Bwsi Group of Companies Project Monitoring Sheet For Pipelaying Activity Responsible Person Attachments/ Forms Signatories Duration (Days) Seq No
Bwsi Group of Companies Project Monitoring Sheet For Pipelaying Activity Responsible Person Attachments/ Forms Signatories Duration (Days) Seq No
Bwsi Group of Companies Project Monitoring Sheet For Pipelaying Activity Responsible Person Attachments/ Forms Signatories Duration (Days) Seq No
Seq
Activity Responsible Person Attachments/ Forms Signatories Duration(Days)
No.
16 Contract, NOA Signing SVP/ PMDM NOA & Contract agreement SVP / PMDM / Contractor 1
17 Preparation of Advance Payment Billing
*For New/Infrequent Contractor (Provisions for Contract agreement/ Billing Documents/
Advance Payment Guarantee Bond/
17.1 submission of bonds are needed upon releasing the PMDM
Performance Bond/ Contractor's All Risk
1
Advance Payment) Insurance
*For Regular/Frequent Contractor (No provisions for
17.2 submission of bonds needed upon releasing the Advance PMDM Contract agreement/ Billing Documents 1
Payment)
BE/Branch
18 Project Stakeout Representative/PMDM/Contractor/AM
1
BE/Branch
19 Preconstruction Meeting Representative/PMDM/Contractor/AM
1
23.1 Punch-listing PMDM/Contractor/BE Punchlist form BE/PMDM/ Contractor 1 To be conducted two days after project completion
23.2 Rectification of Punch List Contractor Punchlist form BE/PMDM./ Contractor 3 Contractor to start one day after the punch-listing
23.3 Final Inspection PMDM/BE/ BM/ OS/Contractor Final Inspection Report BE/PMDM/ Contractor 1
23.4 Final Quantification PMDM/Contractor/BE Final Quantification BM/BE 1 To be conducted one day after punch-list rectification is completed
23.5 Materials Inventory BE/Contractor/ Warehouseman/ BA Materials Inventory form Warehouseman/BM/ BE 1 To be conducted one day after final quantification is completed
23.6 Turnover of Unused Materials Contractor/ Warehouseman MRW Contractor/ Warehouseman 1 To be conducted one day after materials inventory is completed
DAR
Hydro Form
24 Preparation of Final Billing BE
Billing Forms & Docs
BE/PMDM /Accounting 3
Certificate of Completion
1 PRE-CONSTRUCTION MEETING
2 PROJECT STAKE-OUT
4 BIDDING
5 NEGOTIATED CONTRACT
6 EXCAVATION/BACKFILLING
7 PIPELAYING
8 PIPE FITTING
9 HYDROTESTING
10 RESTORATION