SAIC-A-2016 Pneumatic Test of Reinf Pad, Weld+Ends
SAIC-A-2016 Pneumatic Test of Reinf Pad, Weld+Ends
SAIC-A-2016 Pneumatic Test of Reinf Pad, Weld+Ends
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Re-inforcing pads that will require pneumatic test are provided with at
A1 Best Practice
least a 1/4" tapped vent hole.
A pneumatic test of 173 kPa (ga) (25 psi) shall be applied to the SAEP-311,
A2
reinforcing pad or ring after installation. Para. 3.8.8
The test pressure is then be reduced to 21 - 35 kPa (ga) (3 - 5 psi) for a SAEP-311,
A3
tightness test using a soap solution. Para. 3.8.8
SAEP-312,
B1 Both ends of the weld-Plus-Ends coupling are welded to the pipe. Para. 3.4.13
(Step 2)
SAEP-312,
B2 All of the thrust screw ends are welded over. Para. 3.4.13
(Step 2)
All joints including welded shall be left exposed for visual leak detection SAES-L-150,
C1
during the strength test. Para. 7.3
Visual examination is done with sufficient safe access such that the
SAES-A-004,
C2 component to be inspected is in close proximity to the eye(24").
Para. 6.3.2
(ASME Sec V, Article 10, Para. I-1075 & Article 9, Para. T-952)
The joint/area to be inspected is properly illuminated by natural or
SAES-A-004,
C3 supplemental white light.
Para. 6.3.2
(ASME Sec V, Article 10, Para. I-1075 & Article 9, Para. T-952)
The bubble forming solution is compatible with the temperature of the
test conditions.
(NOTE: As a standard technique, the temperature of the SAES-A-004,
C4
surface of the part to be examined shall not be below Para. 6.3.2
40°F (4°C) nor above 125°F (52°C) throughout the
examination.) (ASME Sec V, Article 10, Para. I-1032 b & I-1072)
Page 1 of 2
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Visual Inspection of Pneumatic Test for Reinforcing Pads,
SAIC-A-2016 25-May-05 WELD-
Sleeves, or Weld-Plus-Ends Couplings
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
SAES-L-150,
C7 Pressure gages showed no loss in pressure.
Para. 5.2
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, (30 June, 2003)
2. SAEP-312, PLIDCO Weld+Ends Couplings, (31 January, 2005)
3. SAEP-311, Installation of Hot Tapped Connections, (29 January, 2003)
4. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (30 September, 2003)
5. ASME Sec V, Nondestructive Examination, (July 1, 2001)
Page 2 of 2