O'HARA - Quick Guides To The Evaluation of Orebodies PDF
O'HARA - Quick Guides To The Evaluation of Orebodies PDF
O'HARA - Quick Guides To The Evaluation of Orebodies PDF
ABSTRACT the conditions likely to cause high capital and operating costs
are known from knowledge of the local topography, climate or
Annual mining revenue can be computed by formulae relating accessibility, or can be assessed by tests on core samples, as
metal prices, smelting schedules, concentrate grade and soon as the orebody has been outlined by drilling .
recovery to known ore grade and an assessment of core A more accurate estimate of over-all project capital cost and
samples. Operating costs at different daily tonnages are related operating cost can be made from a summation of items of cost
to orebody shape, mining method, milling process and general after judging the effect of specific local conditions on each
plant services. Capital costs are related to sizing of mining item of capital and operating cost. This paper offers guides in
equipment, mine development, plant-site topography, climate judging the effect of local conditions on the sizing and 1978
and accessibility, plant services and personnel housing. cost of specific items of capital cost and operating cost and
Introduction operating cost of mine projects. When the specific items of
capital cost and operating cost are totalled ~nd measu~ed
A crude guide to the average 1978 cost of mine projects is against expected net revenue and taxes over the life of the rmne
shown in Figure 1, but the costs of many mine projects have
using the net-present-value or discount-cash-flow methods, the
differed widely from the graphed average costs of $800,000 result should show whether the mine project development is
"[0.6 for underground mine/mill projects and $400,000 "[0.6 for
clearly feasible, doubtfully feasible or clearly uneconomic. If
low-grade open-pit mine/mill projects.
the development of the mine project is clearly feasible, or pro-
High mine project costs and high operating costs are
bably feasible, a detailed feasibility study by experienced co.n-
characteristic of open-pit mines with high stripping ratios,
suiting engineers should be commissioned before any financial
underground mines with thin orebodies, mills with complex
commitments are made; but if project development appears to
metallurgy, and projects located in isolated regions with severe be uneconomic, the time and cost of a detailed feasibility study
climate, mountainous topography, and lacking access to ex- is not warranted.
isting roads, towns and electric power. When none of these
The chief variable affecting all items of capital cost, revenue
adverse conditions prevailed, the mine project cost was and operating cost is the daily tonnage of ore that is treated by
typically much less than the graphed average cost. Virtually all the process plant. The guides to capital and operating cost of-
fered in this paper are based on the assumptions that the pro-
cess plant will be operated continuously for seven days per
week but mining operations and crushing plants will operate
T.A. O'Hara for only five days per week, with only necessary maintenance
services on weekends. Thus, the daily ore tonnage mined and
T. Alan O'Hara was born in New crushed will be 40010 greater than the daily ore tonnage milled.
Zealand and graduated with B.Sc.,
B.Eng., A.O .S.M. and M.S. degrees 260
from the Universities of New Zealand,
Otago and Missouri. He immigrated 240
to Canada in 1947 and for the next 17
years was employed in mining
engineering and mine operations at
Cominco Ltd., San Antonio Gold Mines Ltd ., Hudson Bay Mining
and Smelting Co ., Limited and Upper Canada Mines Ltd .
. In 1946, he joined the consulting engineering firm of Wright
Engineers Limited and , as staff consultant, he was engaged in field in-
vestigations, feasibility studies and project design for mining projects
in Canada, Mexico, Australia, Peru, Bolivia, Ireland, France, Moroc-
co and Iran.
Mr. O'Hara returned to Hudson Bay Mining in 1970 and for the
last nine years has managed the Development Group of senior
engineers responsible for the evaluation of major mining and
metallurgical projects, and corporate acquisitions for Hudson Bay
Mining and Smelting and Anglo American Corporation of Canada.
Keywords: Orebodies, Evaluation, Open-pit mines, Underground
20
mines, Process plants, Capital costs, Operating costs, Revenues,
Equipment, Storage, Transportation, Housing , Manpower, Cost for-
2000 5000 10000 15000 20000 30000
mulae.
FIG I. T = TONS MINED a MILLED DAILY
;;:;
sF
1.5
~<v<v
~
(jll"\'"
The cost of site preparation , as shown in Figure 2, will depend
on the area, the topography and tree growth on the site of the
proposed open pit, waste dumps and process plant. The area
, "\
'"
a: y..~~~ o~ of the site and length of the access road to be prepared will :
[ I'!'
0{ ffF"\' typically vary with the square root of the size of the open-pit
a:
c,
w
lO r rfS!",<{Y' • ':J
r,"\Co mine as expressed in terms of the tonnage of ore and waste (Tp)
>-
iii ~ c,o to be mined daily.
1<-<:>
>- I
a: "GO
z
w
r '1'
Pre-Production Stripping Costs
c,
0
u, 5 r
I Figure 3 shows the cost of stripping soil and rock overburden,
0
>- Ai assuming that soil will be stripped by contractors using
~ .3 scrapers, and rock overburden will be removed by drilling,
u
.2
blasting , loading and haulage of rock by readily available sizes
0 .1
~!- ' I I ( I • of drills, loaders and trucks. Because the size and condition of
20000 4 0 000 60 0 00 80 0 0 0 10 0 0 0 0 equipment readily available for rock overburden stripping is
FIG 2 Tp = TONS OF ORE a WASTE PER DAY rarely suitable for production mining, the cost of this equip-
ment must be amortized over the pre-production period.
Open-Pit Equipment-Sizing and Cost
20 OPEN PIT PREPRODUCTON STRIPPING
The most important items of pit equ ipment are usually the pit
IB shovels and haulage trucks, and because the size and number
of haulage trucks depends on the size and number of shovels,
16 selection of shovel size affects all other items of pit equipment.
Figure 4 shows the typical selection of shovel size and number
14
of shovels for different daily pit tonnages. Although some pits
may have conditions suitable for partial replacement of
shovels by front-end loaders at lower capital cost and improv-
Cost " $ BOO T~' (Soi l) ed flexibility, this study assumes that only shovels will be used
" $ B500 T.O' ( Rock)
for loading rock.
The size of haulage trucks should be matched against the
shovel size so that a unit number of shovel loads fills the
waiting truck. In general, the truck size in tons is about nine
times the shovel size (in cubic yards) for small shovels, and
--
about ten times the shovel size for large shovels as shown by
SOIL OVERBURDEN the formula t = 8 SJ.I .
The cost of open-pit equipment is shown in Figure 5 as a
12 3 45 6 7 function of tons of ore and waste mined daily (T»)
FIG. 3 To = TONS OF OVERBURDEN (MILLIONS) Figure 5 shows that the two major items in pit equipment
cost are the fleet of shovels, each of which costs about
12
SIZES 6 NUMBER OF PIT SHOVELS
(5 ) S ize = 0 .13 T,IO. 4 II
TpO.8
No. " 0 007
S 10
TRUCK $ IZ£ (r)= 8 S l 1 In ton s
~ 9
Vl
z
s..J B
..J
~ 7
z
;: 6
z
w
~ 5
5
~ 4
!::
a. 3
~
0007 T,
S
°• ;t
S 230 000 Son
•
BB
$230,000 SO.73, and the fleet of trucks, each of which costs
320
about $9,000 to.8' .
300
Open-Pit Maintenance Facilities
The cost of building and equipping facilities for the garaging ~ 250 ~
and maintenance of open-pit equipment will be dependent I-- I--
chiefly on the sizing and numbers of pit haulage trucks . The lJJ
lJJ lJJ
W
u, u,
haulage truck size varies directly with T pO.44, and the number lJJ 200
of haulage trucks varies directly with T pO.36. The cost of c:: ~
«
::> 15 I--
maintenance facilities will vary with the square of haulage 0 u,
(f) «
truck size and directly with the number of trucks required, and 150 14 I(f)
~
consequently the cost of maintenance facilities will vary ap- « 13 u,
0
proximately with the 0.3 power of tons of ore and waste mined lJJ
a:: 12 a::
daily, as shown in Figure 15. « 100 A (sq. tI)· 17 TO." w
I-- 11 I--
u, w
[FOR RECTANGULAR SHAFTS WITH SETS] 10 ~
Capital Cost Estimates- «
I «
15
Underground Mines (f)
50 d (in fl.)' 5.2 T O. I •
[FOR CIRCULAR CONCRETE SHAFTS]
If the orebody is amenable to underground mining, knowledge
or" the shape and attitude of the orebody will enable a judg-
ment to be made on: the hoisting distance necessary to extract 1000 2000 3000 4000 5000 6000 7000
the lowest ore, and the average stoping width of the mineable FIG 6 TONS OF ORE HOISTED PER DAY (T)
ore.
If the nature of the ore boundary and the competence of the
wall rock are known from drill core samples, a judgment can Nt ~j Wi ~i roi ~i ~I oj ~i ~i mi N i
~i Wi
be made on the appropriate stoping method.
It is assumed that almost all underground orebodies can be
~ ! ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ m
(f) d • DIAMETER OF CONCRETE SHAFT REQUIRED
developed by vertical shaft access and lateral levels, but it is 5 2 .2
CONCRETED SHAFT 01
recognized that under some conditions development by inclin- ::J
CIRCULAR dO'+ $228 F d .
~ 2.0
ed ramps may be more appropriate. Nevertheless, the capital 80 0 0 0
~ COST" '
costs estimated for development by a vertical shaft could be ~
[F • Fl. of shaft sunk]
used as a measure of whether or not alternative development
methods would be preferable. Generally these alternative t« 1.5 o AO.'8>+ ~B5 .. F AO...
methods would be appropriate only when they are both Vi COST ' $60,00 ECTANGULAR SHAFT
u, Tlt/l8ERED R
physically feasible and less costly than shaft development. o
The capital cost estimates and operating costs for t 10
underground mines are based on the higher productivity at-
tained by mechanized equipment for drilling, drifting, raising,
§
stope mucking, drawpoint mucking and trackless haulage. ~
52
This equipment would be suitable for room-and-pillar stopes ~ 0 .5 A' SQ. FT OF RECTANGULAR SHAFT REQUIRED
over 8 ft high, and for blasthole stopes and cut-and-fill stopes 15 N ~ m ~ ~ ~ ~ 2N ~ ~ ~ ~ ~ ~
over 15 ft wide. A partially mechanized mine would attain I-- N w m ro ~ ~ ~ N N ~ Q ro ~
~ ~ ~ 2 ~ ~ ~ ~ ~ ~ ~ ~ ~
lower productivity for shrinkage stopes, for blasthole stopes
and cut-and-fill stopes less than 15 ft wide, and for room-and-
S 1000 2000
N
3000 4000 5000 6000 7000
pillar stopes less than 8 ft high, and consequently manpower FIG. 7 T c TONS OF ORE TO BE HOISTED PER DAY
requirements and operating costs are substantially higher in
such mines.
(Fd) of 8- by 8-ft drift or the equivalent in costs for ramps,
Cost of Shaft Sinking raises and miscellaneous excavations.
Fd (in feet of equivalent 8x8 drift) = 270 T/W o.8 , where T is tons of
If the ground through which the shaft is to be sunk is known to
ore milled daily and W is average stoping width in feet.
be fractured, waterbearing, or weak and incompetent, the
shaft will probably need to be a circular concrete-lined shaft. The average cost per foot of 8x8 drift, as of January 1979, is
If the shaft sinking will be in strong competent rock, a rec-
estimated to be about $150, including all direct labour and
tangular shaft with multi-compartment shaft sets 8 feet apart material costs, as well as proportionate amount of general ex-
and blocked to the bare rock excavation will probably be most penses (administration, supervision, general supplies, fringe
appropriate. The size of the rectangular shaft, or the diameter benefits, etc.) incurred during mine development.
Capital cost of mine development = S.w,OOO T/Wo.8 (Fig. 8).
of concrete shaft, required to hoist the daily tonnage of ore
and service the mine is shown in Figure 6. It will be noted that "mine development" does not include
The cost of shaft sinking, as shown in Figure 7, consists of the driving of stope development drifts, crosscuts and raises,
mobilization and demobilization costs (which will be virtually because this is essentially an operating cost associated with the
independent of shaft sinking distance) as well as unit shaft need to develop future new stopes to replace those stopes cur-
sinking costs, including shaft supplies per foot of sha ft. rently in production.
"i
~-=
20 180
~
...
,~
18 160
{!
~
16 140
>-
u,
~~I
, ~_\
ri'
;; 120
;; 14
>-
>- :r
CJ)
0 12 ~
:r
10 0 _\'1' --,
o
>- w 80
z
w
;:,
10 ;:,
~
.t'?o/
1.....
0[ ]3•
Heod"ame hei<jhl = 0 25 .0 • 5 5 100
033
6 .3 T .
n, u, 60
0 8 0
-' COST . S 40 ,000 T <{
D = holst drum die
w Woe w
> 6 :r 40
w W is average ore widt h
0
4 20
90
2 .4
2 .0
Io Is hoist diameter in inches
0 .5
1.8
~ 1.6
04
'"
z
01.4 '"
u,
:::J o
d
~
;;;
1.2
5:::;'" 0 .3
t; r ,0 .J
8 ~
8
~ ....~ 0 .2
E6
o
su
«
w :rALLATIONQ!i..:OO~ST:.----
:I: 0 .1
~PR 5.",-",- " , ,-
6 4 .0
1f>o
Z
o
50 :J
..J
~
... ~ 3.0
(f)
u, 40 w
o f=
:J
U
L1 2 .0
w
u
Z
<!
~ 20 Z
W
f- f-
(f) Z
o <i 1 0
u
::;: .8
1.0 u,
o 6
f- •
(f)
o 2
U
100 0 2000 3000 4000 5000 6000 7000
500 1000 2000 3000 4 000 5000 6000 7 00 0
FIG. 14 T ' TONS MINED DAILY (UNDERGROUND MINES)
T = TONS MINED PER DAY
10,000 20 ,000 30 ,000 4 0 ,000 50 ,000 60 ,000 70, 000
FIG. 15 Tp ' TONS ORE 8 WASTE DAILY (OPEN PITS)
... 1.0
40
LL
o u,
o
~ 08 V>
o is 3.0
::::; :::;
....J ..J
~
~ 06 Z
z ....- 2 .0 lAI\"O C I
V>
o ,------~
t- u Cost " S 30, 000 T~ ' Fel
lfl
804 Cosrs > $ 40 ,000 T0 3Fs 1.0
Wh«e Fel " 1.0 mild clim:rte
1.8 cold climl2e
....J
Where FS " 10 for f10t sites 2 .5 seere d imote
I':! " I5 fo- moderate slopes
~ 02 ::: 2.5 for steep slopes
u 10 0 0 2000 3000 4 0 00 5000 60 00 70 00
92
It should be noted that the costs graphically shown in Figure
20 allow for sufficient fine ore storage to permit the mill to
operate seven days per week on ore which has been crushed for GRINDING SECTION 8 FINE crlE STORAGE
five days per week. If the crushing plant will be operated each
day that the mill is operating, less fine ore storage will be re- 5 .0
quired and the cost of the fine ore storage and grinding section
will be redu ced by 25070.
4 .0
Flotation and/or Processing Section
The capital cost of installing the processing equipment to con-
centrate the valuable minerals from the waste in the finely 30
ground ore will depend on the type of separation pro cess and
the degree of complexity in the flowsheet. Figure 21 illustrates
2 .0
the cost of the process section for several different types of Cost ' 8 a.ooo T O.T F.
process and flowsheet complexity. When F, = 1.0 so 11 ores 55% - 200 '"
1. 5 medium ores 70 % - 200 IIfI
Thickening and Filtering Section 1.0
1.8 hord ores 80 % - 20 0 ""
Ul
10
requiring mor e complete processing. z
0 CAPITAL COST
The cost of electric power supply depends on the peak load :J 8
-' UTILI TY SUBSTATION • S 35OIKW)Oej
requirements and also on whether the power is generated by a ~
6 LV. DISTRIBUT ION • S 6()(~)(W)o~
coal-fired plant (for large isolated mines) or by diesel ;; DIESEL GENERAT~S • S 4.~KW)O ~
jects consuming a large amount of electric power, the electric u~oOO eobo .ol>oo I~ 2O~OOO ~ ~ooo 4 0'.000
,he, 000 zOoo x:oo «>00 sooo 7hoo 10000 OPEN PIT 6 MILL
utility will typically install the transmission line and stepdown UNDERGROUND MINES 8 MIL L
FIG. 22
transformer station on the assured basis that future revenue T' TONS MILLED PER DAY
from mine plant consumption of electric power will repay the
94
facilities and leisure facilities for 950/0 of the employees at
$12,000 each as well as family accornodation for the remaining
"I. DILUTI ON
5%, consisting of senior staff at $50,000 each, and minimum "I.
JO
townsite facilities at 20% of housing cost : BLA 5 TH Ol E STOPES
community as well as single accommodation for 35% of the >- W ST OPE WIDT H I,.. fEE T
lD 20 A' DIP Of" OREBOQY
employees and housing for townsite service employees will w
0:
cost: 0
u,
Family townsite cost = $55,000 N. 0
15
Z
0
Project Overhead Costs ;:::
::>
..J
A. Feasibility studies, design engineering and technical plan- 0
10
ning: 4% to 6% of all mining pre-production costs , site W
C)
<I
preparation, excavation and road building costs, as well as 6% >-
Typical
Recovery Formulae Cone. Grade
Cu in straight chalcopyrite ores R 100% (1-0.07 Cu·0 .8 ) 28.5% Cu
in oxidized copper ores (sulphides) sco, = 100% (1-0.08 Cu s ·0 .8 ) Variable
in oxidized copper ores (oxides) ncu, = 100% (1-0.40 Cu o·0 .3) Variable
in copper-zinc ores R 100% (1·0.16 CU-Q8) 25.5% Cu
in lead-zinc-copper ores R 100% (1-0.22 Cu·0 .8 ) 22.0% Cu
MoS 2 in straight molybdenite ores R = 100% (1-0.04 MOS2·0 8 ) 88.0 % MoS2
in copper-moly ores R 100% (1-0.06 MOS2·0 8) Variable
Zn in straight sphalerite o res R 100% (1-0.25 Zn·0 .6) 56% Zn
in lead-zinc ore s R 100% (1·0.32 Zn-o·6) 53% Zn
in copper-zinc ores R 100% (1-0.45 Zn·0 .6) 52% Zn
i n copper-lead-zinc ores R 100% (1-0.55 Zn·0 .6) 50% Zn
Pb in straight galena ores R 100% (1-0.13 Pb·0 .8) 60% Pb
in lead-zinc ores R 100% (1-0.18 Pb·0 .8) 53% Pb
in copper-lead-zinc ores R = 100% (1-0.28 PbO.8) 45% Pb
Miscellaneous Ores
Tungsten ores (gravity separat ion) R = 100% (1-0.33 W0 3·0 .5) 75% W03
Nickel in nick el-copper ores R = 100% (1-0.20 Ni·0 .6 ) 10% Ni
Uranium ores (flotation-leaching) R = 100% (1-0.16 U30S·0 .S) 77% U308
Iron ores (gravity-magnet ic) R = 100% (1-1.5 Fe·0 .6) 65% Fe
Precious Metal Ores and Precious Metals in
Base Metal Ores: (head grades in oz per ton) Process
Gold in siliceous ores R = 100% (1-0.013 AU·o.s) Cyanidation only
in pyr ite ores R =100% (1-0.03 Au ·0 .8) Flot.! Roast.!Cyan.
in base metal ores R = 100% (1-0.3 Au ·0 .8 ) Flotation
Silver in straight silver ores R = 100% (1-0.22 Ag·0.6) Flot.!Grav. Separat ion
in base metal ores (-1.0 oz/t) R = 100% (1-0.40 Ag·0.6) Flotation
26 0 500
<n 220
400
"""">-
0
ct:
W
..J
a. 180 :;:
::;;
ur
o
l-
~ 300
ii 140 <l
z
uj
L
a.
0
100 20 0
u,
0
g
60
100
20
FIG. 26
T = TONS MINED PER DAY
96
OPEN PIT MI NE S
:j
C UT 80 F ILL M IN I NG COS T / TON
OPERATING COSTITON
10
LABOUR COST . 58 ~ J Tp.o, . 3'91T ,,· 0 3
LA B O U R/ J O~:> t ~ t'- qQ
SUPPLIES COST " 13 " 0 l'p , O' . 124 1',,'° ' - .')Olp 0 2 20 T °"w ° ~
SUF'PLI£S/TON _ ~2.Q..
z I. Vi IS S ToPt:. ·...,IOT H IN ~1
~
06
0::
W
0-
l-
V} O'
o
U
rr e.
u;
a
SUPPliES COST
>-
02 v>
0 '1
u
1 I
20 ,000 4 0 .000 60.000 80 ,00 0 100, 000 ! OOO 40 0 0 ,000 ~o
rt G 2 9 T· TONS MI N ED PER DAY
FIG 27 T ~ TONS OF ORE AND WASTE PER DAY
22 ~ ~~ ~ ~ LA BOUR COST
20 LABOUR COST/ TON • ~
lTW)o ,
with an allowance of 35l1Jo to cover fringe benefits. The cost of Z 18 SUPPU ES · ~~~ :~ 2
supplies for development, stoping and general mine services o
~ 16
W • ORE WIDTH IN FEET
typically varies with the number of men employed in these
functions . :;;: "
z
Employees Required-Process Plants ~ 12
The number of mill employees and mill staff is shown in Figure ffi '0
0-
32 for differing process flowsheets. Typically, mills treating I-
gold ores will require more employees in the cyanidation pro- IJl
cess than mills using flotation , and mills using selective flota - 8 6
~
b) Electrical services 0.05 Nm (power diesel generated)
c) Electrical services = 0.08 Nm (power generated by coal-fired
plant)
w
>
B. Surface plant services & road maintenance = 0.04 Nm
~ C. (a) Townsite employees = none for existing town
~
(b) Townsite employees = 0.03 Nm (bunkhouse-type mine camp)
k
0 (c) Townsite employees = 0.05 Nm (family townsite-subsidized)
tx
w D. Concentrate transport (contracted out)
rn
3z E. General administration = 0.07 Nm
Total employees N = Nm + (0.14 to O.24)Nm, depending on type of
townsite and electric power supply.
20
98
the best fit of the data to an equation of the form Q = K'P, T i, the K, values were first determined for the most influential
where Q represents the actual data on quantities required or condition T 1 to fit Q = KIT." and then changes in the K.
cost, and T represents the tonnage rate, milled head grade or values were computed to fit the equation KI = K2T 2 Y, so that
other physical condition causing changes in quantities or costs. Q = K2T2YT\' where K2 is a constant.
The x values were determined to yield the lowest range of
variation in K values across the widest range of T values for Because of the inevitable dispersion of data, the
which reliable data were available . The x values tested were mathematical analyses did not rigorously consider each data
within a relatively narrow range which was judged to be consis- point of equal value, but judgment factors were utilized in
tent with technical considerations and operating exper ience. weighting data from individual mine projects according to the
Whenever changes in the quantity Q were judged to result presence or absence of localized conditions that would result in
from simultaneous changes in two physical cond itions T 1 and unusually high or low values for costs or quantities.
International conference on
energy and the environment
Envitec 80, which will be held at the pumps, solar energy systems), alternate and long-range environmental and energy
Dusseldorf Fairgrounds (West Germany), methods of power for both commercial problems. The fair will include over 400
February 11-15, 1980, is the world' s and private vehicles (including new different exhibit s of equipment, proce sses
largest and most comprehensive en- automobile engine design), air, water and and services covering every aspect of en-
vironmental technolog y exposition. Dur - noise pollution control, and other sub- vironment protection and control techno-
ing the fair, an international conference jects that have a direct bearing on today's logy.
will be held on February II, 12 and 13, environmental needs .
There will also be an Environment
1980. Thi s comprehensive conference deals
Info-Center during the full five days of
This meeting will bring together leading with all aspects of the environment as
Envitec 80, which will allow an exchange
authorities from all over the world who related to international, community and
of information among industry, govern-
will present the latest developments in en- industrial needs . It will provide new ap-
ment and science. The Environment Info-
vironmental and energy conservation proaches and immediate solutions to
Center will offer academic institutes, in-
technolo gy. It will cover a wide variet y of many different individual problems. The
dustry associations, government officials
subjects that have a direct impact on assembly of the world's leading author-
and other authorities in the field an op-
many of the world's common problems . ities on energy and the environment is of
portunity to present the results of research
The speakers will represent govern- importance to anyone directly or indirect-
as well as new operational technology. It
ment, industry, research and lead ing ly involved with saving the quality of the
will include open discussions with an ex-
academic institutions from all over the environment. All presentations will be
change of experiences and viewpoints.
world. Th e subjects cover energy and en- simultaneously translated into English as
vironmental policies, current state-of-the- well as other languages. Exhibitors' seminars will also be held
art environmental pro cessing technology, The Envitec 80 International Trade Fair each day during Envitec 80. These
development of alternative energy source s will attract over 30,000 visitors from over seminars will allow the exhibiting com-
and their impact on the environment, coal 50 different countries. The visitors will panies to present and demonstrate new
gasification, industrial pollution control represent a high-level international au- technology and procedures co vering
(toxic gas, dust control, chemical waste dience made up of indu stry execut ives, special subjects. As small-scale forums,
removal and disposal), refuse disposal government (local and national) officials, the seminars will cover specific subjects
and recycling, refuse-fueled power plants, and research and academic institute such as air pollution control, water pollu-
radioact ive waste dispo sal, new energy- representati ves who will com e · to tion control, noise abatement, solar
saving heating methods (new types of heat Dusseldorf to seek solutions to current energy, radioactive waste disposal , etc.