General Conditions of Contract
General Conditions of Contract
1F
Section VI. General Conditions of Contract
Notes on the General Conditions of Contract (GCC)
The GCC provides the general terms and conditions ofthe contract between the Procuring Entity
and the winning bidder.
The provisions of the GCC are to be used unchanged as part of the contract-specific BDs.
To supplement the GCC, the Special Conditions of Contract (SCC) in ANNEX II-l.lG
provide detailed information or requirements on particular provisions of the GCC that are
specific to the contract at hand.
STANDARD FORMAT
TABLE OF CONTENTS
l. Definitions.....
2. Interpretation
3. Goveming Language and Law
4. Communications
5. Procuring Entity's Obligation to Deliver the Site, Materials, Equipment, and
Plans
6. Contractor's Obligations
7. Performance Security
8. Sub-Contracting...........
9. Liquidated Damages
10. Site Investigation Reports
1.2 As-Built Drawings refer to the engineering plans for the structure as actually
constructed and completed under this Contract, considering all variations and
modifications as approved and executed.
1.3 Bill of Quantities refers to a list of the specific pay items of the Works under this
Contract, particularly their identification numbers, descriptions, units of
measurement, and quantities, together with their corresponding unit and total
bid prices.
1.5 contract is the legal agreement between the procuring Entity and the contractor to
execute, complete, and maintain the works. It consists of the documents listed
in GCC Clawe 2.2.
1.6 contract Price is the price stated in the Notice of Award and thereafter to be paid
by the Procuring Entity to the contractor for the execution of the works in
accordance with this Contract.
1.7 contract Time is the allowable period or duration within which the contract
works must be completed, i.e., from the Start Date to the Intended completion
Date as specified in the SCC.
1.8 contractor is the juridical entity whose bid has been accepted by the procuring
Entity and to whom this contract to execute the work was awarded. enterel
into. and approved.
1.9 contractor's Bid is the signed offer or proposal submitted by the contractor
to the
Procuring Entity in response to the Bidding Documents.
l.l2 Defect is any part ofthe works not constructed in accordance with this contract.
1.16 Defects Liability Period is the one-year period after the issuance of the
Certificate of Completion during which the Contractor assumes the
responsibility to undertake the repair ofany defect in or damage to the works at
his own expense as a condition for the issuance ofthe certificate ofAcceptance.
1.17 Drawings are graphical presentations of the works. They include all engineering
plans, supplementary details, shop drawings, calculations, and other information
provided or approved for the execution of this Contract.
1.18 Equipment refers to all machines, tools, facilities, supplies, appliances, and
related items required for the execution and completion of the works provided
by the contractor and which shalr not lorm or are not intended to form part of
the Permanent Works.
1.19 Intended completion Date refers to the date specified in the scc when the
contractor is expected to have completed the works. The Intended completion
Date may be revised only by the procuring Entity's Representative by issuing
an extension of Contract Time or an acceleration order.
1'20 Materials are all supplies, including consumables, used by the contractor for
incorporation in the Works.
1.21 Notice to Proceed is a written notice issued by the procuring the procuring
Entity's Representative to the contractor requiring the latter to begin the worki
not later than the date specified in this Notice.
1.21 Permanent works refer to all permanent structures and all other project
features
and facilities required to be constructed and completed in accordance with
this
contract which shalr be delivered to the procuring Entity and which shall
remain at the Site after the removal of all Temporary Works.
1.24 Procuring Entity is the party that engages the Contractor to carry out the Works
stated in the SCC.
1.25 Procuring Entity's Representative refers to the Ho
PE or his duly authorized representative, identified in the SCC, who shall be responsible
for supervising the execution of the Works and administering this Contract.
1.26 Site is the righrof-way or place provided by the Procuring Entity where the
Works shall be executed and any other place or places which may be designated
in the SCC, or notified to the Contractor by the Procuring Entity's
Representative, as forming part ofthe Site.
1.27 Site Investigation Reports are factual and interpretative reports about the surface
and subsurface conditions at the Site, which are provided by the Procuring
Entity in the Bidding Documents.
1.28 Slippage is a delay in work execution occurring when actual accomplishment falls
below the target as measured by the difference between the scheduled and
actual accomplishment of the Works by the Contractor as established from the
work schedule. This is actually described as a percentage ofthe whole Works.
1.30 Start Date, as specified in the SCC, is the date when the Contractor is obtiged to
commence execution of the Works. It is the same as the effectivity date of the
Contract as stated in the Notice to Proceed. It does not necessarily coincide with
any of the Site Possession Dates.
1.31 Sub-Contractor is any person or organization to whom a part of the Works has
been subcontracted by the Contractor for execution, as allowed by the Procuring
Entity, but not any assignee of such person.
1.32 Temporary Works are works designed, constructed, installed, and removed by
the Contractor that are needed for the construction or installation of the
Permanent Works.
1.33 Work(s) refer to the Permanent Works and Temporary Works to be executed by
the Contractor in accordance with this Contract, including (i) the fumishing of
all labor, materials, equipment and others incidental, necesse[y or convenient to
the complete execution of the Works; (ii) the passing of any tests before
acceptance by the Procuring Entity's Representative; (iii) and the carrying out
of all duties and obligations of the Contractor imposed by this Contract as
described in the SCC.
.,
Interpretation
2.1 In interpreting the Conditions of Contract, singular also means plural, male also
means female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning under the language of this
Contract unless specifically defined. The Procuring Entity's Representative
will provide instructions clarifying queries about the Conditions ofContract.
2.2 If sectional completion is specified in the SCC, references in the Conditions of
Contract to the Works, the Completion Date, and the Intended Completion Date
apply to any Section of the Works (other than references to the Completion Date
and Intended Completion Date for the whole of the Works).
,1 The documents forming this Contract shall be interpreted in the following order of
priority:
a. Contract Agreement
(4) Specifrcations
(5) Drawings
(8) PerformanceSecurity
C Other Documents
(l ) Construction Methods
(2) Construction Schedule in the form of PERT/CPM
Diagram or Precedence Diagram and Bar Chart with S-Curve.
(4) EquipmentUtilizationSchedule
3.2 This Contract shall be interpreted in accordance with the laws of the Republic of the
Philippines.
4. Communications
Communications between parties that are referred to in these Conditions of Contract
shall be effective only when in writing. A notice shall be effective only when it is
received by the concemed party.
5.2 If possession of a portion is not given by the date stated in SCC Clause 5.1, the
Procuring Entity will be deemed to have delayed the start of the relevant
activities. The resulting adjustments in contract time to address such delay shall
be in accordance with GCC Clause 46.
5.3 The Contractor shall bear all costs and charges for special or temporary right-ofway
required by it in connection with access to the Site. The Contractor shall also
provide at its own cost any additional facilities outside the Site required by it for
purposes of the Works.
5.4 The Contractor shall allow the Procuring Entity's Representative and any person
authorized by the Procuring Entity's Representative access to the Site and to
any place where work in connection with this Contract is being carried out or is
intended to be carried out.
5.5 The Procuring entity shall be responsible for obtaining the appropriate
Environmental Compliance Certificate (ECC) for the Project.
6 Contractor's Obligations
6.1 The Contractor shall carry out the Works properly and in accordance with this
Contract. The Contractor shall provide all supervision, labor, Materials, Plant and
Equipment, which may be required. All Materials and Plant on Site shall be
deemed to be the property ofthe Procuring Entity.
6.2 The Contractor shall commence execution of the Works on the Start Date and shall
carry out the Works in accordance with the approved PERT/CPM network
diagram submitted by the Contractor, as updated with the approval of the
Procuring Entity's Representative, and shall complete the Works by the
Intended Completion Date.
6.3 The Contractor shall be responsible for the safety ofall activities on the Site.
6.4 The Contractor shall cany out all instructions of the procuring Entity,s
Representative that comply with the applicable laws where the Site is located.
6.5 The Contractor shall employ the key personnel, named in the Schedule of Key
Personnel in the SCC, to carry out the supervision of the Works. The procuring
Entity will approve any proposed replacement of key personnel only if their
relevant qualifications and abilities are equal to or better than those of the
personnel listed in the Schedule.
6.6 If the Procuring Entity's Representative asks the Contractor to remove a member of
the Contractor's staff or work force, for justifiable cause, the Contractor shall
ensure that the person leaves the Site within seven (7) days and has no further
connection with the Work in this Contract.
6.7 During Contract implementation, the Contractor and its subcontractors shall abide
at all times by all labor laws, including child labor related enactments, and other
relevant rules.
6.8 The Contractor shall submit to the Procuring Entity for consent the name and
particulars of the person authorized to receive instructions on behalf of the
Contractor.
6.9 The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities, and the Procuring Entity during the dates given in the
schedule of other contractors particularly when they shall require access to the
Site. The Contractor shall also provide facilities and services for them during
this period. The Procuring Entity may modify the schedule of other contractors,
and shall notili/ the Contractor ofany such modification thereto.
7.2 The Performance Security posted in favor ofthe Procuring Entity shall be forfeited
in the event it is established that the Contractor is in default in anv of its
obligations under the Contract.
7.3 The Performance Security shall remain valid until issuance by the Procuring Entity of
the Certificate of Final Acceptance.
7.4 The Performance Security may be released by the Procuring Entity and retumed to
the Contractor after the issuance of the Certificate of Final Acceptance, subject
to the following conditions, provided that the Performance Security is replaced
by a Warranty Security against structural defects and./or failure as provided in
GCC Clause l2:
b. The Contractor has no pending claims for labor and materials filed
against it; and
7.7 Unless otherwise indicated in the SCC, the Contractor, by entering into
the Contract with the Procuring Entity, acknowledges the right ofthe Procuring
Entity to institute action pursuant to Act 3688 against any sub-contractors be
they an individual, firm, partnership, corporation, or association supplying the
Contractor with labor, materials and/or equipment for the performance of this
Contract.
8 Sub-Contracting
8.1 Unless otherwise provided in the SCC, sub-contracting of the Works shall be
subject to the provisions of DPWH Department Order (DO) No. 38, series of
2015 as provided below.
8.2 All sub-contracts shall be subject to prior approval of the appropriate official of the
Procuring Entity within the limits of his delegated authority.
8.3 The Contractor may sub-contract portions of the works to such an extent as may be
approved by the Procuring Entity and stated in the SCC, provided that the
Contractor shall directly undertake, using its own resources, not less than fifty
percent (50%) ofthe contract works in terms ofcost.
8.4. Each sub-contractor must comply with the eligibility criteria as specified in the
Eligibility Requirements (ER) for the portion of the contract works to be
subcontracted to that sub-contractor- e.g., applicable license from the
Philippine Constructors Accreditation Board, satisfactory completion of works
similar to the portion of the contract to be subcontracted and costing at least
fifty percent (50%) of the cost of such portion, and sufficient Net Financial
Contracting Capacity, as well as minimum equipment and manpower. This
requirement does not apply to labor pakyaw contracts.
8.5 The bidder/main contractor may identify the sub-contractors to whom portions of
the contract works will be sub-contracted at any stage ofthe bidding process or
during contract implementation, provided that any sub-contracting requires
prior approval of the Procuring Entity. Sub-contractors identified during the
bidding may be changed during the implementation of the contract, subject to
compliance with the eligibility requirements and the approval of the Procuring
Entity.
8.6 Sub-contracting of any portion olthe contract shall not relieve the main contractor
from any liability or obligation that may arise from the contract. The main
contractor shall be responsible for the acts, defaults, and negligence of any
subcontractor, its agents or workmen.
8.7 For any assignment and sub-contracting ofthe contract or any part thereof without
prior written approval by the concerned Head of the DPWH Procuring Entity,
the DPWH shall impose on the erring contractor, after the termination of the
contract, the penalty of suspension for one (l) year for the first offense, and
suspension of two (2) years for the second offense from participating in the
public bidding process, pursuant to the provision of Appendix l1 Section 4.2
of the IRR of RA 9184, in accordance with Section 69(6) of RA 9184 and
without prejudice to the imposition of additional administrative sanctions as
the intemal rules of the agency may provide and/or further criminal
prosecution as provided by applicable laws.
9. Liquidated Damages
9.1 The Contractor shall pay liquidated damages to the Procuring Entity for each day
that the Completion Date is later than the Intended Completion Date. The
applicable liquidated damages is at least one-tenth (1/10) of a percent ofthe cost
of the unperformed portion for every day ol delay. The total amount of
liquidated damages shall not exceed ten percent (10%) of the amount of the
contract. The Procuring Entity may deduct liquidated damages from payments
due to the Contractor. Payment of liquidated damages shall not affect the
Contractor. Once the cumulative amount of liquidated damages reaches ten
percent (10%) ofthe amount olthis Contract, the Procuring Entity shall rescind
this Contract, without prejudice to other courses of action and remedies open to
it.
9.2 If
the Intended completion Date is extended after liquidated damages have been
paid, the Engineer ofthe Procuring Entity shal correct any overpayment of liquidated damages
by the contractor by adjusting the next payment certificate. 10. Site Investigation
Reports
The Contractor, in preparing the Bid, shatl rely on any Site Investigation Reports referred
to in the SCC supplemented by any information obtained by the c;ntractor.
11. Licenses and Permits
The Procuring Entity shall, if requested by the Contractor, assist it in applying for
permits, licenses or approvals, which are required for the Works. These shall include
assistance to the contractor in securing necessary quarry permits, construction permits,
access to sites, among others, from the Local Govemment Units concemed.
12.2 The defects liability period for infrastructure projects shall be one year from
contract completion up to final acceptance by the Procuring Entity. During this
period, the Contractor shall start the repair works, at his own expense, of any
damage to the Works on account of the use of materials of inferior quality, and
shall complete the repair works within ninety (90) days lrom the time the Ho
PE has issued an order to undertake repair. In case of failure or refusal to comply with
this mandate, the Procuring Entity shall undertake such repair works and shall
be entitled to full reimbursement of expenses incurred therein upon demand.
12.3 Unless otherwise indicated in the SCC, in case the Contractor fails to comply with
the preceding paragraph, the Procuring Entity shall forfeit its performance
security, subject its properties to attachment or gamishment proceedings, and
perpetually disqualify it from participating in any pubtic bidding. All payables
of the GOP in his favor shall be offset to recover the costs.
12.4 After final acceptance of the Works by the Procuring Entity, the following shall be
held responsible for "Structural Defects", i.e., major faults/flaws/deficiencies in
one or more key structural elements of the project which may lead to structural
failure of the completed elements or structure, or "Structural Failures,"
i.e.,where one or more key structural elements in an infrastructure facility fails
or collapses, thereby rendering the facility or part thereof incapable of
withstanding the design loads, andior endangering the safety ofthe users or the
general public:
15.2 The CARI shall cover the value of the completed portions of the Works.
It shall not, however, cover any damage to the Works whose value is not more
than ten percent (10%) of the Total Contract Cost, as this is to be absorbed by
the Contractor. The CARI shall, therefore, start with nil at the beginning of
Contract execution. It shall then be increased over time as the Works progresses
so that at any time it covers the value of the portions of the Works actually
completed.
15.4 The Contractor shall notifu the insurer of changes in the nature, extent,
or program for the execution of the Works and ensure the adequacy of the
insurance at all times in accordance with the terms of this Contract and shall
produce to the Procuring Entity's Representative the insurance policy in force
including the receipts for payment of the current premiums.
15.5 If the Contractor fails to obtain and keep in force the insurance which it
is required to obtain under the terms of this Contract, the Procuring Entity may
obtain and keep in force any such insurance and pay such premiums as may be
necessary for the purpose. From time to time, the Procuring Entity may deduct
the amount it shall pay for said premiums including twenty five percent (250h)
therein from any monies due, or which may become due, to the Contractor,
without prejudice to the Procuring Entity exercising its right to impose other
sanctions against the Contractor pursuant to the provisions of this Contract.
15.6 In the event the Contractor fails to observe the above safeguards, the
Procuring Entity may, at the Contractor's expense, take whatever measure is
deemed necessary for its protection and that of the Contractor's personnel and
third parties, and/or order the intemrption of dangerous Works. In addition, the
Procuring Entity may refuse to make the payments under GCC Clause 4l until
the Contractor complies with this Clause.
15.7 The Contractor shall immediately replace the insurance policy obtained
as required in this Contract, without need of the Procuring Entity's demand,
with a new policy issued by a new insurance company acceptable to the
Procuring Entity for any ofthe lollowing grounds:
b. Reasonable grounds exist that the insurer may not be able, fully
and promptly, to fulfitt its obligation under the insurance policy.
a. Due to the Contractor's fault and while the Works are on-going,
it has incurred a negative slippage of fifteen percent (15%) or more in
accordance with Presidential Decree 1870; or
b. Due to the Contractor's fault and after the Contract time has
expired, it has incurred a negative slippage often percent (10%) or more
in the completion oithe Works; or
c The Contractor:
(3) does not actually have on the Site the minimum essential
equipment listed in the Bid necessary to prosecute the Works in
accordance with the approved PERT/CPM network diagram and
equipment utilization schedule as required under the Contract;
(4) does not execute the Works in accordance with this Contract or
persistently or flagrantly neglects to carry out its obligations under
this Contract;
(l) The Contractor stops work for twenty eight (28) days
when no stoppage of work is shown on the current Program of
Work and the stoppage has not been authorized by the Procuring
Entity's Representative.
16.2 When persons lrom the Procuring Entity gives notice of a fundamental
breach to the Procuring Entity's Representative in order to terminate the
existing contract for a cause other than those listed under GCC Clause 16.1-e,
the Procuring Entity's Representative shall decide whether the breach is
fundamental or not.
16-4 All materials on the Site, Plant, Equipment, and Works shall be deemed
to be the property ofthe Procuring Entity if this Contract is terminated because
of the Contractor's default.
17.2 When persons from the Contractor gives notice of a fundamental breach to the
Procuring Entity's Representative in order to terminate the existing conftact for
a cause other than those listed under GCC Clause I 7. l -b, the Procuring Entity's
Representative shall decide whether the breach is fundamental or not.
19.1 The following provisions shall govern the procedures for the termination of this
Contract:
19.2 Pursuant to Section 69(f.1 ofRA 9184 and without prejudice to the imposition of
additional administrative sanctions as the intemal rules of the agency may
provide and./or further criminal prosecution as provided by applicable laws, the
Procuring Entity shall impose on conffactors after the termination of the
contract the penalty of suspension for one (l) year for the first offense,
suspension for two (2) years for the second offense from participating in the
public bidding process, for violations committed during the contract
implementation stage, which include but not limited to the following:
(l) Employmentofcompetenttechnicalpersonnel,competent
engineers and/or work supervisors:
(1) Negative slippage of 15% and above within the critical path
of the project due entirely to the fault or negligence of the
contractor; and
20.1 For purposes of this Contract the terms 'force majeure" and "fortuitous event"
may be used interchangeably. In this regard, a fortuitous event or.force majeure
shall be interpreted to mean an event which the Contractor could not have
foreseen, or which though foreseen, was inevitable. It shall not include ordinary
unfavorable weather conditions, and any other cause the effects of which could
have been avoided with the exercise ofreasonable diligence by the Contractor.
20.4 After termination, the Contractor shall be entitled to payment of the unpaid
balance of the value of the Works executed and of the materials and Plant
reasonably delivered to the Site, adjusted by the following:
20.5 The net balance due shall be paid or repaid within a reasonable time period from the
date of the Notice oI Termination.
21.2lf the Contract is terminated for the Procuring Entity's convenience or because of
a fundamental breach of Contract by the Procuring Entity, the Procuring
Entity's Representative shall issue a certificate for the value of the work done,
materials ordered, the reasonable cost of removal of Contractor's equipment,
and the Contractor's costs of protecting and securing the Works, less advance
payments received up to the date of the certificate.
21.3 The net balance due shall be paid or repaid within twenty eight (28) days fiom the
notice of termination.
21.4 lf the Contractor has terminated the Contract under GCC Clause 17 or 18, the
Procuring Entity shall promptly retum the Performance Security to the
Contractor.
22. Resolution of Disputes
22.1 \f any dispute or difference of any kind whatsoever shall arise between the parties
in connection with the implementation of the contract covered by RA 91 84 and
its IRR, the parties shall make every effort to resolve amicably such dispute or
difference by mutual consultation.
22.3 Any and all disputes arising from the implementation of this Contract covered by
the RA 9184 and its IRR shall be submitted to arbitration in the Philippines
according to the provisions of RA 876, otherwise known as the "Arbitration
Law" and RA 9285, otherwise known as the "Alternative Dispute Resolution
Act of 2004. However, disputes that are within the competence of the
Construction Industry Arbitration Commission to resolve shall be refened
thereto. The process of arbitration shall be incorporated as a provision in this
Contract that will be executed pursuant to the provisions of RA 9184 and its
IRR. By mutual agreement, however, the pa(ies may agree in writing to resort
to other altemative modes of dispute resolution.
b. If the Contractor has not received sums due it for work already done
within forty five (45) days from the time the Contractor's claim for payment has
been certified by the Procuring Entity's Representative, the Contractor may
immediately issue a suspension of work notice in accordance with GCC Clause
44.
24. ProcuringEntity'sRepresentative'sDecisions
24.1 Except where otherwise specifically stated, the Procuring Entity's Representative
shall decide contractual matters between the Procuring Entity and the
Contractor in the role representing the Procuring Entity.
24.2 The Procuring Entity's Representative may delegate any of his duties and
responsibilities to other people, except to the Arbiter, after notifying the
Contractor, and may cancel any delegation after notifying the Contractor.
25. Approval of Drawings and Temporary Works by Procuring Entity's
Representative
25.1 All Drawings prepared by the Contractor for the execution of the Temporary
Works are subject to prior approval by the Procuring Entity's Representative
before their use.
25.2 The Contractor shall be responsible for the design of Temporary Works.
25.3 The Procuring Entity's Representative's approval shall not alter the Contractor,s
responsibility for the design olthe Temporary Works.
25.4 The Contractor shall obtain approval by third parties of the design of the Temporary
Works, when required by the Procuring Entity.
26.2 \f rhe confiactor's Financial Proposals for an acceleration are accepted by the
Procuring Entity, they are incorporated in the Contract price and treated as a
Variation.
27.2 The Procuring Entity's Representative shall decide whether and by how much to
extend the Intended Completion Date within twenty one (21) days of the
contractor asking the Procuring Entity's Representative for a decision thereto
after fully submitting all supporting information. If the contractor has failed to
give an early warning of a delay or has failed to cooperate in dealing with a
delay, the delay by this failure shall not be considered in assessing the new
Intended Completion Date.
28. Contractor's Right to Claim
If the Contractor incurs a cost as a result of any of the events under GCC Clause 13,
the Contractor shall be entitled to the amount of such cost. If as a result of any of the
said events, it is necessary to change the Works, this shall be dealt with as a Variation
Order.
29. Dayworks
29.1 Subject to GCC Clause 44 on Variation Orders, and if applicable as indicated in
the SCC, the Dayworks rates in the Contractor's Bid shatl be used for small
additional amounts of work only when the Procuring Entity's Representative
has given written instructions in advance for additional work to be paid for in
that way.
29.2 All work to be paid for as Dayworks shall be recorded by the Contractor on forms
approved by the Procuring Entity's Representative. Each completed form shall
be verified and signed by the Procuring Entity's Representative within two days
ofthe work being done.
29.3 The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks
forms.
30.2 The Contractor shall cooperate with the Procuring Entity's Representative in
making and considering proposals for how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the Work and in
carrying out any resulting instruction of the Procuring Entity's Representative.
31.3 The Contractor shall submit to the Procuring Entity's Representative for approval an
updated Program of Work at intervals no longer than the period stated in the
SCC. If the Con[actor does not submit an updated Program of Work within
this period, the Procuring Entity's Representative may withhold the amount
stated in the SCC from the next payment certificate and continue to withhold
this amount until the next payment after the date on which the overdue Program
of Work has been submitted.
31.4 The Procuring Entity's Representative's approval of the Program of Work shall
not alter the Contractor's obligations. The Contractor may revise the Program
of Work and submit it to the Procuring Entity's Representative again at any
time. A revised Program of Work shall show the effect of any approved
Variations.
31.5 When the Program of Work is updated, the Contractor shall provide the Procuring
Entity's Representative with an updated cash flow forecast. The cash flow
forecast shall include different currencies, as defined in the Contract, converted
as necessary using the Contract exchange rates.
31,6 All Variations shall be included in updated Program of Work produced by the
Contractor.
32. ManagementConferences
32.1 Either the Procuring Entity's Representative or the Contractor may require the
other to attend a Management Conference. The Management Conference shall
review the plans for remaining work and deal with matters raised in accordance
with the early waming procedure.
32.2 The Procuring Entity's Representative shall prepare the minutes of Management
conferences and provide copies of the minutes to those attending the
Conference. The responsibility of the parties for actions to be taken shall be
decided by the procuring Entity's Representative either at the Management
conference or after the Management conference and stated in writinf to all
who attended the Conference.
33.3 If the final quantity of any pay item accomplished differs from the original
quantity in the BOQ for that item and is not more than twenty five percent
(25%) of that original quantity, provided the aggregate changes for all work
items do not exceed ten percent (10%) of the Contract Price, the Procuring
Entity's Representative shall make the necessary adjustments to allow for the
changes, subject to applicable laws, rules, and regulations.
33.4 Ifrequested by the Procuring Entity's Representative, the Contractor shall provide
the Procuring Entity's Representative a detailed cost breakdown of any unit
price or rate in the BOQ.
34.2 lf the Procuring Entity's Representative instructs the Contractor to cary out a test
not specified in the Specifications to check whether any work has a defect and
the test shows that it does, the Contractor shall pay for the test and any samples.
Ifthere is no defect, the test shall be a Compensation Event.
34.3 The Contractor shall permit the Funding Source named in the SCC to inspect the
accounts and records of the Contractor relating to its performance and to have
them audited by auditors approved by the Funding Source, if so required by the
Funding Source.
37.2 Every time notice of a Defect is given, the Contractor shall correct the notified
defect within the length of time specified in the Procuring Entity's
Representative's notice.
37.3 The Contractor shall correct the Defects which it notices itself before the end ofthe
Defects Liability Period.
37.4 The Procuring Entity's Representative shall certify that all Defects have been
corrected. If the Procuring Entity's Representative considers that correction ofa
Defect is not essential, he can request the Contractor to submit a quotation for
the corresponding reduction in the Contract Price. If the Procuring Entity's
Representative accepts the quotation, the corresponding change shall be covered
by a Variation Order.
38. UncorrectedDefects
38.1 The Procuring Entity shall give the Contractor at least fourteen (14) days notice of
its inlention to use a third party to correct a Defect. If the Contractor itself does
not correct the Defect within that period, the Procuring Entity may have the
Defect corrected by the third party. The cost of the correction will be deducted
from the Contract Price.
38.2 The use of a third party to correct Defects that are unconected by the Contractor
shall in no way relieve the contractor of its liabilities and warranties under the
Contract.
39.2 The Advance Payment shall be made only upon the submission by the
Contractor to and acceptance by the Procuring Entity of an irrevocable standby
letter ofcredit of equivalent value from a commercial bank, a bank guarantee or
a surety bond callable upon demand, issued by a surety or insurance company
duly licensed by the Insurance Commission and confirmed by the Procuring
Entity.
39.4 The Contractor may reduce its standby letter of credit or guarantee
instrument by the amounts refunded by the Monthly Certificates in the advance
payment.
40. Monthly Statements or Progress Billings
40.1 The Contractor shall submit to the Procuring Entity's Representative, after the end
of each month, a Statement of Work Accomplished (SWA) or Progress Billing,
showing the amounts which the Contractor consider itself to be entitled up to
the end ofthe month, to cover:
40.2 Except as otherwise stipulated in the SCC, materials and equipment delivered on the
site but not completely put in place shall not be included for payment.
41.2 The Procuring Entity's Representative shall check the Contractor's monthly
statement and certifl, the amount to be paid to the Contractor.
41.4 The Procuring Entity's Representative may exclude any item certified in
a previous certificate or reduce the proportion ofany item previously certified in
any certificate in the light of later information.
41.5 The Procuring Entity's Representative shall deduct the following from
the certified gross amounts to be paid, resulting in the net amount payable to the
Contractor as Progress Payment:
41.6 The Procuring Entity shall pay the Contractor the said net amounts
certified by the Procuring Entity's Representative within twenty eight (28) days
from the date each certificate was issued. No payment of interest for delayed
payments and adjustments shall be made by the Procuring Entity.
41.7 The first progress payment may be paid by the Procuring Entity to the
Contractor provided that at least twenty percent (20%) of the work has been
accomplished as certified by the Procuring Entity's Representative.
41.8 Items of the Works for which a price of "0" (zero) has been entered will
not be paid for by the Procuring Entity and shall be deemed covered by other
rates and prices in the Contract.
41.9 The Procuring Entity shall pay the Contractor a cumulative gross
amount not exceeding ninety percent (90%) of the total Contract price, since the
remainder shall serve as the ten percent (10%) retention money, as provided in
GCC Clause 42.
42. Retention
42.1The Procuring Entity shall retain from each progress payment ten percent (10%) of
such payment, referred to as the "retention money." Such retention money shall
be based on the total amount due to the Contractor prior to any deduction and
shall be retained from every Progress Payment until fifty percent (50%) of the
value of the Works, as determined by the Procuring Entity, is completed. If,
after fifty percent (50%) completion, the Works are satisfactorily done and on
schedule, no additional retention shall be made; otherwise, the ten percent
(10%) retention shall again be imposed using the rate specified therefor.
42.2 The total retention money shall be due for release upon final acceptance of the
Works. The Contractor may, however, request the substitution of the retention
money for each progress billing with an irrevocable standby letter ofcredit from
a commercial bank, bank guarantee and/or surety bond callable on demand, of
amounts equivalent to the retention money substituted for and in a form
acceptable to the Procuring Entity. The Procuring Entity shall allow such
substitution provided that the Contract is on schedule and is satisfactorily
undertaken. The said inevocable standby letter ol credit, bank guarantee and/or
surety bond, to be posted in favor of the Procuring Entity, shatl be valid for a
duration to be determined by the Procuring Entity and shall answer for the
purpose for which the retention is intended, i.e., to cover uncorrected discovered
Defects and third party liabilities.
42.3 On completion of the whole Works, the Contractor may substitute retention money
with an "on demand" Bank guarantee in a form acceptable to the Procuring
Entity.
43 Variation Orders
43.1 Variation Orders (VOs) shall be subject to the provisions of Annex E of RA
9184lRR and DPWH DO 28, series of 2015. may be issued by the Procuring
Entity to cover any increase or decrease in quantities, including the introduction
of new work items not included in the original Contract or reclassification of
work items due to change of plans, design or alignment to suit actual field
conditions, resulting in disparity between the preconstruction plans used for
purposes ofbidding and the "as staked plans" or construction drawings prepared
after ajoint survey by the Contractor and the Procuring Entity after award ofthe
Contract. The cumulative amount of the positive or additive VOs, however,
shall not exceed ten percent (10%) ofthe original Contract cost. The addition or
deletion of works shall be within the general scope of the Contract as bid and
awarded. The scope ofthe Works shall not be reduced so as to accommodate a
positive VO.
43.2 A deductive VO may be allowed only if it would not significantly impair the
functionality ofthe original design, i.e., it must not reduce the size ofthe facility
by more than ten percent (10%) of the original scope (e.g., shortening of road
length) or must not make the facility unsafe (e.g., removal of guard rails) or
structurally unstable (e.g., removal of a column) or unusable (e.g., removal of a
bridge abutment).
43.3 A VO in the form of a Change Order may be issued by the Procuring Entity to
cover any increase or decrease in quantities of original Work items in the
Contract.
43.4 A VO in the form an Extra Work Order may be issued by the Procuring Entity to
cover the introduction of new work necessary for the completion, improvement
or protection of the project which were not included as items of work in the
original Contract, such as where there are subsurface or latent physical
conditions at the Site differing materially from those indicated in the Contract,
or where there are duly unknown physical conditions at the Site of an unusual
nature differing materially from those ordinarily encountered and generally
recognized as inherent in the Works or character provided for in the Contract.
43.5 Any cumulative positive VO beyond ten percent (10%) shall be the subject of
another contract to be bid out if the works are separable from the original
Contract.
43.6 In claiming for any VO, the Contractor shall, within seven (7) calendar days after
such work has been commenced or after the circumstances leading to such
condition(s) leading to the extra cost, and within twenty-eight (28) calendar
days deliver a written communication giving full and detailed particulars of any
extra cost in order that it may be investigated at that time. Failure to provide
either of such notices in the time stipulated shall constitute a waiver by the
contractor for any claim. The Contractor shall not "accumulate" claims for VOs
before submitting them to the Procuring Entity for investigation and processing.
b. In the absence of unit prices for the same items rates in this
Contract, at prices or rates obtained from those of similar or related
items in this Contract.
45 Suspension of Work
45.1 In accordance with DPWH Do 100, series of 2015, the procuring Entity, through its
Project Engineer/Engineer's Representative, shall have the authority to isiue a
Work Suspension Order to the Contractor suspend the work wholly or partly by
written order for such period as may be deemed necessary, o, of tna
following grounds: -y
a. Force majeure or any fortuitous event that has taken place, which
inflicts extensive damage and/or makes it difficult to proceed with the
work, such as a devastating earthquake or flood.
The Contractor shall immediately comply with such order to suspend the Works
wholly or partly.
45.2 The Contractor or its duly authorized representative shall have the right to suspend
work operation on any or all projects/activities along the critical path of
activities after fifteen (15) calendar days from date of receipt of written notice
from the Contractor to the district engineer/regional director/consultant or
equivalent official, as the case may be, on any ofthe following grounds:
46.1 Extension of the Contract Time shall be subject to the provisions of DPWH DO 100,
series of20l5 and the provisions of this GCC Clause 46.
46.2 Should the amount of additional work under an approved Variation Order or other
special circumstances of any kind whatsoever occur such as to fairly entitle the
Contractor to an extension of Contract Time, the Procuring Entity shall
determine the amount of such extension; provided that the Procuring Entity is
not bound to take into account any claim for an extension of time unless the
Contractor has, prior to the expiration of the Contract time and within thirty (30)
calendar days after such work has been commenced or after the circumstances
leading to such claim have arisen, delivered to the Procuring Entity notices in
order that it could have investigated them at that time. Failure to provide such
notice shall constitute
a waiver by the Contractor of any claim. Upon receipt of full and detailed
particulars, the Procuring Entity shall examine the facts and extent ofthe delay
and shall extend the Contract time to complete the contract work when, in the
Procuring Entity's opinion, the findings of facts justify an extension.
46.3 No extension of contract time shall be granted the Contractor due to (a) ordinary
unfavorable weather conditions and (b) inexcusable failure or negligence of
Contractor to provide the required equipment, supplies or materials.
46.4 Extension of contract time may be granted only when the affected activities fall
within the critical path of the PERTiCPM network.
46.5 No extension of contract time shall be granted when the reason given to support
the request for extension was already considered in the determination of the
original contract time during the conduct of detailed engineering and in the
preparation of the contract documents as agreed upon by the parties before
contract perfection.
46.6 Extension ofcontract time may be granted for any olthe following grounds:
c. Upon receipt of advice from the Contractor that the defects and
deficiencies indicated in the said Notice have been corrected, the HOPE
shall instruct the Inspectorate Team to conduct an inspection of the
project and to submit its Completion Inspection Report within seven (7)
days. If the report shows that the defects/deficiencies have been
satisfactorily corrected, the report is considered as the Final Completion
Inspection Report. Otherwise, the process is repeated until the noted
defects/deficiencies have been satisfactorily conected.
d. Upon the receipt ofthe Final Completion Inspection Report from
the Inspectorate Team, the HopE shall issue the Certificate of
Completion of the project, certifying that the Project has been
satisfactorily completed as of the date indicated in the Final Inspection
Report.
48.2 The Cerlificate of Acceptance shall be issued by the HoPE at the end of the
oneyear Defects Liability period, after all defects/deficiencies, if any, shall have
been repaired by the Contractor to the satisfaction of the same Inspectorate
Team of the Procuring Entity mentioned above and upon submission of the
Wananty Certificate by the Contractor in accordance with the provisions of
GCC Clause
12.The issuance of a Certificate of Acceptance shall be subject to the provisions
of DPWH DO 99, series of 2015.
d. Upon the receipt ofthe Final Acceptance Report, the Head ofthe
I0 shall issue the Certificate of Acceptance.
49. Taking Over
The Procuring Entity shall take over the Site and the Works within seven (7) days from
the date the Procuring Entity's Representative issues a Certificate ofAcceptance.
50.2 If the Contractor does not supply the said Drawings by the date stated in the SCC,
or if they do not receive the approval of the Procuring Entity's Representative,
the Procuring Entity's Representative shall withhold the amount stated in the
SCC from payments due to the Contractor.