Overall Project Timeline: Appraisal, Select and Define
Overall Project Timeline: Appraisal, Select and Define
Overall Project Timeline: Appraisal, Select and Define
Baseline Finish 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1
1
Overall project Timeline Tue 3/22/05
2190 days Thu 7/21/11
2
Appraisal, Select and Define 123 daysMon 7/25/05 Fri 7/8/11
3 Conceptual Review 37 days Wed 10/15/14 Tue 10/21/14
4 Conceptual/Design Finalization 70 days Sun 10/19/14 Tue 10/21/14
5 Conceptual Approval 23 days Thu 10/23/14 Sat 10/25/14
6
Engineering 134 daysThu 10/23/14 Mon 12/22/14
7 Civil Foundation 35 days Sat 11/1/14 Mon 11/17/14
8 Civil Structural ( outsourcing) 15 days Thu 12/11/14 Mon 12/22/14
9 Piping 7 days Tue 11/18/14 Mon 11/24/14
10 I&E 85 days Thu 10/23/14 Thu 12/11/14
11
Procurement 189 daysFri 10/31/14 Sat 3/14/15
12 Arrival /clearance of 3*HVAC Plants 16 days Thu 11/20/14 Thu 11/20/14
13 Arrival/clearance Cooling towers 15 days Sat 1/3/15 Sat 1/3/15
14 Arrival of Control Panel for HVAC Plant 12 days Mon 1/5/15 Mon 1/5/15
15 14 days
Procurement Of fork lifters, Valves, lift apparatus Fri 12/12/14 Thu 1/22/15
16 Procurement of Lithium 23 days Fri 10/31/14 Thu 11/13/14
17 Fabrication of Control Room 165 daysSat 11/1/14 Fri 12/12/14
18 Procurement of Power cables 34 days Fri 12/12/14 Thu 1/15/15
19 Procurement of Motors and Pumps, Vaccum38pumps days Mon 12/22/14 Sat 1/10/15
20 9 days Sun 12/14/14
Procurement of Glass for Glass work in the building Sun 12/21/14
21 Bidding Job award for Civil Job award 8 days Thu 11/20/14 Wed 11/26/14
22 Bidding Job award for HVAC equipment 8 days Wed 12/24/14 Tue 12/30/14
23 Bidding Job award for Cooling towers, pumps 8 days Sat 12/13/14
and motors Fri 12/19/14
24 Execute/Operate 1804 daysThu 11/20/14 Sat 3/14/15
25 Bidding Job Award and Construction 1795 daysThu 11/20/14 Sat 3/14/15
26 Area Leveling for new HVAC equipment 123 daysThu 11/20/14 Mon 12/22/14
27 Civil foundations for new HVAC equipment925 daysFri 12/19/14 Mon 1/12/15
28 Civil Works for Control Room 725 daysThu 12/25/14 Wed 1/14/15
29 Preparation of Cable duct at HVAC 156 Fri 12/5/14 Wed 1/7/15
Page 1
ID Task Name Duration Baseline Start Baseline Finish 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1
31 Civil Foundation for HVAC Shed beams 235 Wed 12/24/14 Fri 1/2/15
days
32 Civil Foundations for Building 325 Sat 11/22/14 Wed 11/26/14
Page 2