01a-Introduction To Process Plant Design
01a-Introduction To Process Plant Design
01a-Introduction To Process Plant Design
Tanks, Pumps,
Compressors, Reactors, Drums, Reflux, Tanks,
Warehouses, Furnaces, Towers, Strippers, Warehouses,
Hoppers, Exchangers,
Heaters, etc. Filters, Treaters, Baggers,
Piles, etc. Dryers, etc. etc. etc.
Crushers,
Mixers, etc.
http://www.ih.navy.mil/Departments/ord/che-ext-tec-div/index.asp
http://www.tfhrc.gov///pubrds/05jan/02.htm
http://www.netl.doe.gov/technologies/coalpower/cctc/summaries/tampa/tampaedemo.html
http://www.npt.nuwc.navy.mil/facilities/QuietWater/default.htm http://www.pmcd.apgea.army.mil/multimediaviewer.aspx?id=585
1
Product Separation Product Purification
(US DOE) (US OSHA, DOT)
• Drums, Towers,
• Reflux, Strippers,
Filters, Dryers, etc.
Treaters, Sorters, etc.
http://www.nrel.gov/data/pix/searchpix.cgi?
http://www.greensboro-nc.gov/departments/Water/watersystem/treatment.htm http://iforms.osha-slc.gov/dts/osta/otm/otm_iv/otm_iv_2.html
http://pubs.usgs.gov/gip/gw_ruralhomeowner/gw_ruralhomeowner_new.html
http://www.fedcenter.gov/_storage/Photos/176.jpg
http://www.tobyhanna.army.mil/about/certifications/environmental/rcra%20cleanup.htm
Limestone,
Clay, etc.
http://www.msc.navy.mil/sealift/2005/September/katrina.htm http://www.cdc.gov/elcosh/docs/d0200/d000279/ilochap93.html
2
Parties to Plant Process Plant Client
Design • Funds the engineering and construction of the plant
(The 'PIPING GUIDE') • Generally supplies or approves the processes to be used
• Client wants a finished • Accepts the work performed
plant
– Business Case Primary
Concern
– Everyone Else is
Temporary
• Design Engineers
produce highly quality
assured product
definition data
• Construction Realizes
Design
Source:
The 'PIPING GUIDE'
http://www.pipingguide.com
3
Project Organization Project
Design
Groups and
Information
Flow
(Source: The
'PIPING GUIDE')
4
Functional Equipment Characteristics Vendor-Proprietary Equipment
• Describe or specify: • Equipment whose performance is
guaranteed by the vendor.
–Functional requirements for the
equipment • Specified by equipment datasheet in
process design specifications
–Service provided to the process by
package.
the equipment
• Usually designed by first selecting a
–What equipment is supposed to do
vendor who performs testing and
sizing of the item
5
Activity Model of the Oil and Gas Common Status Terms
Production Facility Life-cycle
(ISO 15926) • As-built: Process plant's actual physical
and functional aspects at a specific point
Produce Conceptual
Process Design
Produce Detailed
Process Design
Commission
Plant
Operate Plant
Decommission
Plant
in time
As-approved: Product data provide to
Produce Conceptual
Produce Detailed Construct Plant Maintain Plant Demolish Plant
and approved by client
Engineering Design
(Front End)
Engineering Design Pre-Commission and Equipment and Restore Site
As-specified: Approved data provide to
engineer by client
Suppliers and
Fabricators
Procure and Control Equipment, Material and Services
As-released: Product data officially
provided to anyone
http://www.tc184-sc4.org/About_TC184-SC4/About_SC4_Standards/
6
Maintenance Shutdown/Decommissioning
• Shutting down the
plant
• Preserving it for
later
commissioning or
demolition
• May not include
site remediation
http://splash.metrokc.gov/wtd/southplant/index.htm
http://www1.usaid.gov/iraq/photogallery/gallery_39/photo18.html http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html
http://www.srs.gov/general/busiops/tech-transfer/plant.htm http://www.lm.doe.gov/land/sites/oh/fernald_orig/VImages/PhotoTour/1998/Dec98/Plt6c.htm
http://www.eere.energy.gov/industry/bestpractices/energymatters/full_issue.cfm/volume=37 http://www-als.lbl.gov/als/als_news/news_archive/vol.240_042804.html
Project Schedule
• Duration
• Start Date
• Critical Path Questions
– Sequence of Tasks
such that if any is late
the project is late.
– Can be more than one
http://www.coconino.az.gov/cji.aspx?id=383
7
Course Outline
• Part 1 Pipe Lifecycle
• Part 2 Pipe Fluid Flow & Control
• Part 3 Plant Equipment
• Part 4 Pipe Structural Design
• Part 5 Project Practices & Management
• Part 6 Project