a cm and X-sectional
dimensions shall be measured as specified in
Ch. 17 of the Schedule, correct to 5 mm.
21 FOR ROUNDING OFF THE VALUES, THE FOLLOWING RULES SHOULD BE APPLIED.
(i) When the figure, next beyond the last figure or place to be retained, is less than 5, the figure in
the last place retained, shall be left unchanged.
(ii) When the figure, next beyond the last figure or place to be retained, is more than or equal to 5,
followed by any figures, the figure in the last place retained, shall be increased by 1.
23 The implications of tendered premium above or below (plus or minus) the ceiling premium fixed by
the Zonal Committee shall be as under:-
"The percentage tendered premium/abatement shall be added to/subtracted from Zonal Ceiling
Premium only. The percentage so arrived at shall be applicable to the basic rates printed in C.S.R."
IRRIGATION BRANCH
Chief Engineer.
MEMBER SECRETARY
SPECIAL INVITEE
(ii) The payment to the labour on daily wages will be paid as per rate fixed by the Labour Department
as per Minimum Wages Act from time to time.
(iii) The Chief Engineer of a branch, shall have full powers to authorise any increase in the labour
wages for departmental work for any length of time in any particular locality.
(iv) These rates are exclusive of contractor's profit and overheads expenses but inclusive of weekly
rest.
(v) The labour rates taken in this chapter are on the basis of minimum wages in Punjab fixed by
Labour Department, Government of Punjab as per notification of labour deptt. Punjab No. 11645 dt.
30-4-2010.
(vi) The rates of skilled & semi-skilled labour are inclusive of all necessary tools which are normally
carried by them according to trade practice in the locality.
1 2 3
L-1 Air-Conditioner/Refrigerator Mechanic per day
1 2 3
L-20 Fitter, Turner and Pipe Fitter (Ist Class) per day
L-21 Fitter, Turner and Pipe Fitter (2nd Class) per day
L-30 Mason for plaster of paris work (Ist Class) per day
1 2 3
Rates
4
223.36
151.44
190.00
173.76
223.36
190.00
151.44
168.08
151.44
223.36
190.00
151.44
223.36
190.00
200.00
223.36
335.06
164.69
164.69
223.36
190.00
136.69
173.76
164.69
151.44
151.44
181.86
174.53
151.44
223.36
164.69
153.56
149.97
143.81
136.69
181.86
174.53
136.69
223.36
223.36
190.00
225.00
223.36
190.00
151.44
223.36
160.96
335.06
173.76
151.44
(ii) These rates are inclusive of VAT & others taxes as applicable but excluding contractor's profit.
(iii) All the rates in this chapter are for materials at the source and inclusive of cost of any cases/
drums/containers or any type of bag etc. except where specified otherwise.
(iv) Supplies from market shall be obtained after calling tenders or quotations.
(v) Two classes of paints have been provided viz. the ordinary quality paints and special quality paints.
The paints, which are available on the rate contract of the Controller of Stores, Punjab, come under
the category of ordinary quality. The special quality paints will be first quality paints manufactured by
reputed firms like Nerolac, Asian, Berger, J&N, ICI or equivalent, approved by the Engineer-in-
Charge. Normally, in this category, will be included special paints, which have been manufactured by
the firm of a long standing and repute, whose products have proved to be of special quality, by
actual use, on some works. Special quality paint shall be used only, when these are specially
provided in the technically sanctioned estimates.
(vi) While making measurements for payment purposes, suitable deduction shall be made for voids to
account for loose stacking of aggregates/boulders as stipulated in the relevant specification.
Sr. Description Unit Basic
No. rates
1 2 3 4
M-1 Aggregates (at quarry site):-
1 2 3 4
(ii) 10mm to 11.2mm nominal size. cum 239.66
(h) Screening ,Stone ballast, shingle or kankar (Labour only). cum 30.00
1 2 3 4
(c) Semi Corrugated sheets 6mm thick. sqm 199.06
M-5 Ballies :-
M-6 Bamboo :-
1 2 3 4
(viii) CRMB-55 (PACK) t 40339.69
(c) Felts -
(i) Bitumen felt, Fibre base, self finished type-2 grade-I. sqm 102.38
(ii) Bitumen felt, Hession base, self finished type-3 grade-I. sqm 106.93
(iii) Bitumen felt, Hession base, self finished upto 3, grade-II. sqm 111.48
1 2 3 4
(i) Hard wire brushes (14 gauge) size 200mm x 63mm x 40mm wires
raised & fixed in wooden case complete in all respects. each 22.75
(iii) Katool Brushes (size 250mm x 63mm) of 75mm Coir raised and
fixed in wooden case complete in all respects). each 22.75
(iv) Soft brushes (size 225mm x 63mm) with 63mm raised hair fixed in
wooden case complete in all respects. each 22.75
(a) Bricks 22.86cm x 11.11cm x 6.83cm hand moulded at kiln site for all
Districts. 1000 nos 2800.00
(b) Modular brick tiles 19cm x 9cm x 4cm for roofing, flooring, tile masonary
and canal lining at kiln site 1000 nos 4000.00
(c) Tiles 22.86cm X 11.43cm X 3.81cm hand moulded at kiln site for all
Districts. 1000 nos 2850.00
(d) Brick bats from well burnt or burnt bricks. cum 307.50
1 2 3 4
M-14 Cast iron rain water pipe non pressure ISI Marked :-
(i) C.I. Rain water pipe (Non pressure) 100mm dia. m 576.03
M-16 Cinder 12.5mm nominal size screened at site (I.S. 2686-1977). cum 358.31
(c) Hasps & staples (Safty type) Anodized aluminium Mat Finish
1 2 3 4
(e) Tower Bolts (Barrel type) Anodized aluminium Mat Finish
(f) Commercial ply wood BWP grade 4mm thick 3 ply ISI Marked at site of 432.25
work. sqm
(C) Commercial Ply on one face & Teak Surface on other surface
M-21 Galvanised, iron sheet (0.80mm) plain or corrugated at site of work. t 69150.00
1 2 3 4
(a) Plain
(b) Frosted
M-29 Lime
M-30 Lubricants
1 2 3 4
(ii) Compressor oil per ltr 93.60
M-32 Marble piece for crazy floor 19mm to 20mm. qtl 159.25
1 2 3 4
M-35 Niwar
Distempers
(b) Oil
1 2 3 4
(vi) Methylated spirit, without container. ltr 39.81
(ix) Ready mixed emulsion paint for plastered or concrete surface (in all
shades). ltr 188.48
(x) Ready mixed exterior paint for plastered or concrete surface (in all
shades). ltr 192.81
(xi) Ready mixed exterior paint for metalic surface (in all shades). ltr 188.48
(xiii) Ready mixed paint for wood work or wooden surface in (all shades.)
ltr 192.81
(xviii) Roofing white ready mixed paint for corrugated sheets. ltr 115.00
(xix) Roofing red grey or green ready mixed paint for corrugated sheets. ltr 187.69
1 2 3 4
(ii) Red chocolate orange buff or yellow paint (Red oxide of iron) Light
shades. kg 568.75
(e) Primers
(f) Polish
(g) Varnish
(h) Miscellaneous
(i) Rolling shutter made of 80mm x 1.25mm machine rolled laths. sqm 1649.38
1 2 3 4
(iii) 27.5 cm. long wire spring, grade No.2 for rolling shutter. each 489.13
(v) Exceeding 11.20 up to 16.80 sqm area of door Extra for mechanical
devices chain and cranked operation for operating rolling shutters.
sqm 398.13
(a) Clean & screened sand including removal of over-burden of soil to expose
the sand quarry up to the depth of 30 cm, if necessary within 30 metres
excluding washing but including royalty. cum 52.75
(b) Clean and screened sand within 30 metres excluding washing but
including royalty where removal of over-burden of Soil above 30 cm depth
is necessary. cum 58.03
(c) Clean, sharp and coarse sand from the following quarries (including
royalty etc.):-
M-42 Steel Fe-415, Fe-500, Fe-550 (ISI Marked).(Ex Shop in local Markete)
1 2 3 4
(e) Joists qtl 3796.00
(h) 25mm x 25mm Tubelor Hallow section 1mm to 2.5mm thick qtl 4212.00
M-43 Miscellaneous
Surkhi
(a) Surkhi prepared from well burnt bricks, ground and Screened at
source. cum 633.00
M-44 Tiles
M-45 Timber
(a) Cheel
1 2 3 4
(i) In sleepers. cum 58012.50
M-46 Wire Gauge 22 gauge 12x12 mesh of (140 G gauge) at site of work . sqm 255.70
M-47 Fire Bricks size 22.86cm x 11.11 cm x 6.83 cm. 1000 nos 10000.00
1 2 3 4
M-61 Main Runner 4' M.F.-5 m 65.27
M-65 Metal rawl plug and screw for fixing parameter @ 450mm for fixing ceiling
angle. each 9.49
M-74 Vitrified floor tiles 600mm x 600mm x 10mm size with 3mm glazzing top
premium quality with water absorption less than 0.08% and conforming to
IS: 15622 of approved make in all colours and shades.
sqm 540.00
M-75 Vitrified floor tiles 400mm x 400mm x 10mm size with 3mm glazzing top
premium quality with water absorption less than 0.08% and conforming to
IS: 15622 of approved make in all colours and shades.
sqm 350.00
1 2 3 4
h) Kunda Chapka each 7.96
M-78 (a) PCC Kerb M-20 Hydraulic made size 300x375x150 each 73.94
(b) PCC Kerb M-20 Hydraulic made size 300x300x150 each 62.56
(ii) Where the lead for loading and unloading is more than the lead specified in the following rates, this
should be paid at carriage rates (Chapter No. 5) for second and third chains of 30 metres length as
the case may be.
(iii) The following rates do not provide for any special arrangements such as provision of mechanical
equipment for loading purposes. The unloading of heavy machinery or consignments requiring crane
work or special arrangements, will be done departmentally or paid for on the merit of each case.
(iv) While making measurements for loading, unloading or stacking suitable deductions shall be made to
account for voids in the loose stacking according to the factors mentioned in the relevant
specifications of materials as given in chapter No. 3 of the P.W.D specifications.
(v) The rates of loading, unloading and stacking shall also include the loading, unloading and stacking
of containers in which the materials are contained. For instance, if 100 tonnes of bitumen are loaded
or unloaded in 160/200 litres drums, the net weight of bitumen will be 100 tonnes and weight of the
drum will be over and above this weight. Nothing extra will be paid for the weight of the bitumen
drums which are supposed to be carried in addition to the bitumen with in the same rate.
(vi) Bricks and tiles shall be properly stacked in vehicles and not dumped. While unloading these shall
be directly placed into stacks and not dumped on the ground and then stacked.
(vii) The rates of item No. 4.29 to 4.40 are not payable over and above the rates of item No. 4.3, 4.7, 4.9
to 4.11 and 4.20 to 4.24.
(viii) Where the earth work is involved more than 100 cum than no unloading will be paid because
unloading shall be done by tipping.
Sr. No. Description Unit Rate for
loading into
wagons,
Trucks or
boats within
15 metres
lead.
1 2 3 4
By Mechanical Means
4.1 (A) Stone (building or pitching) Sand, Earth, Fly Ash,
Bajri, Shingle, Spalls, Brick bats, Brick ballast and
Stone metal. cum 15.22
1 2 3 4
1 2 3 4
By Manual Means
4.1 (B) Stone (building or pitching) Sand, Earth, Fly Ash,
Bajri, Shingle, Spalls, Brick bats, Brick ballast and
Stone metal. cum 16.80
4.3 Bricks 22.86 cm. size (including stacking) 1000 nos 39.20
4.9 M.S. Bars, structural steel G.I. pipes and specials, C.I.
manhole covers, steps and other castings and other
ancillary items like lead, hemp-yarn etc. including stacking. t 56.00
4.10 (a) 200 Litres barrel full including stacking. each 7.00
4.11 Small packages of store up to one qtl including stacking. qtl 5.60
4.12 Timber sleepers (Standard sizes and by manual Labour) 100 nos 112.00
1 2 3 4
(a) Heavy above one tonne if crane or any other suitable
device is arranged by the contractor. t 168.00
(b) (i) Heavy above one tonne if crane or any other suitable
device is arranged by the Deptt. t 44.80
4.15 Ballies :-
4.16 Shuttering :-
4.18 Petrol 10 litre tins including checking and weighing. 100 nos 39.20
1 2 3 4
(i) Upton 300mm dia bore
t 56.00
Stacking within 15 metres of the unloading points into stacks of specified sizes.
4.30 Tiles
1 2 3 4
4.34 M.S Bars, structural steel G.I. pipes and specials, C.I
Manhole covers, steps other castings and other ancillary
items like lead, hemp-yarn etc. t 28.00
ch as provision of mechanical
r consignments requiring crane
on the merit of each case.
Rate for
unloading from
wagons non-
tipping trucks or
boats including
clearing 1.5
metres away
from the Rail or 6
metres away
from the water
edge and
excluding
stacking unless
otherwise stated.
4.90
2.60
9.80
19.60
39.20
47.60
28.00
168.00
184.80
8.40
30.80
25.20
44.80
5.60
4.20
5.60
95.20
168.00
44.80
84.00
56.00
56.00
56.00
67.20
84.00
67.20
179.20
358.40
28.00
39.20
78.40
43.40
86.80
130.20
43.40
43.40
43.40
43.40
ed sizes.
CARRIAGE
Notes :-
(i) The rates for carriage of materials manually upto 0.50 km and by mechanical means for every km
lead, have been given. The actual lead is to be paid if the lead is in fraction, the rate is to be
worked out by interpolation.
(ii) These rates are inclusive of all taxes and contractor's profit.
(iii) These rates are worked out keeping in view the Hon'ble Supreme Court directions to stop
overloading. These rates are worked out taking into consideration the stipulated load to be carried by
the vehicle. If during the execution of work, it is found that over-loading of material is carried by the
agencies then the carriage rates are to be reduced by 50% and the recovery will be made from the
bill of agency suitable condition to this effect is to be provided in the DNIT.
(iv) Unless otherwise stated, the carriage rates do not include loading unloading and stacking for
purposes of measurements.
(v) For carriage of materials on river choe beds, 23 percent extra over the basic rates of kilometres
concerned, should be paid for actual river or choe bed-length involved.
(vi) For carriage of materials on unmetalled roads, 20 percent extra on the basic rates of kilometres
concerned excepting those for item No. 5.3 to 5.5 should be paid.
(vii) For carriage in sub mountainous area, the SE concerned may increase the carriage rates suitably
upto maximum of 30% of the rates provided for the plains, in case he is satisfied that the existing
schedule rates are not workable.
(viii) For carriage of lengths above 6 metres of heavy steel sections like RS Joists, rails etc. which cannot
be easily bent, increase the rates for steel in item No. 5.2 by 50 percent.
(ix) Carriage work if done by boats shall be paid at the same rate as given in this chapter for carriage by
road.
(x) Carriage rates of all materials carried in the containers include the carriage of containers in which the
materials are carried. Only the net weight of material carried, is payable excluding the weight of
container.
(xi) While making measurements of materials for the purposes of payment for carriage, suitable
deduction shall be made to account for voids in loose stacking. The factor will be different with
different materials and may be ascertained from the relevant specifications of that material, as given
in chapter No. 5 of PWD specifications.
(xii) The Superintending Engineer concerned may sanction the approved rates of Truck operators Unions
in specific and emergent cases, in case he feels that the existing schedule rates are not workable.
(xiii) The rates under item No. 5.6 do not provide for special carriage arrangements like cranes, trailors
etc. Carriage of machinery not covered by this item should be paid at special rates to be determined
after inviting quotations or tenders or the work may be got done by employing departmental labour.
1 2 3 4
5.1 (i) Surkhi, Sand, Earth, Fly Ash, Bajri, Ballast, Stone Boulders,
Kankar and Building Rubbish.
For subsequent chain per chain of 30 metres upto 0.50 km cum 2.62
(ii) Cement
(iv) M.S. Bars, steel, coal, lime G.I. pipes and special C.I.
manhole covers, steps and other castings and ancillary
miscellaneous items like lead, hemp yarn etc.
(v) Timber
For subsequent chain per chain of 30 metres upto 0.50 km cum 1.50
2nd and 3rd chain, per chain of 30 metres 1000 nos 10.50
For subsequent chain per chain of 30 metres upto 0.50 km 1000 nos 7.50
2nd and 3rd chain, per chain of 30 metres 1000 nos 16.87
For subsequent chain per chain of 30 metres upto 0.50 km 1000 nos 9.00
2nd and 3rd chain, per chain of 30 metres 1000 nos 10.50
For subsequent chain per chain of 30 metres upto 0.50 km 1000 nos 5.62
5.2 (i) Earth,Surkhi, Sand, Earth, Fly Ash, Bajri, Ballast, Stone
Boulders, Kankar and Building Rubbish, Earth.
(ii) Cement
2.0 km t 43.12
3.0 km t 54.75
4.0 km t 64.12
5.0 km t 72.00
11.0 km to 20 km t 6.75
21.0 km to 40 km t 4.10
41.0 km to 60 km t 3.70
2.0 km t 55.50
3.0 km t 71.25
4.0 km t 84.75
5.0 km t 97.00
2.0 km t 69.00
3.0 km t 81.00
4.0 km t 91.50
5.0 km t 101.25
11.0 km to 20 km t 5.62
21.0 km to 40 km t 3.37
(v) Timber
(ix)(a) Cast iron pipes 80mm i/d (Truck load 8.50 tonnes)
2.0 km t 98.25
3.0 km t 106.50
4.0 km t 114.75
5.0 km t 123.00
11.0 km to 20 km t 5.65
21.0 km to 40 km t 4.12
41.0 km to 60 km t 2.35
(b) Cast iron pipes 100mm to 150mm i/d (Truck load 7.0
tonnes)
2.0 km t 122.25
3.0 km t 132.00
4.0 km t 141.75
5.0 km t 151.50
11.0 km to 20 km t 6.75
21.0 km to 40 km t 4.87
41.0 km to 60 km t 3.04
(c) Cast iron pipes 200mm to 350 mm i/d (Truck load 5.50
tonnes)
2.0 km t 168.00
3.0 km t 180.75
4.0 km t 193.50
5.0 km t 206.25
11.0 km to 20 km t 7.12
21.0 km to 40 km t 6.00
41.0 km to 60 km t 4.05
(d) Cast iron pipes 400 mm to 600 mm i/d (Truck load 4.75
tonnes)
2.0 km t 206.25
3.0 km t 220.50
4.0 km t 234.75
5.0 km t 249.00
11.0 km to 20 km t 7.50
21.0 km to 40 km t 6.75
41.0 km to 60 km t 5.05
2.0 km t 135.00
3.0 km t 146.25
4.0 km t 157.50
5.0 km t 168.75
11.0 km to 20 km t 6.75
21.0 km to 40 km t 5.25
41.0 km to 60 km t 4.05
2.0 km t 186.00
3.0 km t 201.75
4.0 km t 217.50
5.0 km t 233.25
11.0 km to 20 km t 8.25
21.0 km to 40 km t 7.50
41.0 km to 60 km t 6.05
2.0 km t 369.00
3.0 km t 399.00
4.0 km t 429.00
5.0 km t 459.00
11.0 km to 20 km t 24.37
21.0 km to 40 km t 15.00
41.0 km to 60 km t 9.45
(xii)(a) S.W. pipes 100 mm to 200mm i/d (Truck load 4.50 tonnes)
2.0 km t 186.00
3.0 km t 201.75
4.0 km t 217.15
5.0 km t 233.25
11.0 km to 20 km t 8.25
21.0 km to 40 km t 7.50
41.0 km to 60 km t 6.05
(b) S.W. pipes 225mm to 450mm i/d (Truck load 4.00 tonnes)
2.0 km t 206.25
3.0 km t 225.00
4.0 km t 243.75
5.0 km t 262.50
11.0 km to 20 km t 9.00
21.0 km to 40 km t 8.62
41.0 km to 60 km t 7.40
2.0 km t 124.50
3.0 km t 134.25
4.0 km t 144.00
5.0 km t 153.75
11.0 km to 20 km t 7.50
21.0 km to 40 km t 4.87
41.0 km to 60 km t 3.05
(b) RCC pipes 200mm to 300mm i/d (Truck load 6.50 tonnes)
2.0 km t 129.00
3.0 km t 139.12
4.0 km t 149.25
5.0 km t 159.37
11.0 km to 20 km t 7.87
21.0 km to 40 km t 5.25
41.0 km to 60 km t 3.00
(c) RCC pipes 350mm to 450mm i/d (Truck load 6.00 tonnes)
2.0 km t 139.12
3.0 km t 150.00
4.0 km t 160.87
5.0 km t 171.75
11.0 km to 20 km t 7.87
21.0 km to 40 km t 5.25
41.0 km to 60 km t 4.35
(d) RCC pipes above 450 mm i/d (Truck load 5.0 tonnes)
2.0 km t 168.75
3.0 km t 181.90
4.0 km t 195.00
5.0 km t 208.15
11.0 km to 20 km t 9.00
21.0 km to 40 km t 6.35
41.0 km to 60 km t 5.40
(a) Mazdoor load upto 40 kg and distance upto 3.0 km Each 60.00
5.5 Carriage over short distance of small consignments, upto 2.0 qtls in
weight including loading, un-loading and stacking.
(ii) Exceeding 150 metres and upto 300 metres Piece 300.00
(ii) Add for every 300 metres but up to 1200 metres t 22.50
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km
per km